Milestones for Limited Operations Work Milestone Date Responsible Party 115 Sample Clauses

Milestones for Limited Operations Work Milestone Date Responsible Party 115 kV Metering 1 Fully Executed Interconnection Agreement Completed Connecting Transmission Owner & Developer 2 Notice to Proceed Oct-2016 Developer Milestone Date Responsible Party 3 Request for drawings and documentation Oct-2016 Developer 5 Issue Unit 4 metering drawings & documentation of existing installation Oct-2016 Connecting Transmission Owner 8 Test Unit 4 metering set-up (confirm point to points) Dec-2016 Developer 9 Issue metering transformer test results Dec-2016 Developer 10 Perform functional test and review of existing metering system to determine required repairs/upgrades Jan-2017 Connecting Transmission Owner 11 Issue metering deficiency report to Customer/Developer Jan-2017 Connecting Transmission Owner 12 Install equipment replacements, repairs and upgrades Feb-2016 Developer 13 Functional witness testing of the completed installation Feb-2017 Developer 15 Initial Synchronization Date Feb-2017 Developer 34.5 kV Reverse Power Relaying 1 Fully Executed Interconnection Agreement Completed Connecting Transmission Owner & Developer 2 Notice to Proceed Oct-2016 Developer 3 Authorization to use P14-73 PTs in the 34.5 kV yard Oct-2016 Connecting Transmission Owner 4 Request for drawings and documentation Oct-2016 Developer 5 Issue all required drawings and documentation of the existing installation Oct-2016 Connecting Transmission Owner 6 Conceptual package delivered to CTO Nov-2016 Developer Milestone Date Responsible Party 7 Conceptual package review completed Nov-2016 Connecting Transmission Owner 8 Equipment Procurement Started Nov-2016 Developer 9 ES4/S1 Relay Upgrade Package – delivered to CTO Dec-2016 Developer 10 ES4/S1 Relay Upgrade Package – review completed Dec-2016 Connecting Transmission Owner 11 Mobilize and start construction Dec-2016 Developer 12 Issue relay settings to CTO for review Jan-2017 Developer 13 Settings review completed Jan-2017 Connecting Transmission Owner 14 Installation completed Feb-2017 Developer 16 Witness testing completed Feb-2017 Connecting Transmission Owner 17 Both ES4 & S1 re-energized Feb-2017 Developer 18 Commercial Operation Date Feb-2017 Developer 19 As-built drawings submitted for review Mar-2017 Developer 20 As-built drawings review completed Apr-2017 Connecting Transmission Owner 21 Close-out package issued May-2017 Developer APPENDIX D SECURITY ARRANGEMENTS DETAILS
AutoNDA by SimpleDocs

Related to Milestones for Limited Operations Work Milestone Date Responsible Party 115

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones:

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving the following development milestones in its diligence activities under this AGREEMENT: (a) (b).

  • Milestone schedule Please state the status and progress of each Milestone and identify any completed Milestone(s) for the previous calendar quarter.

  • Project/Milestones Taxpayer develops and manufactures various products for use in the defense, aerospace and security industries. In consideration for the Credit, Taxpayer agrees to expand its operations at various locations throughout California, including El Segundo, Redondo Beach, Palmdale, Sunnyvale, Woodland Hills, Azusa and Rancho Xxxxxxxx. As part of its expansion, Taxpayer will invest in manufacturing equipment, computer and electrical equipment and make tenant improvements to the above facilities. Additionally, Taxpayer will hire full-time employees as part of its expansion (collectively, the “Project”). Further, Taxpayer agrees to satisfy the milestones as described in Exhibit “A” (“Milestones”) and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of Full- time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” Taxpayer may use the salaries of any of the Full-time employees hired and retained within the required time period. For purposes of calculating the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” the salary of any full-time employee that is not employed by the taxpayer for the entire taxable year shall be annualized. In addition, Xxxxxxxx agrees that any full-time employee hired after the effective date of this agreement that is a “qualified full-time employee” (as defined in RTC section 23636) shall be excluded from the calculation of the net increase of full-time employees required by this Agreement if Taxpayer claims the credit allowed by RTC section 23636.

  • TASK 1 GENERAL PROJECT TASKS PRODUCTS

  • Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.

  • PROJECT MILESTONES, REPORTING AND PAYMENTS 15. The milestones for the projects, their relationship to the outputs, expected completion dates, relevant reporting dates and expected payments to be made are set out in bilateral schedules to this Agreement. The Commonwealth will make payments subject to the performance reports demonstrating the relevant milestone has been met.

  • Table 7b - Other milestones and targets Reference Number Select stage of the lifecycle Please select target type from the drop-down menu Description (500 characters maximum) Is this a collaborative target? Baseline year Baseline data Yearly milestones (numeric where possible, however you may use text) Commentary on your milestones/targets or textual description where numerical description is not appropriate (500 characters maximum)

  • Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Development Schedule The Project shall substantially comply with the specific timetables and triggers for action set forth in Article 5 of this Agreement. The parties acknowledge that, as provided in G.S. 160A-400.25(b), the failure to meet a commencement or completion date shall not, in and of itself, constitute a material breach of this Agreement pursuant to G.S. 160A-400.27 but must be judged based upon the totality of the circumstances.