Payment of Final Application for Payment Sample Clauses

Payment of Final Application for Payment. Landlord shall not be obligated to make any payment under the final Application for Payment until the last to occur of (a) Landlord's receipt from Tenant of the architect's certificate of substantial completion described in Paragraph 4(n) below, (b) Landlord's receipt of final invoices marked paid or other evidence reasonably satisfactory to Landlord confirming the total amount expended by Tenant for the Work, (c) Landlord's approval of the Work as having been completed in accordance with the Approved Construction Documents, which approval shall not be unreasonably withheld, (d) Landlord's receipt of a final lien waiver in form satisfactory to Landlord, covering the release of all mechanics' and materialmen's liens or potential mechanic's and materialmen's liens that could arise from the construction of the Work from Tenant's Contractor and each person entitled to a lien under applicable law by virtue of contributing to the Work, (e) an affidavit from Tenant and Tenant's Contractor that such final lien waiver includes and covers all materials and services for which a lien could be filed, provided that Tenant may, if any subcontractor or supplier refuses to furnish a release in full, furnish a surety bond satisfactory to Landlord to indemnify Landlord, its successors and assigns, against any mechanics' or materialmen's lien, (f) Landlord's receipt of final as-built plans and specifications in a form satisfactory to Landlord and certified by Tenant's architect or engineer as accurately and completely depicting the Property as the completed Work, together with all written warranties and guaranties and all operating and maintenance manuals related to the Work, and (g) 35 days have elapsed from the last day of the month in which the Work is completed including "punch-list" items, and no affidavit as required by applicable law has been filed against the Property (or Tenant's interest therein), the Building, or the Project, or notice of a claim has been delivered to Tenant or Landlord, as a result of the Work, provided that Tenant may furnish a surety bond satisfactory to Landlord to indemnify Landlord, its successors and assigns, against any such claims.
AutoNDA by SimpleDocs
Payment of Final Application for Payment. Landlord shall not be obligated to make the final installment until the last to occur of (A) Construction Manager’s receipt from Tenant or an architect’s certificate of substantial completion certifying that the Tenant Work has been completed in accordance with all applicable Law and the Approved Construction Documents, (B) Construction Manager’s receipt of final invoices marked paid or other evidence reasonably satisfactory to Construction Manager confirming the total.

Related to Payment of Final Application for Payment

  • Application for Payment The form acceptable to Owner that is to be used by the Contractor during the course of the Work in requesting payment from the Owner and that is to be accompanied by such supporting documentation as is required by the Contract Documents.

  • Applications for Payment 9.3.1 At least ten days before the date for each progress payment established in the State- Contractor Agreement, the Contractor shall submit to the Architect an itemized Application for Payment, notarized if required, supported by such data substantiating the Contractor's right to payment as the State or the Architect may require. The application for payment must, at a minimum, reflect retainage and the required waivers of lien and any other support documentation enumerated elsewhere in the Contract Documents. 9.3.2 Unless otherwise provided in the Contract Documents, payments will be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site and, if approved in advance by the State, payments may similarly be made for materials or equipment suitably stored at some other location agreed upon in writing. Payments for materials or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the State to establish the State's title to such materials or equipment or otherwise protect the State's interest, including applicable insurance and transportation to the site for those materials and equipment stored off the site. 9.3.3 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment will pass to the State either by incorporation in the construction or upon the receipt of payment by the Contractor, whichever occurs first, free and clear of all liens, claims, security interests or encumbrances, hereinafter referred to in this Article 9 as "liens"; and that no Work, materials or equipment covered by an Application for Payment will have been acquired by the Contractor, or by any other person performing Work at the site or furnishing materials and equipment for the Project, subject to an agreement under which an interest therein or an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.

  • Due date for payment The settlement date for each Tax Invoice issued by the Distributor must be the 20th day of the month in which the Tax Invoice is received, or if the 20th day of the month is not a Working Day, the first Working Day after the 20th day. However, if the Distributor fails to send a Tax Invoice to the Trader within 10 Working Days after the last day of the month to which the Tax Invoice relates, the due date for payment is extended by 1 Working Day for each Working Day that the Tax Invoice is late.

