Functions Variation Procedure. (a) The Authority’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering. (b) Within 7 days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the Authority’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee. (c) Each of the Authority’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that: (1) the Fee is adjusted as set out in the Independent Certifier’s notice; or (2) the adjustment (if any) to the Fee will be determined under Section 8.4.
Appears in 3 contracts
Samples: Independent Certifier Agreement, Independent Certifier Agreement, Independent Certifier Agreement
Functions Variation Procedure.
(a) The Authority’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering.
(b) Within 7 days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the Authority’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee.
(c) Each of the Authority’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that:that:
(1) the Fee is adjusted as set out in the Independent Certifier’s notice; or
(2) the adjustment (if any) to the Fee will be determined under Section 8.4.
Appears in 2 contracts
Samples: Independent Certifier Agreement, Independent Certifier Agreement
Functions Variation Procedure. (a) The the Authority’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering.
(b) Within 7 days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the Authority’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee.
(c) Each of the Authority’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that:
(1) the Fee is adjusted as set out in the Independent Certifier’s notice; or
(2) the adjustment (if any) to the Fee will be determined under Section 8.4.
Appears in 2 contracts
Samples: Independent Certifier Agreement, Independent Certifier Agreement
Functions Variation Procedure. (a) The Authority’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering.
(b) Within 7 days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the Authority’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee.
(c) Each of the Authority’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that:
(1) the Fee is adjusted as set out in the Independent Certifier’s notice; or
(2) the adjustment (if any) to the Fee will be determined under Section 8.48.4 [Cost of Functions Variation].
Appears in 1 contract
Samples: Independent Certifier Agreement
Functions Variation Procedure.
(a) The the Authority’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering.
(b) Within 7 days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the Authority’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee.
(c) Each of the Authority’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that:that:
(1) the Fee is adjusted as set out in the Independent Certifier’s notice; or
(2) the adjustment (if any) to the Fee will be determined under Section 8.49.4.
Appears in 1 contract
Samples: Independent Certifier Agreement
Functions Variation Procedure. (a) The AuthorityProvince’s and Project Co’s Design and Construction Representatives may jointly issue a document titled “Functions Variation Price Request” to the Independent Certifier which will set out details of a proposed Functions Variation which the PA Parties are considering.
(b) Within 7 seven days after the receipt of a “Functions Variation Price Request”, the Independent Certifier will provide each of the AuthorityProvince’s and Project Co’s Design and Construction Representatives with a written notice in which the Independent Certifier sets out the effect which the proposed Functions Variation will have on the Fee.
(c) Each of the AuthorityProvince’s and Project Co’s Design and Construction Representatives may then jointly direct the Independent Certifier to carry out a Functions Variation by written document titled “Functions Variation Order” which will state either that:
(1) the Fee is adjusted as set out in the Independent Certifier’s notice; or
(2) the adjustment (if any) to the Fee will be determined under Section 8.4.
Appears in 1 contract