Pedestrian Bridge. 5.7.1. The Plans include a pedestrian bridge (the “Bridge”), to be constructed by Lessee to connect the Project to the Venetian/Palazzo hotel complex at a point of interconnection (the “Interconnection Point”). 5.7.2. Lessor and Lessee shall cooperate in good faith in the implementation of the Bridge at the Interconnection Point, consistent with the Concept Drawings that were approved as part of the Agreement to Lease. In that regard, Lessee shall prepare and submit to Lessor, at Lessee’s expense, schematic drawings with respect to the design specifications of the Bridge, including the Interconnection Point (the “Bridge Schematic Drawings”). Within thirty (30) days of receiving the Bridge Schematic Drawings, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any other points where the Bridge physically connects to the Sands Expo Center improvements or land (collectively, “Other Physical Connection Points”), such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge Schematic Drawings that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge Schematic Drawings, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge Schematic Drawings, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge Schematic Drawings. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge Schematic Drawings, desires to make any changes from what was previously approved by Lessor in the Concept Drawings that were approved as part of the Agreement to Lease, then any direct incremental cost increases (including the costs of revising the Bridge Schematic Drawings) associated with such relocation shall be borne by Lessor. 5.7.3. Subsequent to the approval of the Bridge Schematic Drawings in accordance with Section 5.7.2 above, Lessee shall prepare and submit to Lessor, at Lessee’s expense, design development drawings consistent with the Bridge Schematic Drawings (the “Bridge DD Documents”). Within thirty (30) days of receiving the Bridge DD Documents, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any Other Physical Connection Points, in each case only to the extent that the Bridge DD Documents disclose new information not previously shown on the Bridge Schematic Drawings, such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge DD Documents that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge DD Documents, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge DD Documents, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge DD Documents. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge DD Documents, desires to make any changes from what was previously approved by Lessor in the approved Bridge Schematic Drawings, then any direct incremental cost increases (including the costs of revising the Bridge DD Documents) associated with such relocation shall be borne by Lessor. 5.7.4. Subsequent to the approval of the Bridge DD Documents in accordance with Section 5.7.3 above, Lessee shall prepare and submit to Lessor, at Lessee’s expense, construction drawings with respect to the Bridge, including the Interconnection Point (the “Bridge Construction Drawings”). Within thirty (30) days of receiving the Bridge Construction Drawings, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any Other Physical Connection Points, in each case only to the extent that the Bridge Construction Drawings disclose new information not previously shown on the Bridge DD Documents, such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge Construction Drawings that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge Construction Drawings, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge Construction Drawings, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge Construction Drawings. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge Construction Drawings, desires to make any changes from what was previously approved by Lessor in the approved Bridge DD Documents, then any direct incremental cost increases (including the costs of revising the Bridge Construction Drawings) associated with such relocation shall be borne by Lessor. 5.7.5. Throughout the Bridge construction process, Lessee will consult and coordinate with Lessor (with update meetings to occur no less frequently than quarterly). Without limiting the generality of the foregoing, in the course of construction of the Project in accordance with the terms and conditions of this Lease, Lessor and Lessee shall cooperate in good faith on issues related to construction staging, crane overhang, and construction parking. 5.7.6. Lessee shall use commercially reasonable efforts to cause Lessor to be named as a third-party beneficiary of any contractor or manufacturer warranties in favor of Lessee in respect of the construction of the Interconnection Point and any other portion of the Bridge located on the Sands Expo Center property. 5.7.7. In the course of construction of the Bridge, Lessee shall comply with the terms and conditions of all agreements with Xxxx Sunrise LLC, a Nevada limited liability company (“Xxxx”), pertaining to the Bridge and recorded against title to the Premises (collectively, and as may be amended from time to time by Xxxx and Lessee, the “Xxxx Bridge Agreements”). Lessor shall reasonably cooperate with Lessee, at no out of pocket cost or expense to Lessor, in connection with any amendments or assignments of or supplements to the Xxxx Bridge Agreements necessary for the construction and operation of the Project, provided that any such amendments do not result in a material adverse impact on the Venetian/Palazzo Resort or the Sands Expo Center.
