Installation and Commissioning. 9.1 The Buyer is responsible for the installation of the Equipment. The installation will be performed by the Buyer in accordance with the guidelines and procedures of the Supplier. 9.2 Following installation, if so contractually agreed, the Equipment shall be checked and started up in accordance with the Supplier’s guidelines and procedures (“Commissioning”). Commissioning does not construe responsibility to the Supplier for the defects of the installation performed by the Buyer. The Supplier reserves the right to stop, re-start and re-perform the Commissioning. In no case will the Buyer commence or carry out the Commissioning without the involvement of the Supplier as contractually agreed. 9.3 If services outside the Supply under the Contract are required, or if the Services supplied under the Contract are performed outside Normal Working Time, the Supplier is entitled to charge the Buyer in accordance with the Supplier’s price list in force at the time of their performance. If Commissioning has not started within eighteen (18) months after Delivery due to reasons attributable to the Buyer, any claims of the Buyer against the Supplier in this respect will be deemed to be waived and absolutely time barred upon the expiry of nineteen
Appears in 3 contracts
Samples: General Terms and Conditions of Contract, General Terms and Conditions of Contract, General Terms and Conditions of Contract
Installation and Commissioning. 9.1 The Buyer is responsible for the installation of the Equipment. The installation will be performed by the Buyer in accordance with the guidelines and procedures of the Supplier.
9.2 Following installation, if so contractually agreed, the Equipment shall be checked and started up in accordance with the Supplier’s guidelines and procedures (“Commissioning”). Commissioning does not construe responsibility to the Supplier for the defects of the installation performed by the Buyer. The Supplier reserves the right to stop, re-start and re-perform the Commissioning. In no case will the Buyer commence or carry out the Commissioning without the involvement of the Supplier as contractually agreed.
9.3 If services outside the Supply under the Contract are required, or if the Services supplied under the Contract are performed outside Normal Working Time, the Supplier is entitled to charge the Buyer in accordance with the Supplier’s price list in force at the time of their performance. If Commissioning has not started within eighteen (18) months after Delivery due to reasons attributable to the Buyer, any claims of the Buyer against the Supplier in this respect will be deemed to be waived and absolutely time barred upon the expiry of nineteeneighteen