  • Procedure for Payment Whenever a payment for fractional Rights, Preferred Shares or Common Shares is to be made by the Rights Agent pursuant to this Agreement, the Company will (i) promptly prepare and deliver to the Rights Agent a certificate setting forth in reasonable detail the facts related to such payment and the prices or formulas utilized in calculating such payments; and (ii) provide sufficient monies to the Rights Agent to make such payments. The Rights Agent will be fully protected in relying upon such certificate and will have no duty with respect thereto, and will not be deemed to have knowledge of any payment for fractional Rights, Preferred Shares or Common Shares pursuant to this Agreement unless and until the Rights Agent has received such certificate and sufficient monies.

  • Request for Payment Payment to the Grantee shall be due 30 calendar days following receipt by the City of the Grantee’s fully and accurately completed payment request, using the City’s contract management system. The payment request must be submitted to the City no later than 11:59 p.m. Central Standard Time 25 calendar days following the end of the month covered by the payment request. If the 25th calendar day falls on a weekend or holiday, as outlined in Section 8.24, the deadline to submit the payment request is extended to no later than 11:59 p.m. Central Standard Time of the 1st weekday immediately following the weekend or holiday.

  • Treatment of Unallowable Costs Previously Submitted for Payment Mallinckrodt further agrees that within 120 days of the Effective Date of this Agreement it shall identify to applicable Medicare and TRICARE fiscal intermediaries, carriers, and/or contractors, and Medicaid and FEHBP fiscal agents, any Unallowable Costs (as defined in this Paragraph) included in payments previously sought from the United States, or any State Medicaid program, including, but not limited to, payments sought in any cost reports, cost statements, information reports, or payment requests already submitted by Mallinckrodt or any of its subsidiaries or affiliates, and shall request, and agree, that such cost reports, cost statements, information reports, or payment requests, even if already settled, be adjusted to account for the effect of the inclusion of the Unallowable Costs. Mallinckrodt agrees that the United States, at a minimum, shall be entitled to recoup from Mallinckrodt any overpayment plus applicable interest and penalties as a result of the inclusion of such Unallowable Costs on previously-submitted cost reports, information reports, cost statements, or requests for payment. Any payments due after the adjustments have been made shall be paid to the United States pursuant to the direction of the Department of Justice and/or the affected agencies. The United States reserves its rights to disagree with any calculations submitted by Mallinckrodt or any of its subsidiaries or affiliates on the effect of inclusion of Unallowable Costs (as defined in this Paragraph) on Mallinckrodt or any of its subsidiaries or affiliates’ cost reports, cost statements, or information reports.

  • Time for Payment Interconnection Customer must provide the additional Security, in a form and with terms as required by Section 212.4, within 15 days after its receipt of Transmission Provider’s notice under this section. The requirement for additional Security under this section shall be treated as a milestone included in the Interconnection Service Agreement pursuant to Section 212.5.

  • Repayment of Overpayments a. If, at any time, Good Shepherd identifies any Overpayment, Good Shepherd shall repay the Overpayment to the appropriate payor (e.g., Medicare contractor) within 60 days after identification of the Overpayment and take remedial steps within 90 days after identification (or such additional time as may be agreed to by the payor) to correct the problem, including preventing the underlying problem and the Overpayment from recurring. If not yet quantified, within 60 days after identification, Good Shepherd shall notify the payor of its efforts to quantify the Overpayment amount along with a schedule of when such work is expected to be completed. Notification and repayment to the payor shall be done in accordance with the payor’s policies. b. Notwithstanding the above, notification and repayment of any Overpayment amount that routinely is reconciled or adjusted pursuant to policies and procedures established by the payor should be handled in accordance with such policies and procedures.

  • Release for Payment Upon receipt by the Collateral Custodian of the Servicer’s request for release of documents and receipt in the form annexed hereto as Exhibit M (which certification shall include a statement to the effect that all amounts received in connection with such payment or repurchase have been credited to the Collection Account as provided in this Agreement), the Collateral Custodian shall promptly release the related Required Loan Documents to the Servicer.

  • Application for Benefits Requests for short-term leaves shall be in writing, upon the appropriate form prescribed and provided by the District, and shall be filed with the unit member's supervisor and the appropriate manager five (5) days in advance of the intended leave (except in emergency situations), unless otherwise stated by the provisions of the specific leave.