Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.
Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.
FINAL COMPLETION AND FINAL PAYMENT 9.9.1 Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect will promptly make such 9.9.2 Neither the final payment nor the remaining retained percentage shall become due until the Contractor submits to the Architect (1) an affidavit that all payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the State or its property might in any way be responsible, have been paid or otherwise satisfied; (2) consent of surety, if any, to final payment; (3) Other data establishing payment or satisfaction of all such obligations, including, but not limited to, receipts, releases, or other supporting documentation. and (4) final waivers of liens arising out of the Contract, to the extent and in such form as may be designated by the State. If any Subcontractor refuses to furnish a release or waiver required by the State, the Contractor may furnish a bond satisfactory to the State to indemnify him against any such lien. If any such lien remains unsatisfied after all payments are made, the Contractor shall refund to the State all moneys that the latter may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees. 9.9.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by the issuance of Change Orders affecting final completion, and the Architect so confirms, the State shall, upon application by the Contractor and certification by the Architect, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipulated in the Contract Documents, and if bonds have been furnished as required by the Contract Documents, the written consent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect prior to certification of such payment. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims. 9.9.4 The making of final payment shall constitute a waiver of all claims by the State except those arising from: (a) unsettled liens, (b) faulty or defective Work appearing after Substantial Completion, (c) failure of the Work to comply with the requirements of the Contract Documents, or (d) terms of any special warranties required by the Contract Documents. 9.9.5 The acceptance of final payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the final Application for Payment.
Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.
Events Subsequent to Most Recent Fiscal Year End Since the Most Recent Fiscal Year End and except as described herein and in the attached exhibits, there has not been any material adverse change in the business, financial condition, operations, results of operations, or future prospects of Sewcal. Without limiting the generality of the foregoing, since that date: (i) Sewcal has not sold, leased, transferred, or assigned any of its assets, tangible or intangible, other than for a fair consideration in the Ordinary Course of Business; (ii) Sewcal has note entered into any agreement, contract, lease, or license (or series of related agreements, contracts, leases, and licenses) involving more than $10,000.00 outside the Ordinary Course of Business; (iii) Sewcal has not accelerated, terminated, modified, or canceled any agreement, contract, lease, or license (or series of related agreements, contracts, leases, and licenses) involving more than $10,000.00 to which Sewcal is a party. (iv) Sewcal has not imposed any Security Interest upon any of its assets, tangible or intangible; (v) Sewcal has not made any capital expenditure (or series of related capital expenditures) either involving more than $5,000.00 outside the Ordinary Course of Business; (vi) Sewcal has not made any capital investment in, any loan to, or any acquisition of the securities or assets of, any other Person (or series of related capital investments, loans, and acquisitions) either involving more than $5,000.00 outside the Ordinary Course of Business; (vii) Sewcal has not issued any note, bond, or other debt security or created, incurred, assumed, or guaranteed any indebtedness for borrowed money or capitalized lease obligation either involving more than $2,500.00 singly or $5,000.00 in the aggregate. (viii) Sewcal has not delayed or postponed the payment of accounts payable and other Liabilities outside the Ordinary Course of Business; (ix) Sewcal has not canceled, compromised, waived, or released any right or claim (or series of related rights and claims) involving more than $2,500.00 outside the Ordinary Course of Business; (x) Sewcal has not granted any license or sublicense of any rights under or with respect to any Intellectual Property; (xi) Sewcal has not made or authorized any change in its articles of incorporation or bylaws of any of Sewcal or its Subsidiaries; (xii) Sewcal has not issued, sold, or otherwise disposed of any of its capital stock, or granted any options, warrants, or other rights to purchase or obtain (including upon conversion, exchange, or exercise) any of its capital stock; (xiii) Sewcal has not declared, set aside, or paid any dividend or made any distribution with respect to its capital stock (whether in cash or in kind) or redeemed, purchased, or otherwise acquired any of its capital stock; (xiv) Sewcal has not experienced any damage, destruction, or loss (whether or not covered by insurance) to its property outside the ordinary course of business; (xv) Sewcal has not made any loan to, or entered into any other transaction with, any of its directors, officers, and employees outside the Ordinary Course of Business; (xvi) Sewcal has not entered into any collective bargaining agreements, written or oral, or modified the terms of any existing such contract or agreement; (xvii) Sewcal has not granted any increase in the base compensation of any of its directors, officers, and employees outside the Ordinary Course of Business; (xviii) Sewcal has not adopted, amended, modified, or terminated any bonus, profit-sharing, incentive, severance, or other plan, contract, or commitment for the benefit of any of its directors, officers, and employees (or taken any such action with respect to any other Employee Benefit Plan); (xix) Sewcal has not made any other change in employment terms for any of its directors, officers, and employees outside the Ordinary Course of Business; (xx) Sewcal has not made or pledged to make any charitable or other capital contribution outside the Ordinary Course of Business; (xxi) (removed) (xxii) There has not been any other material occurrence, event, incident, action, failure to act, or transaction outside the Ordinary Course of Business involving Sewcal and/or its Subsidiaries; and
ADDITIONAL SPECIAL CONTRACT CONDITIONS Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following:
Completion Date The Work under this Contract shall be completed by midnight of the date required in the Contract as the Material Completion and Occupancy Date unless extended by approved requests for extension of time.
