Milestones Milestone Date Responsible Party Sample Clauses

Milestones Milestone Date Responsible Party. 1. Fully Executed Interconnection Agreement October 2016 Connecting Transmission Owner & Developer 2. Conceptual Package and Equipment Specifications to CTO January 2017 Developer
AutoNDA by SimpleDocs
Milestones Milestone Date Responsible Party. 1. Engineering firm selected TBD Developer 2. Execution of interconnection agreement July 2020 Developer / Connecting Transmission Owner/ NYISO
Milestones Milestone Date Responsible Party. 1. Execute EPC Agreement October 2019 Affected System Operator/ Transmission Developer/ NYISO 2. Provide Security pursuant to EPC October 2019 Transmission Developer 3. Issue written authorization to proceed with engineering October 2019 Transmission Developer 4. Start engineering October 2019 Affected System Operator 5. Issue written authorization to proceed with procurement and construction February 2020 Transmission Developer 6. Start procurement March 2020 Affected System Operator
Milestones Milestone Date Responsible Party. 1. Engineering firm selected TBD Developer
Milestones Milestone Date Responsible Party. 1. Engineering start Complete Connecting Transmission Owner (“CTO”)/Developer 2. Procurement start Complete CTO/Developer 3. Construction start Complete CTO/Developer 4. Outage for demo of existing equipment and System Upgrade Facilities relocation Complete CTO 5. Engineering end Complete CTO/Developer
Milestones Milestone Date Responsible Party. 1. Execute EPC Agreement Completed Affected System Operator/ Transmission Developer/ NYISO 2. Provide Security pursuant to EPC Completed Transmission Developer 3. Issue written authorization to proceed with engineering Completed Transmission Developer 4. Start engineering Completed Affected System Operator Milestone Date Responsible Party
Milestones Milestone Date Responsible Party. 1. Execute EPC Agreement October 2019Completed Affected System Operator/ Transmission Developer/ NYISO 2. Provide Security pursuant to EPC October 2019Completed Transmission Developer 3. Issue written authorization to proceed with engineering October 2019Completed Transmission Developer 4. Start engineering October 2019Completed Affected System Operator 5. Issue written authorization to proceed with procurement and construction February 2020Completed Transmission Developer 6. Start procurement March 2020Completed Affected System Operator 7. Complete engineering September 2020Completed Affected System Operator 8. Complete procurement JanuaryFebruary 2021 Affected System Operator 9. Start construction MarchApril 2021 Affected System Operator
AutoNDA by SimpleDocs
Milestones Milestone Date Responsible Party. 1. Provide initial prepayment/security Completed Developer 2. Issue written authorization to proceed with engineering Completed Developer 3. Execute Interconnection Agreement August 2022 Connecting Transmission Owner/Developer 4. Start conceptual package according to engineering deliverables TM2.71.18 and equipment specification Completed Developer 5. Conceptual package according to engineering deliverables TM2.71.18 and equipment specification issued for use (“IFU”) approved Completed Connecting Transmission Owner 6. System Protection and Control (“SPC”) 1&2 starts (after conceptual engineering has been approved) August 2022 Developer 7. Start Rating and Modeling (“RAM”) (transmission facility rating and modeling) process August 2022 Developer 8. Procurement start Completed Developer 9. Start detail engineering package according to engineering deliverables TM2.71.18 IFR August 2022 Developer 10. Start SPC3-7 according to engineering deliverables TM2.71.18 IFR, IFA (starts after SPC 1&2 has been completed) August 2022 Developer
Milestones Milestone Date Responsible Party. Award order for Procurement of the Phase Angle Regulator Completed Transmission Developer 2. Start engineering of Dover PAR Substation and Transmission Line to ROW Completed Transmission Developer 3. Execute Interconnection Agreement November 2022 Connecting Transmission Owner/Transmission Developer/ NYISO 4. Post Security Deposit Simultaneously with execution of Interconnection Agreement Transmission Developer 5. Complete engineering for Transmission Project principal components * Completed Transmission Developer Milestone Date Responsible Party 6. Complete 60% Transmission Line design for submittal Completed Transmission Developer 7. Complete 90% Transmission Line design for submittal November 2022 Transmission Developer 8. Complete 60% Design Package - Relay Upgrades January 2023 Connecting Transmission Owner 9. Complete Issued for Construction Transmission Line submittal January 2023 Transmission Developer 10. Commence substation and transmission line site prep January 2023 Transmission Developer 11. Complete Issued for Construction Primary design Substation submittal March 2023 Transmission Developer 12. Mobilize crews for the substation build March 2023 Transmission Developer 13. Commence testing and commissioning October 2023 Connecting Transmission Owner/ Transmission Developer 14. Complete 90% Design Package - Relay Upgrades April 2023 Connecting Transmission Owner

Related to Milestones Milestone Date Responsible Party

  • Project/Milestones Taxpayer provides refrigerated warehousing and logistic distribution services to clients throughout the United States. In consideration for the Credit, Taxpayer agrees to invest in a new refrigeration and distribution facility in the XxXxxxxxx Park area of Sacramento, California, and hire full-time employees (collectively, the “Project”). Further, Taxpayer agrees to satisfy the milestones as described in Exhibit A (“Milestones”) and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of full-time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” Taxpayer may use the salaries of any of the full-time employees hired within the required time period. For purposes of calculating the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” the salary of any full-time employee that is not employed by Taxpayer for the entire taxable year shall be annualized. In addition, the salary of any full-time employee hired to fill a vacated position in which a full-time employee was employed during Taxpayer’s Base Year shall be disregarded.

  • Milestones Subject to the provisions of the SGIP, the Parties shall agree on milestones for which each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations under this provision may be extended by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the other Parties of the reason(s) for not meeting the milestone and: (1) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (2) requesting appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not unreasonably withhold agreement to such an amendment unless: (1) it will suffer significant uncompensated economic or operational harm from the delay, (2) attainment of the same milestone has previously been delayed, or (3) it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.