Common use of Failure to Maintain Schedule Clause in Contracts

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- Dispute Resolution Procedure.

Appears in 4 contracts

Samples: Project Agreement, Project Agreement, Project Agreement

AutoNDA by SimpleDocs

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 - Dispute Resolution Procedure.

Appears in 4 contracts

Samples: Project Agreement, Project Agreement, Project Agreement

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner CHH or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a28.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 - Dispute Resolution Procedure.

Appears in 1 contract

Samples: Project Agreement

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner CMH or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a28.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 – Dispute Resolution Procedure.

Appears in 1 contract

Samples: Project Agreement

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner UOHI or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a28.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 - Dispute Resolution Procedure.

Appears in 1 contract

Samples: Project Agreement

AutoNDA by SimpleDocs

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner THP or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a28.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 - Dispute Resolution Procedure.

Appears in 1 contract

Samples: Project Agreement

Failure to Maintain Schedule. (a) If Project Co is not meeting the deadlines set out in the Construction Schedule consistent with its obligations under this Project Agreement, then at the written request of Owner STEGH or the Consultant, Project Co, and the Project Co Parties as required, shall promptly increase efforts on the Project, including the addition of more personnel to the Project during regular times and during periods of time for which overtime may be required, and if the delay is for any reason other than as described in Sections 22.1(a) and 27.1(a28.1(a), all expenses and costs incurred as a result shall be borne by Project Co. Any dispute between the parties as to whether Project Co is meeting the deadlines set out in the Construction Schedule shall be resolved in accordance with the provisions of Schedule 14- 14 - Dispute Resolution Procedure.

Appears in 1 contract

Samples: Project Agreement