Applications for Payment. 9.3.1 At least ten days before the date for each progress payment established in the State- Contractor Agreement, the Contractor shall submit to the Architect an itemized Application for Payment, notarized if required, supported by such data substantiating the Contractor's right to payment as the State or the Architect may require. The application for payment must, at a minimum, reflect retainage and the required waivers of lien and any other support documentation enumerated elsewhere in the Contract Documents.
9.3.2 Unless otherwise provided in the Contract Documents, payments will be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site and, if approved in advance by the State, payments may similarly be made for materials or equipment suitably stored at some other location agreed upon in writing. Payments for materials or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the State to establish the State's title to such materials or equipment or otherwise protect the State's interest, including applicable insurance and transportation to the site for those materials and equipment stored off the site.
9.3.3 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment will pass to the State either by incorporation in the construction or upon the receipt of payment by the Contractor, whichever occurs first, free and clear of all liens, claims, security interests or encumbrances, hereinafter referred to in this Article 9 as "liens"; and that no Work, materials or equipment covered by an Application for Payment will have been acquired by the Contractor, or by any other person performing Work at the site or furnishing materials and equipment for the Project, subject to an agreement under which an interest therein or an encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person.
Applications for Payment. Based on Engineer’s observations as an experienced and qualified design professional and on review of Applications for Payment and accompanying supporting documentation:
a) Determine the amounts that Engineer recommends Contractor be paid. Recommend reductions in payment (set-offs) based on the provisions for set- offs stated in the Construction Contract. Such recommendations of payment will be in writing and will constitute Engineer’s representation to Owner, based on such observations and review, that, to the best of Engineer’s knowledge, information and belief, Contractor’s Work has progressed to the point indicated, the Work is generally in accordance with the Construction Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Construction Contract Documents, and to any other qualifications stated in the recommendation), and the conditions precedent to Contractor’s being entitled to such payment appear to have been fulfilled in so far as it is Engineer’s responsibility to observe the Work. In the case of unit price Work, Engineer’s recommendations of payment will include final determinations of quantities and classifications of the Work (subject to any subsequent adjustments allowed by the Construction Contract Documents).
b) By recommending payment, Engineer shall not thereby be deemed to have represented that observations made by Engineer to check the quality or quantity of Contractor’s Work as it is performed and furnished have been exhaustive, extended to every aspect of Contractor’s Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to Engineer in this Agreement.
Applications for Payment. Based on Engineer’s observations as an experienced and qualified design professional and on review of Applications for Payment and accompanying supporting documentation:
a. Determine the amounts that Engineer recommends Contractor be paid. Such recommendations of payment will be in writing and will constitute Engineer’s representation to Owner, based on such observations and review, that, to the best of Engineer’s knowledge, information and belief, Contractor’s work has progressed to the point indicated, the quality of such work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, to the results of any subsequent tests called for in the Contract Documents and to any other qualifications stated in the recommendation), and the conditions precedent to Contractor’s being entitled to such payment appear to have been fulfilled in so far as it is Engineer’s responsibility to observe Contractor’s work. In the case of unit price work, Engineer’s recommendations of payment will include final determinations of quantities and classifications of Contractor’s work (subject to any subsequent adjustments allowed by the Contract Documents). The responsibilities of Engineer contained in paragraph A1.05.A.6.a are expressly subject to the limitations set forth in paragraph A1.05.A.6.b and other express or general limitations in this Agreement and elsewhere.
b. By recommending any payment, Engineer shall not thereby be deemed to have represented that observations made by Engineer to check the quality or quantity of Contractor’s work as it is performed and furnished have been exhaustive, extended to every aspect of Contractor’s work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to Engineer in this Agreement and the Contract Documents. Neither Engineer’s review of Contractor’s work for the purposes of recommending payments nor Engineer’s recommendation of any payment including final payment will impose on Engineer responsibility to supervise, direct, or control Contractor’s work in progress or for the means, methods, techniques, sequences, or procedures of construction or safety precautions or programs incident thereto, or Contractor’s compliance with Laws and Regulations applicable to Contractor’s furnishing and performing the Work. It will also not impose responsibility on Engineer to make any examination to ascer...
