Interconnection Customer Compensation. If Transmission Provider requests or directs Interconnection Customer to provide a service pursuant to Article 13.5.1 of this SGIA, Transmission Provider shall compensate Interconnection Customer in accordance with Interconnection Customer's applicable Commission-approved rate schedule in effect. Interconnection Customer shall serve Transmission Provider with any filing of a proposed rate schedule at the time of such filing with the Commission. To the extent that no rate schedule is in effect at the time the Interconnection Customer is required to provide or absorb any reactive power under this SGIA, Transmission Provider agrees to compensate Interconnection Customer in such amount as would have been due Interconnection Customer had the rate schedule been in effect at the time service commenced; provided, however, that such rate schedule must be filed at the Commission or other appropriate Governmental Authority within sixty (60) Calendar Days of the commencement of service.
Appears in 3 contracts
Samples: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)
Interconnection Customer Compensation. If Transmission Provider requests or directs Interconnection Customer to provide a service pursuant to Article 13.5.1 of this SGIA, Transmission Provider shall compensate Interconnection Customer in accordance with Interconnection Customer's applicable Commission-approved rate schedule in effect. Interconnection Customer shall serve Transmission Provider with any filing of a proposed rate schedule at the time of such filing with the Commission. To the extent that no rate schedule is in effect at the time the Interconnection Customer is required to provide or absorb any reactive power under this SGIA, Transmission Provider agrees to compensate Interconnection Customer in such amount as would have been due Interconnection Customer had the rate schedule been in effect at the time service commenced; provided, however, that such rate schedule must be filed at the Commission or other appropriate Governmental Authority within sixty (60) Calendar Days of the commencement of service.sixty
Appears in 2 contracts
Samples: Standard Generator Interconnection Agreement (Sgia), Standard Generator Interconnection Agreement (Sgia)