Liquidated Damages for delay, Error or Variation. In case of delay, error or variation in completion of the work as specified in the delivery schedule, the consultant shall be liable to pay liquidated damages not exceeding an amount equal to 0.5% (zero point five percent) of the total value of the contract per day, subject to a maximum of 5% (five percent) of the total value of the contract. AERA will take into consideration the reasons for delay, error or variation, if any, while imposing liquidated damages on the selected applicant. However, in the event of delay, error or variation caused due to reasons beyond the control of the Consultant, AERA may, in its sole discretion, consider granting of appropriate extension of time, without imposition of liquidate damages.