Milestone Due Dates; Liquidated Damages Sample Clauses

Milestone Due Dates; Liquidated Damages. The Contractor’s obligations pursuant to this Contract shall be performed in accordance with the Milestone Due Dates. It is mutually understood and agreed by and between the Parties that time is of the essence with respect to completion of each of the Milestones on or before its respective Milestone Due Date and that in case of any failure on the part of Contractor to complete the such Milestones within the time specified in the Milestone Due Dates, Authority will be damaged thereby and will be entitled to Performance Deficiency Charges. The amount of said Performance Deficiency Charges, being difficult if not impossible of definite ascertainment and proof, are acknowledged to be liquidated damages and not a penalty.
AutoNDA by SimpleDocs

Related to Milestone Due Dates; Liquidated Damages

  • Delay Liquidated Damages Delay Liquidated Damages has the meaning set out in GC 7.6.1.

  • Payment of Liquidated Damages If you supply all or some of your milk to a third party during a Month you must, if required by DFMC, immediately pay to DFMC liquidated damages for that Month calculated as follows: $X = W cents x (Y – Z) Where: $X is the amount payable by you to DFMC for the relevant Month. If $X is a negative amount, no amount is payable by you. Y is the average monthly litres you have supplied to DFMC based on the 12 months immediately preceding the relevant Month (or in the event you have not supplied DFMC for 12 months, the average monthly litres you have supplied to DFMC during the period you have supplied DFMC). Z is the number of litres supplied to DFMC by you for the relevant Month.

  • CONTRACT TIME AND LIQUIDATED DAMAGES (7-1-95) (Rev. 12-18-07) 108 SP1 G10 A The date of availability for this contract is April 25, 2016. The completion date for this contract is October 15, 2017. Except where otherwise provided by the contract, observation periods required by the contract will not be a part of the work to be completed by the completion date and/or intermediate contract times stated in the contract. The acceptable completion of the observation periods that extend beyond the final completion date shall be a part of the work covered by the performance and payment bonds. The liquidated damages for this contract are Two Thousand Dollars ($ 2,000.00) per calendar day.

  • Liquidated Damages The Company’s obligations to pay any partial liquidated damages or other amounts owing under the Transaction Documents is a continuing obligation of the Company and shall not terminate until all unpaid partial liquidated damages and other amounts have been paid notwithstanding the fact that the instrument or security pursuant to which such partial liquidated damages or other amounts are due and payable shall have been canceled.

  • Milestone Event Milestone Payment [***] [***]

  • Milestone Fees Licensee will pay Milestone Fees indicated in Section 3.1(b) of the Patent & Technology License Agreement by the Quarterly Payment Deadline for the Contract Quarter in which the milestone events set forth in Section 3.1(b) of the Patent & Technology License Agreement are achieved.

  • Notice of Liquidated Damages System Agency will formally notify Grantee in writing when liquidated damages action is imposed, stating the nature of the action, the reasons for imposing, and the method of appealing. Grantee must submit a written appeal, within ten (10) calendar days of receipt of the notice, to the SUD email box, XxxxxxxxxXxxxx.Xxxxxxxxx@xxxx.xxxxx.xx.xx.

  • Milestone Payment The first time Net Sales in the Territory in a Royalty Period exceed US$[***] ([***] dollars) US$[***] ([***] dollars)

  • Sales Milestone Payments Artiva shall make the following one-time, non-refundable and non-creditable sales milestone payments to GCLC when the aggregate annual Net Sales of Products in the Territory first reach the thresholds specified below. Artiva shall notify GCLC promptly of the achievement of each such sales threshold. Each sales milestone payment shall be made by Artiva within [***] days after the end of the calendar quarter in which such sales threshold is achieved. To the extent more than one sales threshold is reached in any given calendar year, then the applicable milestone payment for each such achievement shall be due and owing with respect to such calendar year. For clarification, the total milestone payments payable hereunder if all milestone events are achieved is [***].

  • Liquidated Damages for Delay In addition to the Contractor bearing the actual cost of correcting any non-compliant work or any other actual damages resulting from Contractor’s breach of this Agreement, the Contractor agrees to pay the Contractor delay damages in the amount of $500.00 per day for every day that the goods and/or services to be provided pursuant to this Agreement have not been timely delivered to the District in compliance with the Scope of Services set forth above, unless the delay has been properly excused by the terms of this Agreement. The parties agree that the District’s actual damages for delay are difficult to estimate and that this $500.00 per day sum is a reasonable pre-estimate of the District’s actual damages for each day of delay and that the is $500.00 per day sum is intended by the parties to be in the nature of liquidated damages, not a penalty. It is not the parties’ intent for this provision to limit either party’s remedies against the other for the breach of this Agreement, except for the District’s money damages for unexcused delays caused by the Contractor.