Meeting with Transmission Provider. Transmission Provider shall use Reasonable Efforts to meet with Interconnection Customer within ten (10) Business Days of providing an Interconnection System Impact Study report to Interconnection Customer to discuss the results of the Interconnection System Impact Study.
Appears in 5 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Meeting with Transmission Provider. Transmission Provider shall use Reasonable Efforts to meet with Interconnection Customer within ten (10) Business Days of providing an a draft Interconnection System Impact Facilities Study report to Interconnection Customer to discuss the results of the Interconnection System Impact Facilities Study.
Appears in 4 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Meeting with Transmission Provider. Transmission Provider shall use Reasonable Efforts to meet with Interconnection Customer within ten (10) Business Days of providing an a draft Interconnection System Impact Facilities Study report to Interconnection Customer to discuss the results of the Interconnection System Impact Facilities Study.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)
Meeting with Transmission Provider. Transmission Provider shall use Reasonable Efforts to meet with Interconnection Customer within ten (10) Business Days of providing an Interconnection System Impact Study report to Interconnection Customer to discuss the results of the Interconnection System Impact Study.
Appears in 1 contract
Samples: Standard Large Generator Interconnection Agreement (Lgia)