Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever (a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6 (b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and (c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 7 contracts
Samples: Draft Contract Agreement, Draft Contract Agreement (Dca), Draft Contract Agreement
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway Works shall, as between the Contractor and the AuthorityEmployer, vest in the Authority Employer in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the AuthorityEmployer; and
(c) the Authority Employer shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority Employer in accordance with the provisions of this Agreement.
Appears in 2 contracts
Samples: Epc Agreement, Contract Agreement for Design and Construction
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.623.6 96
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 2 contracts
Samples: Draft Contract Agreement, Contract Agreement
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Railway Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole, free from any and all Encumbrances; provided that the foregoing shall be without prejudice to Clause 23.621.6;
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Engineering, Procurement and Construction (Epc) Agreement
Other Rights and Obligations of the Parties. β Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Construction Contract
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property Property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk Risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Construction Contract
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.,
Appears in 1 contract
Samples: Draft Contract Agreement
Other Rights and Obligations of the Parties. β Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway Works shall, as between the Contractor and the AuthorityEmployer, vest in the Authority Employer in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the AuthorityEmployer; and
(c) the Authority Employer shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority Employer in accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Demonstration Agreement
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.
Appears in 1 contract
Samples: Epc Agreement
Other Rights and Obligations of the Parties. Upon Termination for any reason whatsoever
(a) property and ownership in all Materials, Plant and Works and the Project Highway shall, as between the Contractor and the Authority, vest in the Authority in whole; provided that the foregoing shall be without prejudice to Clause 23.6
(b) risk of loss or damage to any Materials, Plant or Works and the care and custody thereof shall pass from the Contractor to the Authority; and
(c) the Authority shall be entitled to restrain the Contractor and any person claiming through or under the Agreement from entering upon the Site or any part of the Project except for taking possession of materials, stores, implements, construction plants and equipment of the Contractor, which have not been vested in the Authority in accordance with the provisions of this Agreement.in
Appears in 1 contract
Samples: Epc Agreement