Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time. 7.1.2 The RPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD ’s side of Delivery Point. 7.1.3 In addition to ensuring compliance of the applicable codes, the RPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations. 7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article 7.1.3.
Appears in 5 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article 7.1.3.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article Clause 7.1.3.
Appears in 3 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals (two meters, each with separate CT, PT) are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 2 contracts
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI Buyer shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/regulations of the State regulationswhere the Project is located.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals are also to be set up at pooling substation for individual projects to segregate multiple Projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 2 contracts
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI RUVNL shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD WPD and SECI Buyer shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD WPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD WPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD WPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals are also to be set up at pooling substation for individual projects to segregate multiple Projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI CESC shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD HPD and SECI the Buyer shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD HPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD HPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD HPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD OWPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD OWPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD OWPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD OWPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals approval are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD WPD and SECI Buyer shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD WPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD WPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD WPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/regulations of the State regulationswhere the Project is located.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals are also to be set up at pooling substation for individual projects to segregate multiple Projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD RPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement
Meters. 7.1.1 For installation of Meters, Meter testing, Meter calibration and Meter reading and all matters incidental thereto, the RPD WPD and SECI shall follow and be bound by the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006, the Grid Code, as amended and revised from time to time.
7.1.2 The RPD WPD shall bear all costs pertaining to installation, testing, calibration, maintenance, renewal and repair of meters at RPD WPD’s side of Delivery Point.
7.1.3 In addition to ensuring compliance of the applicable codes, the RPD WPD shall install Main & Check meters at the Delivery Point, along with Stand-by meter(s) as per the applicable Central/State regulations.
7.1.4 In case of pooling of multiple Projects, power from multiple Projects can be pooled at a Pooling Substation prior to the Delivery point and the combined power can be fed at Delivery point through a common transmission line from the Pooling Substation. In such cases, ABT compliant sub-meters as per relevant regulation/approvals (two meters, each with separate CT, PT) are also to be set up at pooling substation for individual projects in addition to the meters at Delivery Point as described in Article clause 7.1.3.
Appears in 1 contract
Samples: Power Purchase Agreement