Installation Scheduling Permits. If the period of time for the Participating Cities to issue Installation Scheduling Permits exceeds, on average, 7 days after final submission of the required materials by Operator, or if more than 25% of the Installation Scheduling Permits are issued 14 days or longer after final submission of the required materials, other than on account of errors or omissions by Operator or valid reasons for denial, then the Agreed Completion Dates shall be extended to reflect any reasonably necessary additional period required by Operator to complete the Phases.