Applications for Payment. Subcontractor shall submit to Contractor applications for payment (each, an “Application for Payment”) in a form acceptable to Contractor no later than the 20th day of each month for the portion of the Subcontract Work performed up to and including the last day of the month. Contractor reserves the right to require Subcontractor to submit its Application for Payment electronically through Textura, at Subcontractor’s sole cost and expense, or other software in Contractor’s discretion. An Application for Payment shall be for payment for materials incorporated in the Subcontract Work and work performed in place during the time period since Subcontractor commenced the Subcontract Work or since its last Application for Payment, whichever is later. Subcontractor agrees to furnish, as and when required by Contractor, the Schedule of Values (defined below), Certified Payroll Reports, receipts, vouchers, lien waivers, releases of claims for labor, material and subcontractors performing work or furnishing materials under this Agreement, and any other documents reasonably requested by Contractor, including but not limited to a waiver or other release from one or more Trusts, all in form satisfactory to Contractor, and it is agreed that no payment hereunder shall be made, except at Contractor’s option until and unless such documents have been furnished. Contractor shall have the right, at its sole discretion and upon request, to require Subcontractor’s lower tiers to provide Certified Payroll Reports. In addition to the foregoing, prior to receiving any payment, Subcontractor must furnish Contractor with a valid certificate of insurance. Notwithstanding anything to the contrary, Contractor shall have right, at its sole discretion, to require Subcontractor to have its lower tier subcontractors and suppliers, submit invoices and lien waivers through Textura and receive payments directly from Contractor through ACH disbursements. Tier subcontractor/supplier will pay a one-time Textura fee at time of contract acceptance in Textura. Contractor will reimburse tier subcontractor/supplier within sixty (60) days of payment of fee.
Applications for Payment. (a) At least ten (10) days before the date established for each progress payment, the Prime Contractor shall submit to the Architect/Engineer an itemized Application for Payment for Work completed in accordance with the schedule of values. The Application shall be notarized, if required, and supported by data substantiating the Prime Contractor’s right to payment as the Owner or Architect/Engineer may require, including but not limited to copies of requisitions from Subcontractors and material suppliers, and reflecting the applicable retainage as required in the Contract Documents. Prime Contractor's Application for Payment shall also provide other supporting documentation as the Owner or the other applicable provisions of the Contract Documents may require.
(b) Applications for Payment may not include requests for payment of amounts the Prime Contractor does not intend to pay to a Subcontractor because of a good faith dispute, unless the Prime Contractor complies with Clause 5.3(b) (2) of these General Conditions and the Prime Contractor’s Payment Bond Surety consents in writing to payment to the Prime Contractor of the funds deemed to be in dispute.
(c) Unless otherwise provided in the Contract Documents, progress payments shall include payment for materials and equipment delivered and suitably stored at the Project site for subsequent incorporation into the Work within thirty (30) days after delivery to the Project site. If approved in advance by the Owner, payment may similarly be made for materials and equipment suitably stored away from the Project site at a location agreed upon in writing. Payment for costs incurred in storage of materials or equipment away from the Project site will NOT be made by Owner unless:
(1) the Owner has given prior approval of such off-site storage in writing;
(2) the materials or equipment are stored in a bonded warehouse located in Xxxxxx County and identified with the Project for which they are stored, as evidenced by warehouse receipts and appropriate documents of title; and
(3) the materials or equipment stored off-site will be incorporated into the Work within thirty (30) days after delivery. STORAGE IN FACILITIES OF THE MANUFACTURER OR THE PRIME CONTRACTOR WILL NOT BE PERMITTED OR PAID FOR, UNLESS THE OWNER HAS EXPRESSLY GIVEN PRIOR APPROVAL OF SUCH STORAGE IN WRITING.
(d) The Prime Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payme...
