Common use of Extra Cost Clause in Contracts

Extra Cost. If the Contractor maintains that any instructions by drawings or otherwise involve extra cost to the Owner under this Contract, the Contractor shall give the Owner and the Engineer written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute any change except in emergency endangering life or property. The allowances to the Contractor shall then be as provided under Article 29 of the General Conditions. No claim for extra cost shall be valid unless so made.

Appears in 5 contracts

Samples: Macon Water Authority, Macon Water Authority, Macon Water Authority

AutoNDA by SimpleDocs

Extra Cost. If the Contractor maintains that any instructions by drawings or otherwise involve extra cost to the Owner under this Contract, the Contractor shall give General Conditions the Owner and the Engineer written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute any change except in emergency endangering life or property. The allowances to the Contractor shall then be as provided under Article 29 of the General Conditions. No claim for extra cost shall be valid unless so made.

Appears in 2 contracts

Samples: Macon Water Authority, Macon Water Authority

Extra Cost. If the Contractor maintains that any instructions by drawings or otherwise involve extra cost to the Owner under this Contract, the Contractor shall give the Owner and the Engineer written notice thereof within a reasonable time after the receipt of such General Conditions instructions, and in any event before proceeding to execute any change except in emergency endangering life or property. The allowances to the Contractor shall then be as provided under Article 29 of the General Conditions. No claim for extra cost shall be valid unless so made.

Appears in 1 contract

Samples: Contract Agreement

Extra Cost. If the Contractor maintains that any instructions by drawings or otherwise involve extra cost to the Owner under this Contract, the Contractor shall give the Owner and the Engineer written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute any change except in emergency endangering life or property. The allowances to the Contractor shall then be as provided under Article 29 of the General Conditions. No claim for extra cost shall be valid unless so made.. Section 00700-41 General Conditions

Appears in 1 contract

Samples: Contract Agreement

AutoNDA by SimpleDocs

Extra Cost. If the Contractor maintains that any instructions by drawings or otherwise involve extra cost to the Owner under this Contract, the Contractor he shall give the Owner and the Engineer Architect written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute any change except in emergency endangering life or of property. The allowances to the Contractor shall then be as provided under Article 29 of the General ConditionsGC-15. No claim for extra cost shall be valid unless so made.

Appears in 1 contract

Samples: pur.doas.ga.gov