Metering Commissioning Tests. (A) Metering Commissioning Tests must be performed on site. (B) For each Metering Commissioning Test, a Metering Equipment Commissioning Record in the form set out at Appendix 1 must be completed. (C) The results of such tests shall be used to confirm and record, so far as appropriate, that: (i) the current transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow; (ii) the voltage transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow; (iii) the relationships between voltages and currents are of the correct phase sequence and that phase rotation is standard at the Meter terminals; (iv) the burdens on the Measurement Transformers are within the normal operating range of the Measurement Transformers; (v) the Meters are set to the same current transformer and voltage transformer ratios as the installed Measurement Transformers; (vi) the output of the Metering System correctly records the electricity in the primary system; and (vii) the Metering Equipment detects phase failure and operates the necessary alarms.
Appears in 7 contracts
Samples: Private Network CFD Agreement, Private Network CFD Agreement, Private Network CFD Agreement
Metering Commissioning Tests. (A) Metering Commissioning Tests must be performed on site.
(B) For each Metering Commissioning Test, a Metering Equipment Commissioning Record in the form set out at Appendix 1Appendix 1 must be completed.
(C) The results of such tests shall be used to confirm and record, so far as appropriate, that:
(i) the current transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow;
(ii) the voltage transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow;
(iii) the relationships between voltages and currents are of the correct phase sequence and that phase rotation is standard at the Meter terminals;
(iv) the burdens on the Measurement Transformers are within the normal operating range of the Measurement Transformers;
(v) the Meters are set to the same current transformer and voltage transformer ratios as the installed Measurement Transformers;
(vi) the output of the Metering System correctly records the electricity in the primary system; and
(vii) the Metering Equipment detects phase failure and operates the necessary alarms.
Appears in 1 contract
Samples: Private Network CFD Agreement
Metering Commissioning Tests. (A) 6.2.1 Metering Commissioning Tests must be performed on site.
(B) 6.2.2 For each Metering Commissioning Test, a Metering Equipment Commissioning Record in the form set out at Appendix 1 must be completed.
(C) 6.2.3 The results of such tests shall be used to confirm and record, so far as appropriate, that:
(ia) the current transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow;
(iib) the voltage transformers are of the ratio specified in the Key Meter Technical Details, have the correct polarity and are correctly located to record the required power flow;
(iiic) the relationships between voltages and currents are of the correct phase sequence and that phase rotation is standard at the Meter terminals;
(ivd) the burdens on the Measurement Transformers are within the normal operating range of the Measurement Transformers;
(ve) the Meters are set to the same current transformer and voltage transformer ratios as the installed Measurement Transformers;
(vif) the output of the Metering System correctly records the electricity in the primary system; and
(viig) the Metering Equipment detects phase failure and operates the necessary alarms.