Interim Design Submissions. Design-Builder shall submit to Owner interim design submissions for the Work at forty percent (40%), sixty-five percent (65%), and one hundred percent (100%) design completion. On or about the time of the scheduled design submissions, Design-Builder and Owner shall meet and confer about the submissions, with Design-Builder identifying during such meetings, among other things, the evolution of the design and any significant changes or deviations from the Contract Documents, or, if applicable, previously submitted design submissions. Minutes of the meetings will be maintained by Design-Builder and provided to all attendees for review. Following the design review meeting, Owner shall review and approve the interim design submissions in a time that is consistent with the turnaround times agreed upon by the Parties and set forth in the Project Schedule.
Appears in 4 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Interim Design Submissions. Design-Builder shall submit to Owner interim design submissions for the Work at forty percent thirty-five (4035%), sixtyfifty percent (50%), ninety-five percent (6595%), ) and one hundred percent (100%) design completion. On or about the time of the scheduled design submissions, Design-Builder and Owner shall meet and confer about the submissions, with Design-Builder identifying during such meetings, among other things, the evolution of the design and any significant changes or deviations from the Contract Documents, or, if applicable, previously submitted design submissions. Minutes of the meetings will be maintained by Design-Builder and provided to all attendees for review. Following the design review meeting, Owner shall review and approve the interim design submissions in a time that is consistent with the turnaround times agreed upon by the Parties and set forth in the Project Schedule.
Appears in 1 contract
Samples: Design Build Contract
Interim Design Submissions. Design-Builder shall submit to Owner interim design submissions for the Work at forty percent (40%), sixty-five seventy percent (6570%), and one hundred percent (100%) design completion. On or about the time of the scheduled design submissions, Design-Builder and Owner shall meet and confer about the submissions, with Design-Builder identifying during such meetings, among other things, the evolution of the design and any significant changes or deviations from the Contract Documents, or, if applicable, previously submitted design submissions. Minutes of the meetings will be maintained by Design-Builder and provided to all attendees for review. Following the design review meeting, Owner shall review and approve the interim design submissions in a time that is consistent with the turnaround times agreed upon by the Parties and set forth in the Project Schedule.design
Appears in 1 contract
Samples: Design Build Contract
Interim Design Submissions. Design-Builder shall submit to Owner interim design submissions for the Work at forty percent (40%), sixty-five fiveseventy percent (656570%), and one hundred percent (100%) design completion. On or about the time of the scheduled design submissions, Design-Builder and Owner shall meet and confer about the submissions, with Design-Builder identifying during such meetings, among other things, the evolution of the design and any significant changes or deviations from the Contract Documents, or, if applicable, previously submitted design submissions. Minutes of the meetings will be maintained by Design-Builder and provided to all attendees for review. Following the design review meeting, Owner shall review and approve the interim design submissions in a time that is consistent with the turnaround times agreed upon by the Parties and set forth in the Project Schedule.
Appears in 1 contract
Samples: Design Build Contract