Mobilization. 1. Mobilization shall include, i) commencement of all design activities, including architect, engineer and design services and any and all related support services, and ii) the subsequent moving onto the Site of all equipment; furnishing and temporary buildings, and other construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall be undertaken in compliance with the requirements of the Contract and any staging plan approved by the County and shall include, but not be limited to, the following principal items: a. Moving onto the Site Contractor's equipment as required. b. Installing, outfitting, furnishing, equipping and making operational the temporary facilities as specified. c. Installing temporary construction power and wiring. d. Establishing fire protection system for its temporary facilities. e. Developing construction water supply. f. Providing field office trailers for the Contractor and County representative(s) with all specified furnishings and utility services including telephones. g. Providing connections to on-site sanitary facilities and potable water facilities as specified, or providing a portable toilet as needed. h. Arranging for and erecting of Contractor's work and storage yard(s). i. Posting all Occupational Safety and Health Act of 1970 (OSHA) required notices and establishment of safety programs. j. Establishing procedures for and installing all necessary equipment to comply with all applicable federal, State and local laws and regulations relating to the Work, including storm water run-off systems. 2. Within fifteen (15) days following the Effective Date of this Contract, the Contractor shall submit to the County, for its review and concurrence, a mobilization plan and schedule. a. The mobilization plan and schedule shall be subject to review and concurrence by the County. County shall have ten (10) days to review and approve or reject Contractor's mobilization plan. Should County reject Contractor's mobilization plan, County shall do so in writing. Contractor shall have ten (10) days to provide to County a revised mobilization plan at which time County will have ten (10) days to approve or reject Contractor's revised mobilization plan. After three (3) County rejections, County and Contractor shall follow the dispute resolution procedures set forth in Section 1.12 of the Contract. b. The mobilization plan and schedule shall be developed in both narrative and graphic format, and shall include, at a minimum, the following: i. A mobilization plan and Project Schedule for architectural, engineering and design services, including review and permitting processes. The mobilization plan shall include the schedules for developing, reviewing, approving and revising the Drawings as set forth in Section 1.05 of the Contract. ii. A mobilization plan and project schedule for initial construction activities, which include but are not limited to soil import and grading, any offsite improvements, parking and traffic control, and temporary facilities and staging. c. Contractor shall provide the mobilization and schedule in Microsoft Project 2000 or later version, in electronic format and hard copy (11” x 17” sheet size minimum format).
Appears in 9 contracts
Samples: Contract, Contract for Design Build Services, Contract
Mobilization.
1. Mobilization shall include, i) commencement of all design activities, including architect, engineer and design services and any and all related support services, and ii) the subsequent moving onto the Site of all equipment; furnishing and temporary buildings, and other construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall be undertaken in compliance with the requirements of the Contract and any staging plan approved by the County and shall include, but not be limited to, the following principal items:
a. Moving onto the Site Contractor's equipment as required.
b. Installing, outfitting, furnishing, equipping and making operational the temporary facilities as specified.specified.
c. Installing temporary construction power and wiring.
d. Establishing fire protection system for its temporary facilities.
e. Developing construction water supply.
f. Providing field office trailers for the Contractor and County representative(s) with all specified furnishings and utility services including telephones.telephones.
g. Providing connections to on-site sanitary facilities and potable water facilities as specified, or providing a portable toilet as needed.
h. Arranging for and erecting of Contractor's work and storage yard(s).yard(s).
i. Posting all Occupational Safety and Health Act of 1970 (OSHA) required notices and establishment of safety programs.
j. Establishing procedures for and installing all necessary equipment to comply with all applicable federal, State and local laws and regulations relating to the Work, including storm water run-off systems.
2. Within fifteen (15) days following the Effective Date of this Contract, the Contractor shall submit to the County, for its review and concurrence, a mobilization plan and schedule.schedule.
a. The mobilization plan and schedule shall be subject to review and concurrence by the County. County shall have ten (10) days to review and approve or reject Contractor's mobilization plan. Should County reject Contractor's mobilization plan, County shall do so in writing. Contractor shall have ten (10) days to provide to County a revised mobilization plan at which time County will have ten (10) days to approve or reject Contractor's revised mobilization plan. After three (3) County rejections, County and Contractor shall follow the dispute resolution procedures set forth in Section 1.12 of the Contract.
b. The mobilization plan and schedule shall be developed in both narrative and graphic format, and shall include, at a minimum, the following:
i. A mobilization plan and Project Schedule for architectural, engineering and design services, including review and permitting processes. The mobilization plan shall include the schedules for developing, reviewing, approving and revising the Drawings as set forth in Section 1.05 of the Contract.
ii. A mobilization plan and project schedule for initial construction activities, which include but are not limited to soil import and grading, any offsite improvements, parking and traffic control, and temporary facilities and staging.
c. Contractor shall provide the mobilization and schedule in Microsoft Project 2000 or later version, in electronic format and hard copy (11” x 17” sheet size minimum format).
