Common use of Float Clause in Contracts

Float. All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 10 contracts

Samples: Comprehensive Development Agreement, Comprehensive Development Agreement, Comprehensive Development Agreement

AutoNDA by SimpleDocs

Float. All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 10 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 10 contracts

Samples: Development Agreement, Development Agreement, Comprehensive Development Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 5 contracts

Samples: Development Agreement, Development Agreement, Development Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 4 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, event and achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 3 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, event or to achieve schedule milestones, interim completion dates and/or or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 3 contracts

Samples: Design Build Agreement, Design Build Agreement, Design Build Agreement

Float. β€Œ All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, thereafter shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, event and achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification Identification of (or failure to identify) Float on the schedule shall be examined by IFA in determining whether to approve the Project Schedule. Once identified, Developer Design-Build Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 3 contracts

Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement

AutoNDA by SimpleDocs

Float. All Float contained in the Project Schedule, as shown in the initial Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, event and achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, or to achieve schedule milestones, interim completion dates and/or or Completion Deadlines. All Float shall be shown as such in the Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification of (or failure to identify) Float on the schedule in determining whether to approve the Project Schedule. Once identified, Developer DB Contractor shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 2 contracts

Samples: Design Build Agreement, Design Build Agreement

Float. All Float contained in the a Project Schedule, as shown in the initial Project Baseline Schedule initially approved or as generated thereafter, shall be considered a Project resource available to either Party party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines. All Float shall be shown as such in the relevant Project Schedule on each affected schedule path. TxDOT shall have the right to examine the identification Identification of (or failure to identify) Float on the schedule shall be examined by TxDOT in determining whether to approve the relevant Project Schedule. Once identified, Developer Integrator shall monitor, account for and maintain Float in accordance with critical path methodology.

Appears in 1 contract

Samples: And Maintenance Agreement

Float. All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as Parties, on an as-needed basis, to absorb delays caused by any event, achieve schedule Project Schedule milestones, interim completion dates dates, Substantial Completion by the Completion Deadline and/or Completion DeadlinesFinal Acceptance by the Acceptance Deadline. All Float shall be shown as such in the Project Schedule on each affected schedule pathProject Schedule submittal. TxDOT shall have the right to examine the identification Identification of (or failure to identify) Float on the schedule shall be evaluated by the Alamo RMA in determining whether to approve the Project Schedule. Once identified, Developer Float shall monitorbe monitored, account accounted for and maintain Float maintained in accordance with critical path methodology.

Appears in 1 contract

Samples: Development Agreement