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Design-Builder shall submit to the Owner an itemized Application for Payment for completed portions of the Work. The application shall be notarized, if required, and supported by data substantiating the Design-Builder’s right to payment as the Owner may require, such as copies of requisitions from the Architect, Consultants, Contractors, and material suppliers, and shall reflect retainage if provided for in the Design-Build Documents. § 9.3.1.1 As provided in Section 6.3.9, Applications for Payment may include requests for payment on account of changes in the Work that have been properly authorized by Change Directives, or by interim determinations of the Owner, but not yet included in Change Orders.
Applications for Payment. At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documents.
Applications for Payment. Contractor shall submit to Owner and, if directed, Architect, a periodic Application for Payment. The Application for Payment shall consist of the cost of the Project as set forth in the Schedule of Values. Approval of Application for Payments for such materials stored off- site shall be conditioned upon submission by Contractor of bills of sale and applicable insurance or such other procedures satisfactory to Owner to establish Owner’s title to such materials, or otherwise to protect Owner’s interest, including transportation to the Worksite. The extent of such statement shall be as agreed upon between Owner and Contractor. Payment shall be subject to the retainage requirements of Wyo. Stat. § 16-6-702. If an interest bearing account per Wyo. Stat. § 16-6-704 is established the account holders shall include the District, and Contractor. The Owner, Architect and Contractor will set a schedule for Submittal and Approval of Pay Applications to be followed during the preconstruction meeting.
Applications for Payment. Based on the CONSULTANT's on-site observations as an experienced and qualified design professional and on review of applications for payment and the accompanying data and schedules, the CONSULTANT shall determine the amounts owing to the Contractor(s) and recommend in writing payments to the Contractor(s) in such amounts: such recommendations of payment will constitute a representation to the CITY, based on such observations and review, that the work has progressed to the point indicated, and that, to the best of the CONSULTANT's knowledge, information and belief, the quality of such work is generally in accordance with the Construction Contract Documents, drawings and specifications (subject to an evaluation of such work as a functioning Project upon Substantial Completion, to the results of any subsequent tests called for in the Construction Contract Documents, and to any qualifications stated in his recommendation), and that payment of the amount recommended is due to the Contractor(s); but by recommending any payment, the CONSULTANT will not thereby be deemed to have represented that continuous or exhaustive examinations have been made by the CONSULTANT to check the quality or quantity of the work or impose on the CONSULTANT responsibility to supervise, direct, or control such work, or for the means, methods, sequences, techniques or procedures of construction or safety precautions or program incident thereto, or that the CONSULTANT has made an examination to ascertain how or for what purposes any Contractor has used the moneys paid on account of the Contract Price, or that title to any of the work, materials or equipment has passed to the CITY free and clear of any lien, claims, security interests or encumbrances, or that the Contractor(s) have completed their work exactly in accordance with the Contract Documents, drawings and specifications.
Applications for Payment. § 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect an itemized Application for Payment prepared in accordance with the schedule of values, if required under Section 9.2, for completed portions of the Work. The application shall be notarized, if required, and supported by all data substantiating the Contractor’s right to payment that the Owner or Architect require, such as copies of requisitions, and releases and waivers of liens from Subcontractors and suppliers, and shall reflect retainage if provided for in the Contract Documents.
§ 9.3.1.1 As provided in Section 7.3.9, such applications may include requests for payment on account of changes in the Work that have been properly authorized by Construction Change Directives, or by interim determinations of the Architect, but not yet included in Change Orders.
§ 9.3.1.2 Applications for Payment shall not include requests for payment for portions of the Work for which the Contractor does not intend to pay a Subcontractor or supplier, unless such Work has been performed by others whom the Contractor intends to pay.
§ 9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for materials and equipment suitably stored off the site at a location agreed upon in writing. Payment for materials and equipment stored on or off the site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the Owner to establish the Owner’s title to such materials and equipment or otherwise protect the Owner’s interest, and shall include the costs of applicable insurance, storage, and transportation to the site, for such materials and equipment stored off the site.
§ 9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment all Work for which Certificates for Payment have been previously issued and payments received from the Owner shall, to the best of the Contractor’s knowledge, information, and belief, be free and clear of liens, claims, security interests, or encumbrances, in favor of the Contractor, Subcontractors, suppliers, or other persons or e...