No Award of Owner-Contractor Agreement. If the Project is constructed pursuant to M.G.L. c. 149, §§ 44A-44M, the Owner-Contractor Agreement is not awarded by the Owner within one hundred twenty (120) days after the receipt of general bids for the Project and the bids have not been rejected and the Project has not been suspended, the Designer shall be paid through the Bidding Phase as if a contract for construction were awarded according to the payment schedule provided in Attachment A. This Article 12.5 does not apply, however, if the Designer has been directed to perform design revisions pursuant to 4.10.2, for the purposes of bringing the design of the Project within the Project Construction Budget.