National Grid Design, Engineering and Construction Activities. 4.3.1 At Municipal's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or Modifications and Upgrades in accordance with (a) the Interconnection Study, (b) Good Utility Practice and (c) National Grid and NYISO standards. Any disputes concerning the foregoing shall be resolved in accordance with Article XXI of this Agreement. 4.3.2 At Municipal's expense, National Grid agrees to procure any and all equipment and materials to be incorporated into the construction or modification of the National Grid Interconnection Facility and Upgrades. 4.3.3 All design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activities. National Grid, at Municipal's expense, agrees to inform Municipal on the first business day of each month and at such other times as Municipal reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or the National Grid Interconnection Facilities. 4.3.4 No design, engineering, procurement, or construction activities shall be undertaken by National Grid prior to Municipal's receipt of the Interconnection Study and until such time as Municipal issues a written notice to proceed with such activities and a money deposit received by National Grid for services to be rendered. 4.3.5 Municipal reserves the right, upon thirty (30) Calendar Days prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or with any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or Modifications. Municipal acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to Municipal's suspending said work, in accordance with Article X of this Agreement. National Grid shall, if requested by Municipal, use Reasonable Efforts to suspend work by National Grid less than thirty (30) Calendar Days after National Grid receives notice from Municipal. 4.3.6 National Grid shall, at Municipal's expense, test the Interconnection Facilities, Modifications and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.
Appears in 12 contracts
Samples: Service Agreement, Interconnection Agreement, Service Agreement
National Grid Design, Engineering and Construction Activities. 4.3.1 At MunicipalSolvay's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or or Modifications and Upgrades in accordance with with: (a) the any Interconnection Study, (b) Good Utility Practice and Practice, (c) National Grid Grid's standards and NYISO standards. Any disputes concerning (d) to the foregoing shall be resolved extent applicable, the Scope of Work in accordance with Article XXI of this Agreement.Exhibit D, the Estimated Project Costs in Exhibit E and the Project Milestone Schedule in Exhibit F.
4.3.2 At MunicipalSolvay's expense, National Grid agrees to procure any and all equipment and materials necessary for National Grid to be incorporated into the construction construct or modification of modify the National Grid Interconnection Facility Facilities and Upgrades.
4.3.3 All design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activitiesactivities and set forth in Exhibit B to this Agreement. National Grid, at MunicipalSolvay 's expense, agrees to inform Municipal on the first business day of each month and Solvay at such other times as Municipal Solvay reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or Modifications to the National Grid Interconnection Facilities.
4.3.4 No design, engineering, procurement, or construction activities not previously authorized by any Cost Reimbursement Agreement between Solvay and National Grid shall be undertaken by National Grid prior to MunicipalSolvay's receipt of the Interconnection Study and until such time as Municipal Solvay issues a written notice to proceed with such activities and a money deposit is received by National Grid for services to be rendered.
4.3.5 Municipal Solvay reserves the right, upon thirty (30) Calendar Days days prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or with any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or or Modifications. Municipal Solvay acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to MunicipalSolvay's suspending said work, work in accordance with Article X IX of this Agreement. National Grid shall, if requested by Municipal, use Reasonable Efforts to suspend work by National Grid less than thirty (30) Calendar Days after National Grid receives notice from Municipal.
4.3.6 National Grid shall, at MunicipalSolvay's expense, test the National Grid Interconnection Facilities, Modifications Modifications, and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.
Appears in 6 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
National Grid Design, Engineering and Construction Activities. 4.3.1 At Municipal's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or Modifications and Upgrades in accordance with (a) the Interconnection Study, (b) Good Utility Practice and (c) National Grid and NYISO Grid's standards. Any disputes concerning the foregoing shall be resolved in accordance with Article XXI of this Agreement.
4.3.2 At Municipal's expense, National Grid agrees to procure any and all equipment and materials necessary for National Grid to be incorporated into the construction construct or modification of modify the National Grid Interconnection Facility and Upgrades.
4.3.3 . All design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activitiesactivities and set forth in Exhibit B to this Agreement. National Grid, at Municipal's expense, agrees to inform Municipal on the first business day of each month and at such other times as Municipal reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or the National Grid Interconnection Facilities.
4.3.4 No design, engineering, procurement, or construction activities shall be undertaken by National Grid prior to Municipal's receipt of the Interconnection Study and until such time as Municipal issues a written notice to proceed with such activities and a money deposit received by National Grid for services to be rendered.
4.3.5 Municipal reserves the right, upon thirty (30) Calendar Days prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or with any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or Modifications. Municipal acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to Municipal's suspending said work, in accordance with Article X of this Agreement. National Grid shall, if requested by Municipal, use Reasonable Efforts to suspend work by National Grid less than thirty (30) Calendar Days after National Grid receives notice from Municipal.
4.3.6 National Grid shall, at Municipal's expense, test the Interconnection Facilities, Modifications and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.
Appears in 4 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
National Grid Design, Engineering and Construction Activities. 4.3.1 At MunicipalCustomer's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or any Modifications and Upgrades in accordance with with: (a) the any Interconnection Study, (b) Good Utility Practice Practice, and (c) National Grid and NYISO standards. Any disputes concerning the foregoing shall be resolved Grid’s standards as identified in accordance with Article XXI of this Agreement.Exhibit B.
4.3.2 At MunicipalCustomer's expense, National Grid agrees to procure any and all equipment and materials necessary for National Grid to be incorporated into the construction or modification of construct any Modification to the National Grid Interconnection Facility and UpgradesFacility.
