Common use of Final Payment Certificate Clause in Contracts

Final Payment Certificate. 17.12.1 Within 30 (thirty) days after receipt of the Final Payment Statement under Clause 17.10, and the written discharge under Clause 17.11, and there being no disputed itemsof claim, the Authority Engineer shall deliver to the Authority, with a copy to the Contractor,a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority Engineer shall ascertain from the Authority all amounts previously paid by the Authority, all sums due to the Authority, and the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be. 17.12.2 The Authority shall, in accordance with the provisions of Clause 17.7, pay to the Contractor the amount which is specified as being finally due in the Final PaymentCertificate.

Appears in 4 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

AutoNDA by SimpleDocs

Final Payment Certificate. 17.12.1 Within 30 (thirty) days after receipt of the Final Payment Statement under Clause 17.10, and the written discharge under Clause 17.11, and there being no disputed itemsof items of claim, the Authority Engineer shall deliver to the Authority, with a copy to the Contractor,, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority Engineer shall ascertain from the Authority all amounts previously paid by the Authority, all sums due to the Authority, and the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be. 17.12.2 The Authority shall, in accordance with the provisions of Clause 17.7, pay to the Contractor the amount which is specified as being finally due in the Final PaymentCertificatePayment Certificate.

Appears in 2 contracts

Samples: Epc Agreement, Epc Agreement

AutoNDA by SimpleDocs

Final Payment Certificate. 17.12.1 Within 30 (thirty) days after receipt of the Final Payment Statement under Clause 17.10, and the written discharge under Clause 17.11, and there being no disputed itemsof items of claim, the Authority Authority’s Engineer shall deliver to the Authority, with a copy to the Contractor,, a final payment certificate (the “Final Payment Certificate”) stating the amount which, in the opinion of the Authority Authority’s Engineer, is finally due under this Agreement or otherwise. For the avoidance of doubt, before issuing the Final Payment Certificate, the Authority Authority’s Engineer shall ascertain from the Authority all amounts previously paid by the Authority, all sums due to the Authority, and the balance, if any, due from the Authority to the Contractor or from the Contractor to the Authority, as the case may be. 17.12.2 The Authority shall, in accordance with the provisions of Clause 17.7, pay to the Contractor the amount which is specified as being finally due in the Final PaymentCertificatePayment Certificate.

Appears in 2 contracts

Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement