Meeting with Transmission Provider. Within fourteen (14) Calendar Days of providing a draft Interconnection System Impact Study report to Interconnection Customer, Transmission Provider shall schedule a meeting with Interconnection Customer at a mutually agreeable date to discuss the results of the draft Interconnection System Impact Study. Within thirty (30) Calendar Days after this meeting, Transmission Provider shall tender the final Interconnection System Impact Study report, unless further study is required.
Appears in 4 contracts
Samples: Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia), Generator Interconnection Agreement (Gia)