4.3.3 All design, engineering, procurement, and construction activities in connection with and as may be required by any Modification performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activities. National Grid, at Municipal's Customer’s expense, agrees to inform Municipal Customer on the first business day of each month and at such other times as Municipal Customer reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or the National Grid Interconnection Facilitiesany Modification.
4.3.4 No design, engineering, procurement, or construction activities shall be undertaken by National Grid prior to Municipal's receipt of the Interconnection Study in connection with and as may be required by any Modification until such time as Municipal Customer issues a written notice to proceed with such activities and a money deposit received by National Grid for services to be rendered.
4.3.5 Municipal Customer reserves the right, upon thirty (30) Calendar Days Day prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or in connection with and as may be required by any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or Modifications. Municipal Customer acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to MunicipalCustomer's suspending said work, work in accordance with Article X of this Agreement. National Grid shall, if requested by MunicipalCustomer, use Reasonable Efforts to suspend work by National Grid in less than thirty (30) Calendar Days after National Grid receives notice from MunicipalCustomer.
4.3.6 National Grid shall, at MunicipalCustomer's expense, test the Interconnection Facilities, any Modifications and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.their
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
National Grid Design, Engineering and Construction Activities. 4.3.1 At Municipal's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or Modifications and Upgrades in accordance with (a) the Interconnection Study, (b) Good Utility Practice and (c) National Grid and NYISO Grid's standards. Any disputes concerning the foregoing shall be resolved in accordance with Article XXI of this Agreement.
4.3.2 At Municipal's expense, National Grid agrees to procure any and all equipment and materials necessary for National Grid to be incorporated into the construction construct or modification of modify the National Grid Interconnection Facility and Upgrades.
4.3.3 All design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activitiesactivities and set forth in Exhibit B to this Agreement. National Grid, at Municipal's expense, agrees to inform Municipal on the first business day of each month and at such other times as Municipal reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or the National Grid Interconnection Facilities.
4.3.4 No design, engineering, procurement, or construction activities shall be undertaken by National Grid prior to Municipal's receipt of the Interconnection Study and until such time as Municipal issues a written notice to proceed with such activities and a money deposit received by National Grid for services to be rendered.
4.3.5 Municipal reserves the right, upon thirty (30) Calendar Days Day prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or with any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or Modifications. Municipal acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to Municipal's suspending said work, work in accordance with Article X of this Agreement. National Grid shall, if requested by Municipal, use Reasonable Efforts to suspend work by National Grid less than thirty (30) Calendar Days after National Grid receives notice from Municipal.
4.3.6 National Grid shall, at Municipal's expense, test the Interconnection Facilities, Modifications and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
National Grid Design, Engineering and Construction Activities. 4.3.1 At MunicipalCustomer's expense, National Grid agrees to design, engineer, and construct the National Grid Interconnection Facilities and/or any Modifications and Upgrades in accordance with with: (a) the any Interconnection Study, (b) Good Utility Practice Practice, and (c) National Grid and NYISO standards. Any disputes concerning the foregoing shall be resolved Grid’s standards as identified in accordance with Article XXI of this Agreement.Exhibit B.
4.3.2 At MunicipalCustomer's expense, National Grid agrees to procure any and all equipment and materials necessary for National Grid to be incorporated into the construction or modification of construct any Modification to the National Grid Interconnection Facility and UpgradesFacility.
4.3.3 All design, engineering, procurement, and construction activities in connection with and as may be required by any Modification performed by National Grid or a third party selected by National Grid shall be performed in accordance with a schedule and an estimated budget mutually agreed to by the Parties in advance of the commencement of such activities. National Grid, at Municipal's Customer’s expense, agrees to inform Municipal Customer on the first business day of each month and at such other times as Municipal Customer reasonably requests of the status of all design, engineering, procurement, and construction activities performed by National Grid or a third party selected by National Grid, including, but not limited to, the following information: progress to date; a description of upcoming scheduled activities and events; the delivery status of all ordered equipment; a revised budget and cost report; and the identification of any event which National Grid reasonably expects may delay construction of the Upgrades or the National Grid Interconnection Facilitiesany Modification.
4.3.4 No design, engineering, procurement, or construction activities shall be undertaken by National Grid prior to Municipal's receipt of the Interconnection Study in connection with and as may be required by any Modification until such time as Municipal Customer issues a written notice to proceed with such activities and a money deposit received by National Grid for services to be rendered.
4.3.5 Municipal Customer reserves the right, upon thirty (30) Calendar Days Day prior written notice to National Grid, to suspend at any time all work by National Grid associated with the design, engineering, procurement, construction of the Upgrades or in connection with and as may be required by any design, engineering, and construction activities relating to the National Grid Interconnection Facilities and/or Modifications. Municipal Customer acknowledges and agrees to reimburse National Grid for all costs incurred by National Grid that cannot be avoided, due to MunicipalCustomer's suspending said work, work in accordance with Article X of this Agreement. National Grid shall, if requested by MunicipalXxxxxxxx, use Reasonable Efforts to suspend work by National Grid in less than thirty (30) Calendar Days after National Grid receives notice from MunicipalCustomer.
4.3.6 National Grid shall, at MunicipalCustomer's expense, test the Interconnection Facilities, any Modifications and Upgrades to ensure their safe and reliable operation in accordance with Good Utility Practice.their
Appears in 1 contract
Samples: Interconnection Agreement