For Installation Connected to CEB 22kV Feeders Sample Clauses

For Installation Connected to CEB 22kV Feeders. (2MW to 4MW)
AutoNDA by SimpleDocs
For Installation Connected to CEB 22kV Feeders. (1) CEB shall be responsible, at the cost and expense of the Seller, for the procurement, construction, installation, testing and commissioning of the 22kV Interconnection Line forming part of the CEB Interconnection Facilities as shown in Annexure D.3.

Related to For Installation Connected to CEB 22kV Feeders

  • No Installing Generator Not to install or keep or run any generator in the Said Apartment.

  • INSTALLATION AND REMOVAL Show Management reserves the right to fix the time for the installation of a booth prior to the Show opening and for its removal after the conclusion of the Show. Installation of all exhibits must be fully completed by the opening time of the exposition. Any space not claimed and occupied three hours prior to opening, may be resold or reassigned without refund. No exhibitor will be allowed to dismantle or repack any part of his exhibit until after the closing of the Show. 6.

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Teaching Staff Assigned to More Than One Building Each Educator who is assigned to more than one building will be evaluated by the appropriate administrator where the individual is assigned most of the time. The principal of each building in which the Educator serves must review and sign the evaluation, and may add written comments. In cases where there is no predominate assignment, the superintendent will determine who the primary evaluator will be.

  • DAMAGE TO COUNTY FACILITIES, BUILDINGS OR GROUNDS 8.16.1 The Contractor shall repair, or cause to be repaired, at its own cost, any and all damage to County facilities, buildings, or grounds caused by the Contractor or employees or agents of the Contractor. Such repairs shall be made immediately after the Contractor has become aware of such damage, but in no event later than thirty (30) days after the occurrence.

  • Compaction of surfaces 5 Compaction of ground surface under floors etc including scarifying for a depth of 150mm, breaking down oversize material, adding suitable material where necessary and compacting to 95% Mod AASHTO density. m2 96

  • Delivery & Installation a) Subject to the conditions of the contract, the delivery of the goods and completion of the related services shall be in accordance with the delivery and completion schedule specified in the bidding document. The details of supply/ shipping and other documents to be furnished by the successful/ selected bidder are specified in the bidding document and/ or contract.

  • MAINTENANCE OF THE SAID BUILDING / APARTMENT / PROJECT The Promoter shall be responsible to provide and maintain essential services in the Project till the taking over of the maintenance of the project by the association of the allottees. The cost of such maintenance has been included in the Total Price of the [Apartment/Plot]. [Insert any other clauses in relation to maintenance of project, infrastructure and equipment]

  • Equipment Installation In order to meet its obligations under this Agreement, a Party that owns, rents, or leases equipment (the equipment owner) may require installation of such equipment on property owned by another Party (the property owner), provided that the property is being used for an electric utility purpose and that the property owner shall not be required to do so if it would thereby be prevented from performing its own obligations or exercising its rights under this Agreement.

  • Utility Infrastructure During the term of this Agreement, Company will have the right to receive water, sanitary sewer, electric, storm drainage, telecommunication and data services at the Premises.

Time is Money Join Law Insider Premium to draft better contracts faster.