Common use of Owner’s Right to Perform Work Clause in Contracts

Owner’s Right to Perform Work. The Owner reserves the right to perform construction or operations related to the Project with Separate Contractors on the Site. If the Contractor claims that delay or additional cost is because of such action by the Owner, the Contractor shall assert such claims as provided in Section 5, Part 2 of the General Conditions.

Appears in 95 contracts

Samples: Construction Contract, Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Owner’s Right to Perform Work. The Owner reserves the right to perform construction or operations related to the Project with Separate Contractors on the Site. If the Contractor Design-Builder claims that delay or additional cost is because of such action by the Owner, the Contractor Design-Builder shall assert such claims as provided in Section 5, Part 2 of the General ConditionsRequirements.

Appears in 17 contracts

Samples: Design Build Contract, Design Build Contract, Design Build Contract

Owner’s Right to Perform Work. The Owner reserves the right to perform construction or operations related to the Project with Separate Contractors on the Site. If the Contractor CM/GC claims that delay or additional cost is because of such action by the Owner, the Contractor CM/GC shall assert such claims as provided in Section 5, Part 2 of the General ConditionsRequirements.

Appears in 15 contracts

Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement

Owner’s Right to Perform Work. The Owner reserves the right to perform construction or operations related to the Project with Separate Contractors on the Site. If the Contractor claims that delay or additional cost is because of such action by the Owner, the Contractor shall assert such claims as provided in Section 5, Part 2 of the General ConditionsRequirements.

Appears in 1 contract

Samples: Design Bid Build Construction Contract

AutoNDA by SimpleDocs

Owner’s Right to Perform Work. The Owner reserves the right to perform construction or operations related to the Project with Separate Contractors other Contractors, as well as the right to award separate contracts in connection with other portions of the Project or other construction or operations on the SiteProject site under conditions of insurance and waiver of subrogation identical to the provisions of this Agreement. If the Contractor Construction Manager claims that delay or additional cost is because of such action by the Owner, the Contractor Construction Manager shall assert such claims as provided in Section 5, Part 2 of the General ConditionsContract Documents.

Appears in 1 contract

Samples: Construction Management Agreement