Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time. 7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point. 7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations. 7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 12 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD WPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD WPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPDWPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD WPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 8 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval (two meters, each with separate CT, PT) are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI Buyer shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/regulations of the State regulationswhere the Project is located.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval (two meters, each with separate CT, PT) are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 4 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/regulations of the State regulationswhere the Project is located.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval (two meters, each with separate CT, PT) are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main main & Check check meters at the Delivery Interconnection Point, along with Standstand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point Interconnection Point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Interconnection Point as described in clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI UPPCL shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & and Check meters at the Delivery Point, along with Standstand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause Article 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall the Buyershall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the SPD and SECI shall follow and be bound by the Central Electricity Authority RERC metering guidelines 2007 (Installation amended time to time) and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The SPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at SPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the SPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in clause 7.1.3.