Appears in 1 contract
Samples: Contract for Design Build Services
Mobilization. 1. Mobilization shall include, i) commencement of all design activities, including architect, engineer and design services and any and all related support services, and ii) the subsequent moving onto the Site of all equipment; furnishing and temporary buildings, and other construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall be undertaken in compliance with the requirements of the Contract and any staging plan approved by the County and shall include, but not be limited to, the following principal items:
a. Moving onto the Site Contractor's equipment as required.
b. Installing, outfitting, furnishing, equipping and making operational the temporary facilities as specified.
c. Installing temporary construction power and wiring.
d. Establishing fire protection system for its temporary facilities.
e. Developing construction water supply.
f. Providing field office trailers for the Contractor and County representative(s) with all specified furnishings and utility services including telephones.
g. Providing connections to on-site sanitary facilities and potable water facilities as specified, or providing a portable toilet as needed.
h. Arranging for and erecting of Contractor's work and storage yard(s).
i. Posting all Occupational Safety and Health Act of 1970 (OSHA) required notices and establishment of safety programs.
j. Establishing procedures for and installing all necessary equipment to comply with all applicable federal, State and local laws and regulations relating to the Work, including storm water run-off systems.
2. Within fifteen (15) days following the Effective Date of this Contract, the Contractor shall submit to the County, for its review and concurrence, a mobilization plan and schedule.
a. The mobilization plan and schedule shall be subject to review and concurrence by the County. County shall have ten (10) days to review and approve or reject Contractor's mobilization plan. Should County reject Contractor's mobilization plan, County shall do so in writing. Contractor shall have ten (10) days to provide to County a revised mobilization plan at which time County will have ten (10) days to approve or reject Contractor's revised mobilization plan. After three (3) County rejections, County and Contractor shall follow the dispute resolution procedures set forth in Section 1.12 Section
1. 12 of the Contract.
b. The mobilization plan and schedule shall be developed in both narrative and graphic format, and shall include, at a minimum, the following:
i. A mobilization plan and Project Schedule for architectural, engineering and design services, including review and permitting processes. The mobilization plan shall include the schedules for developing, reviewing, approving and revising the Drawings as set forth in Section 1.05 of the Contract.
ii. A mobilization plan and project schedule for initial construction activities, which include but are not limited to soil import and grading, any offsite improvements, parking and traffic control, and temporary facilities and staging.
c. Contractor shall provide the mobilization and schedule in Microsoft Project 2000 or later version, in electronic format and hard copy (11” x 17” sheet size minimum format).
Appears in 1 contract
Samples: Construction Contract
Mobilization.
1. Mobilization shall include, i) commencement of all design activities, including architect, engineer and design services and any and all related support services, and ii) the subsequent moving onto the Site of all equipment; furnishing and temporary buildings, and other construction facilities; all as required for the proper performance and completion of the Work. Mobilization shall be undertaken in compliance with the requirements of the Contract and any staging plan approved by the County and shall include, but not be limited to, the following principal items:
a. Moving onto the Site Contractor's equipment as required.
b. Installing, outfitting, furnishing, equipping and making operational the temporary facilities as specified.specified.
c. Installing temporary construction power and wiring.
d. Establishing fire protection system for its temporary facilities.
e. Developing construction water supply.
f. Providing field office trailers for the Contractor and County representative(s) with all specified furnishings and utility services including telephones.
g. Providing connections to on-site sanitary facilities and potable water facilities as specified, or providing a portable toilet as needed.
h. Arranging for and erecting of Contractor's work and storage yard(s).yard(s).
i. Posting all Occupational Safety and Health Act of 1970 (OSHA) required notices and establishment of safety programs.
j. Establishing procedures for and installing all necessary equipment to comply with all applicable federal, State and local laws and regulations relating to the Work, including storm water run-off systems.
2. Within fifteen (15) days following the Effective Date of this Contract, the Contractor shall submit to the County, for its review and concurrence, a mobilization plan and schedule.schedule.
a. The mobilization plan and schedule shall be subject to review and concurrence by the County. County shall have ten (10) days to review and approve or reject Contractor's mobilization plan. Should County reject Contractor's mobilization plan, County shall do so in writing. Contractor shall have ten (10) days to provide to County a revised mobilization plan at which time County will have ten (10) days to approve or reject Contractor's revised mobilization plan. After three (3) County rejections, County and Contractor shall follow the dispute resolution procedures set forth in Section 1.12 of the Contract.
b. The mobilization plan and schedule shall be developed in both narrative and graphic format, and shall include, at a minimum, the following:
i. A mobilization plan and Project Schedule for architectural, engineering and design services, including review and permitting processes. The mobilization plan shall include the schedules for developing, reviewing, approving and revising the Drawings as set forth in Section 1.05 of the Contract.
ii. A mobilization plan and project schedule for initial construction activities, which include but are not limited to soil import and grading, any offsite improvements, parking and traffic control, and temporary facilities and staging.
c. Contractor shall provide the mobilization and schedule in Microsoft Project 2000 or later version, in electronic format and hard copy (11” x 17” sheet size minimum format).
Appears in 1 contract
Samples: Design Build Contract