Common use of Notice of Need for System Impact Study Clause in Contracts

Notice of Need for System Impact Study. After receiving an Application for service, the Transmission Provider shall determine on a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting a System Impact Study is provided in Attachment D. If the Transmission Provider determines that a System Impact Study is necessary to accommodate the requested service, it shall so inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreement, the Eligible Customer can avoid the costs associated with the study of these options. The Transmission Provider shall, within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the study, submit a System Impact Study Agreement whereby the Eligible Customer shall agree to reimburse the Transmission Provider for conducting the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the System Impact Study Agreement and return it to the Transmission Provider within fifteen (15) days. If the Eligible Customer elects not to execute the System Impact Study Agreement, its application shall be deemed withdrawn and its deposit shall be returned with interest pursuant to Section 17.3.

Appears in 2 contracts

Samples: Service Agreement, Service Agreement

AutoNDA by SimpleDocs

Notice of Need for System Impact Study. After receiving an Application a request for service, the Transmission Provider System Operator shall review the effect of the requested service on the reliability requirements to meet existing and pending obligations of the Participant(s) and on the obligations of the particular Participant(s) whose PTF facilities will be impacted by the proposed service and shall determine on a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting completing a System Impact Study is provided in Attachment D. If the Transmission Provider System Operator determines that a System Impact Study is necessary to accommodate the requested service, it shall so as soon as practicable inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider any affected Participant(s) if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreementis to be performed by the Participant(s). If the likely result of the study is that a Direct Assignment Facility will be required, the Eligible Customer can avoid study shall be performed by the costs associated with affected Participant(s), subject to review by the study of these optionsSystem Operator. The Transmission Provider shallIn such cases, the System Operator shall within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the study, submit tender a System Impact Study Agreement whereby agreement in the form of Attachment I to this Tariff, or in any other form that is mutually agreed to, pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider System Operator and any affected Participant for conducting performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the a System Impact Study Agreement agreement and return it to the Transmission Provider System Operator within fifteen (15) days. If the Eligible Customer elects not to execute the a System Impact Study Agreementagreement, its application Application shall be deemed withdrawn and its deposit (less the reasonable Administrative Costs incurred by the System Operator and any affected Participant(s)) shall be returned with interest pursuant to Section 17.3Interest.

Appears in 1 contract

Samples: Service Agreement (North Atlantic Energy Corp /Nh)

Notice of Need for System Impact Study. After receiving an Application a request for serviceFirm Point-To-Point Transmission Service, the Transmission Provider shall System Operator will review the effect of the proposed service on the reliability requirements to meet existing and pending obligations of the Participants and Non-Participants, and the obligations of the particular Participants whose PTF facilities will be impacted by the proposed service and determine on a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting completing a System Impact Study is provided in Attachment D. If the Transmission Provider System Operator determines that a System Impact Study is necessary to accommodate the requested service, it shall as soon as practicable thereafter the System Operator will so inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider any affected Participants if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreementis to be performed by the Participants. If the likely result of the study is that a Direct Assignment Facility will be required, the Eligible Customer can avoid study shall be performed by the costs associated with affected Participants, subject to review by the study of these optionsSystem Operator. The Transmission Provider shallIn such cases, the System Operator will within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the study, submit tender a System Impact Study Agreement whereby agreement in the form of Exhibit I to this Tariff, or in any other form that is mutually agreed to, pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider System Operator and any affected Participants for conducting performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the System Impact Study Agreement agreement and return it to the Transmission Provider System Operator within fifteen (15) days. If the Eligible Customer elects not to execute the a System Impact Study Agreementagreement, its application shall be deemed withdrawn and its deposit shall (less the reasonable Administrative Costs incurred by the System Operator and any affected Participants in connection with the Application), will be returned with interest pursuant to Section 17.3Interest.

Appears in 1 contract

Samples: Service Agreement (North Atlantic Energy Corp /Nh)

Notice of Need for System Impact Study. After receiving an Application a request for serviceFirm Point-To-Point Transmission Service as Through or Out Service, the Transmission Provider shall System Operator will review the effect of the proposed service on the reliability requirements to meet existing and pending obligations of the Participants and the obligations of the particular Participants whose PTF facilities will be impacted by the proposed service and determine on a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting completing a System Impact Study is provided in Attachment D. If the Transmission Provider System Operator determines that a System Impact Study is necessary to accommodate the requested service, it shall as soon as practicable thereafter the System Operator will so inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider any affected Participants if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreementis to be performed by the Participants. If the likely NEPOOL Open Access Transmission Tariff Original Sheet No. 114 result of the study is that a Direct Assignment Facility will be required, the Eligible Customer can avoid study shall be performed by the costs associated with affected Participants, subject to review by the study of these optionsSystem Operator. The Transmission Provider shallIn such cases, the System Operator will within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the studyor compliance with Section 26, submit whichever is applicable, tender a System Impact Study Agreement whereby agreement in the form of Exhibit I to this Tariff, or in any other form that is mutually agreed to, pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider NEPOOL and any affected Participants for conducting performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the System Impact Study Agreement agreement and return it to the Transmission Provider System Operator within fifteen (15) days. If the Eligible Customer elects not to execute the a System Impact Study Agreementagreement, its application shall be deemed withdrawn and its deposit shall be returned with interest pursuant to Section 17.3.(less the reasonable Administrative Costs incurred by the System Operator and NEPOOL Open Access Transmission Tariff Original Sheet No. 115

