Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 31 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider Owner before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's Owner’s prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 15 contracts
Samples: Service Agreement, Interconnection Agreement, Small Generator Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider Owner before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's Owner’s prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating FacilityFacility if required by Good Utility Practice.
Appears in 12 contracts
Samples: Interconnection Agreement, Service Agreement, Service Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Distribution System and/or the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 7 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Service Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider Owner before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission ProviderOwner's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 6 contracts
Samples: Small Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Distribution System and/or Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 4 contracts
Samples: Small Generator Interconnection Agreement, Interconnection Agreement, Small Generator Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider Owner before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's Owner’s prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility. If disconnected, the Small Generating Facility will not be reconnected until the unauthorized modifications are authorized or removed.
Appears in 4 contracts
Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement, Interconnection Agreement
Modification of the Small Generating Facility. In Process The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Distribution System and/or Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 2 contracts
Samples: Small Generator Interconnection Agreement, Small Generator Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's ’s prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 2 contracts
Samples: Study Agreement, Lassen Municipal Utility District Small Generator Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider Owner before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.7
Appears in 1 contract
Samples: Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Distribution System and/or the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 1 contract
Samples: Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Distribution System and/or Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.Facility.
Appears in 1 contract
Samples: Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Distribution Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Distribution Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 1 contract
Samples: Interconnection Agreement
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 1 contract
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 1 contract
Modification of the Small Generating Facility. The Interconnection Customer must receive written authorization from the Transmission Provider before making any change to the Small Generating Facility that may have a material impact on the safety or reliability of the Transmission System. Such authorization shall not be unreasonably withheld. Modifications shall be done in accordance with Good Utility Practice. If the Interconnection Customer makes such modification without the Transmission Provider's prior written authorization, the latter shall have the right to temporarily disconnect the Small Generating Facility.
Appears in 1 contract
Samples: Study Agreement