Notice of Change in Installation. a) The Member will notify the Cooperative in writing thirty (30) days in advance of making any change affecting the characteristics, performance, or protection of the DG facility. b) If any modification undertaken by the Member will create or has created conditions which may be unsafe or adversely affect the Cooperative system, the Member shall immediately correct such conditions or be subject to immediate disconnection from the Cooperative system. c) Any change in the operating characteristics of the DG facility including, but not limited to, size of generator, total facility capacity, nature of facility, fuel source, site change, hours of operation, or type used, may require a new application process, including, but not limited to, application form, application fee, DG plan and DG plan review by the Cooperative.
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Notice of Change in Installation. a) The Member will shall notify the Cooperative in writing thirty (30) days in advance of making any change affecting the characteristics, performance, or protection of the DG facilityFacility.
b) If any modification undertaken by the Member will create or has created conditions which may be unsafe or adversely affect the Cooperative systemSystem, the Member shall immediately correct such conditions or be subject to immediate disconnection from the Cooperative systemSystem.
c) Any change in the operating characteristics of the DG facility Facility including, but not limited to, size of generator, total facility Facility capacity, nature of facilityFacility, fuel source, site change, hours of operation, or type used, may require a new application process, including, but not limited to, application form, application fee, DG plan and DG plan review by the Cooperative.
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Notice of Change in Installation. a) The Member will notify the Cooperative in writing thirty (30) days in advance of making any change affecting the characteristics, performance, or protection of the DG facility.
b) If any modification undertaken by the Member will create or has created conditions which may be unsafe or adversely affect the Cooperative Cooperative’s system, the Member shall immediately correct such conditions or be subject to immediate disconnection from the Cooperative Cooperative’s system.
c) Any change in the operating characteristics of the DG facility including, but not limited to, size of generator, total facility capacity, nature of facility, fuel source, site change, hours of operation, or type of generator used, may will require a new application process, including, but not limited to, application form, application fee, DG plan Plan and DG plan Plan review by the Cooperative.
Appears in 1 contract
Samples: Interconnection Agreement
Notice of Change in Installation.
a) The Member will notify the Cooperative CENTRAL in writing thirty (30) days in advance of making any change affecting the characteristics, performance, or protection of the DG facilityinstallation.
b) If any modification undertaken by the Member will create or has created conditions which may be unsafe or adversely affect the Cooperative CENTRAL system, the Member shall immediately correct such conditions or be subject to immediate disconnection from the Cooperative CENTRAL’s system.
c) Any change in the operating characteristics of the DG facility installation including, but not limited to, size of generator, total facility capacity, nature of facility, fuel source, site change, hours of operation, or type of generator used, may require will required a new application process, including, but not limited to, application form, application fee, DG plan and DG plan review by the CooperativeCENTRAL.
Appears in 1 contract