Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAM a. Hourly compensated MWh received from the Participant Facility to the Transmission Owner; b. Hourly compensated MVARh received from the Participant Facility to the Transmission Owner; c. Hourly compensated MWh delivered from the Transmission Owner to the Participant Facility; d. Hourly compensated MVARh delivered from the Transmission Owner to the Participant Facility; and Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.
Appears in 2 contracts
Samples: Wholesale Market Participation Agreement, Wholesale Market Participation Agreement
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – –SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAMDIAGRAM PSE&G will install the revenue metering at the Wholesale Market Participant’s termination substation as shown in Schedule A. The Wholesale Market Participant is responsible for installing equipment assuring that the following real time data is transmitted to PJM as per Manual 14D
a. Instantaneous net MW for the plant.
b. Instantaneous net MVAR for the plant. The Wholesale Market Participant is responsible for installing equipment assuring the following non real-time data is transmitted to PJM as per Manual 14D
a. Hourly compensated MWh received from delivered by the Participant Facility to the Transmission Owner;plant.
b. Hourly compensated MVARh MWh received from by the Participant Facility to the Transmission Owner;plant.
c. Hourly compensated MWh MVARh delivered from by the Transmission Owner to the Participant Facility;plant.
d. Hourly compensated MVARh delivered from received by the Transmission Owner to the Participant Facility; and Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.plant. e.
Appears in 1 contract
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAMCONDITIONS
a. Hourly compensated MWh received from the Participant Facility to the Transmission Owner;
b. Hourly compensated MVARh received from the Participant Facility to the Transmission Owner;
c. Hourly compensated MWh delivered from the Transmission Owner to the Participant Facility;
d. Hourly compensated MVARh delivered from the Transmission Owner to the Participant Facility; and Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.
Appears in 1 contract
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAMCONDITIONS
a. Hourly compensated MWh received from the Participant Facility to the Transmission Owner;
b. Hourly compensated MVARh received from the Participant Facility to the Transmission Owner;
c. Hourly compensated MWh delivered from the Transmission Owner to the Participant Facility;
d. Hourly compensated MVARh delivered from the Transmission Owner to the Participant Facility; and and
e. Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14DM-14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.
Appears in 1 contract
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – –SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAMDIAGRAM PSE&G will install the revenue metering at the Wholesale Market Participant’s termination substation as shown in Schedule A. The Wholesale Market Participant is responsible for installing equipment assuring that the following real time data is transmitted to PJM as per Manual 14D
a. Instantaneous net MW for the plant.
b. Instantaneous net MVAR for the plant. The Wholesale Market Participant is responsible for installing equipment assuring the following non real-time data is transmitted to PJM as per Manual 14D
a. Hourly compensated MWh received from delivered by the Participant Facility to the Transmission Owner;plant.
b. Hourly compensated MVARh MWh received from by the Participant Facility to the Transmission Owner;plant.
c. Hourly compensated MWh MVARh delivered from by the Transmission Owner to the Participant Facility;plant.
d. Hourly compensated MVARh delivered from received by the Transmission Owner to the Participant Facility; plant. WHOLESALE MARKET PARTICIPANT’s AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS Unexecuted Assigned WMPAs (Clean), Service Agreement Nos. 3147 and Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.3318
Appears in 1 contract
Samples: Interconnection Service Agreement
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAM
a. Hourly compensated MWh received from the Participant Facility to the Transmission Owner;
b. Hourly compensated MVARh received from the Participant Facility to the Transmission Owner;
c. Hourly compensated MWh delivered from the Transmission Owner to the Participant Facility;; and
d. Hourly compensated MVARh delivered from the Transmission Owner to the Participant Facility; and Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.
Appears in 1 contract
Ownership and Location of Metering Equipment. The metering equipment to be constructed, the capability of the metering equipment to be constructed, and the ownership thereof, as required for the Wholesale Transactions shall be identified on the attached Schedule B to this WMPA, and provided consistent with the PJM manuals. SCHEDULES: • SCHEDULE A - SINGLE-LINE DIAGRAM (Showing point of interconnection) • SCHEDULE B - LIST OF METERING EQUIPMENT • SCHEDULE C - LIST OF LOCAL/NETWORK UPGRADES • SCHEDULE D - APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS • SCHEDULE E - WHOLESALE MARKET PARTICIPANT AGREEMENT TO CONFORM WITH IRS SAFE HARBOR PROVISIONS FOR NON-TAXABLE STATUS • SCHEDULE F – SCHEDULE OF NON-STANDARD TERMS & CONDITIONS SCHEDULE A SINGLE-LINE DIAGRAM
a. Hourly compensated MWh received from the Participant Facility to the Transmission Owner;
b. Hourly compensated MVARh received from the Participant Facility to the Transmission Owner;
c. Hourly compensated MWh delivered from the Transmission Owner to the Participant Facility;
d. Hourly compensated MVARh delivered from the Transmission Owner to the Participant Facility; and and
e. Instantaneous net MW and MVar per unit values in accordance with PJM Manuals M-01 and M- 14DM-14D, and Sections 8.1 through 8.5 of Appendix 2 to the Attachment O of the PJM Tariff.
Appears in 1 contract