Appears in 1 contract

Samples: Power Pool Agreement (North Atlantic Energy Corp /Nh)

AutoNDA by SimpleDocs

Notice of Need for System Impact Study. After receiving an Application a request for service, the Transmission Provider System Operator shall review the effect of the requested service on the reliability requirements to meet existing and pending obligations of the Participant(s) and on the obligations of the particular Participant(s) whose PTF facilities will be impacted by the proposed service and shall determine on NEPOOL Restated Open Access Transmission Tariff Original Sheet No. 174 a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting completing a System Impact Study is provided in Attachment D. If the Transmission Provider System Operator determines that a System Impact Study is necessary to accommodate the requested service, it shall so as soon as practicable inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider any affected Participant(s) if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreementis to be performed by the Participant(s). If the likely result of the study is that a Direct Assignment Facility will be required, the Eligible Customer can avoid study shall be performed by the costs associated with affected Participant(s), subject to review by the study of these optionsSystem Operator. The Transmission Provider shallIn such cases, the System Operator shall within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the study, submit tender a System Impact Study Agreement whereby agreement in the form of Attachment I to this Tariff, or in any other form that is mutually agreed to, pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider System Operator and any affected Participant for conducting performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer NEPOOL Restated Open Access Transmission Tariff Original Sheet No. 175 shall execute the a System Impact Study Agreement agreement and return it to the Transmission Provider System Operator within fifteen (15) days. If the Eligible Customer elects not to execute the a System Impact Study Agreementagreement, its application Application shall be deemed withdrawn and its deposit (less the reasonable Administrative Costs incurred by the System Operator and any affected Participant(s)) shall be returned with interest pursuant to Section 17.3Interest.

Appears in 1 contract

Samples: Agreement (North Atlantic Energy Corp /Nh)

Notice of Need for System Impact Study. After receiving an Application a request for serviceFirm Point-To-Point Transmission Service, the Transmission Provider shall System Operator will review the effect of the proposed service on the reliability requirements to meet existing and pending obligations of the Participants and Non-Participants, and the obligations of the particular Participants whose PTF facilities will be impacted by the proposed service and determine on a non-discriminatory basis whether a System Impact Study is needed. A description of the Transmission Provider's methodology for conducting completing a System Impact Study is provided in Attachment D. If the Transmission Provider System Operator determines that a System Impact Study is necessary to accommodate the requested service, it shall as soon as practicable thereafter the System Operator will so inform the Eligible Customer as soon as practicable. At that time, the Transmission Provider shall offer the Transmission Customer the possibility of studying conditional Firm Transmission Service and redispatch options. Once informed, the Eligible Customer shall timely notify the Transmission Provider any affected Participants if it elects to have the Transmission Provider study redispatch or conditional curtailment as part of the System Impact Study. If notification is provided prior to tender of the System Impact Study Agreementis to be performed by the Participants. If the likely NEPOOL Restated Open Access Transmission Tariff Original Sheet No. 134 result of the study is that a Direct Assignment Facility will be required, the Eligible Customer can avoid study shall be performed by the costs associated with affected Participants, subject to review by the study of these optionsSystem Operator. The Transmission Provider shallIn such cases, the System Operator will within thirty (30) days of receipt of a Completed Application, including the technical data needed to conduct the study, submit tender a System Impact Study Agreement whereby agreement in the form of Exhibit I to this Tariff, or in any other form that is mutually agreed to, pursuant to which the Eligible Customer shall agree to reimburse the Transmission Provider System Operator and any affected Participants for conducting performing the required System Impact Study. For a service request to remain a Completed Application, the Eligible Customer shall execute the System Impact Study Agreement agreement and return it to the Transmission Provider System Operator within fifteen (15) days. If the Eligible Customer elects not to execute the a System Impact Study Agreementagreement, its application shall be deemed withdrawn and its deposit shall (less the reasonable Administrative Costs incurred by the System Operator and any affected Participants in connection with the Application), will be returned with interest pursuant to Section 17.3.Interest. NEPOOL Restated Open Access Transmission Tariff Original Sheet No. 135

Appears in 1 contract

Samples: Agreement (North Atlantic Energy Corp /Nh)