Final Completion The full and final completion of all Work in accordance with the Contract Documents.
C1 Contract Price In consideration of the Contractor’s performance of its obligations under the Contract, the Authority shall pay the Contract Price in accordance with clause C2 (Payment and VAT).
Completion Schedule 6.1 The proposed schedule for the completion of the Project is presented in “Attachment D” and is made a part hereof. 6.2 ENGINEER shall adhere to all time limits stated in this Agreement or included in any accepted time schedule. All such time limits shall be of the essence to this Agreement. 6.3 In all events the various stages and phases of ENGINEER’S services are to be completed in such sequence and at such times, and with approved or agreed upon time limits, as may be required to assure the timely, continuous, efficient and diligent prosecution of the work and services provided for by this Agreement. 6.4 OWNER may at any time, by written order, make changes within the general scope of the Agreement in the services of work to be performed. If ENGINEER believes that such a change justifies an increase in ENGINEER’S contract time or contract price required to perform the series under this Agreement it must assert such claim in writing within thirty (30) days of receipt of OWNER’S written order giving rise to the claim. No claim for adjustment in the contract time or contract price will be valid if not submitted in accordance with this paragraph. No services for which ENGINEER will charge additional compensation shall be furnished without the written authorization of OWNER. 6.5 ENGINEER shall carry on all work required under this Agreement and maintain the schedule for services during all disputes or disagreements with OWNER. No work shall be delayed or postponed pending resolution of any disputes or disagreements except as permitted in Article 8, or as ENGINEER and OWNER may otherwise agree in writing. 6.6 If the commencement, prosecution or completion of the services under this Agreement, or of the construction of the Project is delayed by any act, omission, delay, neglect or default of ENGINEER, or anyone employed by ENGINEER, or by any damage or acts caused by the negligent acts or omission by ENGINEER, then ENGINEER shall be liable to OWNER for any and all costs, assessments, expense, liabilities or damages caused thereby, in accordance with Section 4.8. 6.7 ENGINEER shall not be responsible for any time delays in the Project, or in the performance of services under this Agreement, to the extent such delays are caused solely by any act, omission, neglect or default of OWNER or anyone employed by OWNER, or by the unreasonable delay of any review agency or utility, or for any delay or damage caused by fire or the combined action of workers and which are in no way chargeable, in whole or in part, to ENGINEER, or by any other conditions or circumstances beyond the control of ENGINEER, its employee, agent, or other persons for whose acts or omissions ENGINEER is responsible. In the event of such delay, ENGINEER shall be entitled to an adjustment in the schedules or agreed time limitations for the performance of services, and this Agreement shall be modified in writing accordingly. Any claim of ENGINEER for adjustment under this cause must be asserted in writing within thirty (30) days from the date of the occurrence of the event giving rise to the claim, unless OWNER grants a further period of time before the date of final payment to ENGINEER. The adjustment of time for the performance of services, as provided in this paragraph, shall be ENGINEER’s sole exclusive right, entitlement and remedy in the event of such delays, and ENGINEER shall have no claim against OWNER for adjustment for increase in costs of performance, or other damages occurred in connection therewith.