Force Majeure and Excusable Delay; Extension of Time of Performance Sample Clauses

Force Majeure and Excusable Delay; Extension of Time of Performance. In addition to the specific provisions of this Agreement, neither party shall be deemed to be in Default where delays in performance or failures to perform are due to, and a necessary outcome of, war, insurrection, strikes or other labor disturbances, walk-outs, riots, floods, earthquakes, fires, casualties, acts of God, restrictions imposed or mandated by other governmental entities (including new or supplemental environmental regulations), enactment of conflicting state or federal laws or regulations, judicial decisions, or similar basis for excusable performance which is not within the reasonable control of the party to be excused (collectively “Force Majeure”). Litigation attacking the validity of this Agreement or any of the Project Approvals, or any permit, ordinance, entitlement or other action of a governmental agency other than City necessary for the development of the Project pursuant to this Agreement, shall also be deemed to create an excusable delay as to Developer (collectively “Excusable Delay”). The party whose performance is prevented or delayed by such event of Force Majeure or Excusable Delay shall give prompt written notice thereof to the other party and both parties shall have agreed that performance is appropriately excused or delayed pursuant to this Section 10.01. In the event of Force Majeure or Excusable Delay, the parties shall memorialize in writing the extension of time for the performance of any obligation whose performance has been so prevented or delayed. The term of any such extension shall be equal to the period of the Excusable Delay or Force Majeure or such other period as may be mutually agreed upon by both parties.
AutoNDA by SimpleDocs

Related to Force Majeure and Excusable Delay; Extension of Time of Performance

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Excusable Delay The Contractor is entitled to an equitable adjustment of time, issued via Change Order, for delays caused by the following:

  • Unavoidable Delays Delays due to acts of God, acts of public agencies, labor disputes, strikes, fires, freight embargoes, inability (despite the exercise of due diligence) to obtain supplies, materials, fuels or permits, or other causes or contingencies (excluding financial inability) beyond the reasonable control of Landlord or Tenant, as applicable. Landlord shall use commercially reasonable efforts to provide Tenant with prompt notice of any Unavoidable Delays.

  • EXCUSE OF PERFORMANCE Seller shall not be liable for delays in performance or for non-performance due to failure or interruption of computer or telecommunication systems, acts of God, war, riot, fire, terrorism, labor trouble, unavailability of materials or components, explosion, accident, compliance with governmental requests, laws, regulations, orders or actions, or other unforeseen circumstances or causes beyond Seller's reasonable control. In the event of such delay, the time for performance or delivery shall be extended by a period of time reasonably necessary to overcome the effect of the delay.

  • Unavoidable Delay When construction is impeded as a result of strikes, lockouts, acts of God or other factors beyond the control, and ability to remedy, of the Developer.

  • Suspension of Performance Notwithstanding any other provision hereof, if an Event of Default or a Potential Event of Default has occurred and is continuing, the Non-Defaulting Party, upon written notice to the Defaulting Party, has the right (i) to suspend performance under any or all Transactions and (ii) to the extent an Event of Default has occurred and is continuing, to exercise any remedy available at law or in equity, except as limited be Section 5.7.

  • Term and Time of Performance The effective date of this Agreement shall begin on July 1, 2018 and will continue through June 30, 2023, subject to appropriation of funds, notwithstanding any other provision in this agreement.

  • Commencement of Performance This Agreement is of no force and effect until signed by both parties and all JBE-required approvals are secured. Any commencement of performance prior to Agreement approval shall be at Contractor's own risk.

  • Suspension of unsafe Construction Works (i) Upon recommendation of the Authority’s Engineer to this effect, the Authority may by notice require the Contractor to suspend forthwith the whole or any part of the Works if, in the reasonable opinion of the Authority’s Engineer, such work threatens the safety of the Users and pedestrians.

  • FORCE MAJEURE CLAUSE Contractor shall be excused from performance hereunder during the time and to the extent that it is prevented from obtaining delivery, or performing by act of God, fire, strike, loss, or shortage of transportation facilities, lock-out, commandeering of materials, product, plant, or facilities by the government, when satisfactory evidence thereof is presented to the District, provided that it is satisfactorily established that the non-performance is not due to the fault or neglect of Contractor.