Common use of Hydrostatic Testing of Water Mains Clause in Contracts

Hydrostatic Testing of Water Mains. 1. When the Utility Owner and GDOT Project Manager approve a section of pipe for testing, the Contractor shall furnish the materials, equipment, and labor to conduct the pressure and leakage tests. Use a test pump, pressure gauge, and a means of measuring the water necessary to maintain the required pressure during the prescribed testing time. All pressure and leakage testing shall be done in the presence of the Utility Owner and GDOT Project Coordinators as a condition precedent to the approval and acceptance of the system. All pipes shall have been thoroughly flushed prior to testing. Simultaneous or separate pressure and leakage tests may be performed.

Appears in 4 contracts

Samples: Utility Agreement Contract Item Agreement, Advertised Contract, Advertised Contract

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.