Appears in 4 contracts
Samples: Ground Lease (MSG Entertainment Spinco, Inc.), Ground Lease (MSG Entertainment Spinco, Inc.), Construction Agreement (Madison Square Garden Co)
Pedestrian Bridge. 5.7.1. The Plans include a pedestrian bridge (the “Bridge”), to be constructed by Lessee to connect the Project to the Venetian/Palazzo hotel complex at a point of interconnection (the “Interconnection Point”).
5.7.2. Lessor and Lessee shall cooperate in good faith in the implementation of the Bridge at the Interconnection Point, consistent with the Concept Drawings that were approved as part of the Agreement to Lease. In that regard, Lessee shall prepare and submit to Lessor, at Lessee’s expense, schematic drawings with respect to the design specifications of the Bridge, including the Interconnection Point (the “Bridge Schematic Drawings”). Within thirty (30) days of receiving the Bridge Schematic Drawings, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any other points where the Bridge physically connects to the Sands Expo Center improvements or land (collectively, “Other Physical Connection Points”), such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge Schematic Drawings that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge Schematic Drawings, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge Schematic Drawings, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge Schematic Drawings. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge Schematic Drawings, desires to make any changes from what was previously approved by Lessor in the Concept Drawings that were approved as part of the Agreement to Lease, then any direct incremental cost increases (including the costs of revising the Bridge Schematic Drawings) associated with such relocation shall be borne by Lessor.
5.7.3. Subsequent to the approval of the Bridge Schematic Drawings in accordance with Section 5.7.2 above, Lessee shall prepare and submit to Lessor, at Lessee’s expense, design development drawings consistent with the Bridge Schematic Drawings (the “Bridge DD Documents”). Within thirty (30) days of receiving the Bridge DD Documents, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any Other Physical Connection Points, in each case only to the extent that the Bridge DD Documents disclose new information not previously shown on the Bridge Schematic Drawings, such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge DD Documents that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge DD Documents, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge DD Documents, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge DD Documents. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge DD Documents, desires to make any changes from what was previously approved by Lessor in the approved Bridge Schematic Drawings, then any direct incremental cost increases (including the costs of revising the Bridge DD Documents) associated with such relocation shall be borne by Lessor.
5.7.4. Subsequent to the approval of the Bridge DD Documents in accordance with Section 5.7.3 above, Lessee shall prepare and submit to Lessor, at Lessee’s expense, construction drawings with respect to the Bridge, including the Interconnection Point (the “Bridge Construction Drawings”). Within thirty (30) days of receiving the Bridge Construction Drawings, Lessor shall determine whether to approve (a) the Interconnection Point and (b) any Other Physical Connection Points, in each case only to the extent that the Bridge Construction Drawings disclose new information not previously shown on the Bridge DD Documents, such approval not to be unreasonably withheld, conditioned, or delayed. Any disapproval shall be in writing and shall specify the specific reasons for the denial and the changes to the Bridge Construction Drawings that would render them acceptable, at which time Lessor and Lessee shall promptly meet and confer in good faith to resolve such issues. If Lessor fails to respond to the above request for approval within thirty (30) days of receipt of the Bridge Construction Drawings, then Lessee may send Lessor a second notice requesting Lessor’s approval of the Bridge Construction Drawings, which notice shall be in accordance with the Deemed Approval Process set forth in Section 34 hereof. If Lessor fails to respond to such second notice within fifteen (15) days, Lessor shall be deemed to have approved such Bridge Construction Drawings. Notwithstanding the foregoing, if Lessor, in connection with its review of the Bridge Construction Drawings, desires to make any changes from what was previously approved by Lessor in the approved Bridge DD Documents, then any direct incremental cost increases (including the costs of revising the Bridge Construction Drawings) associated with such relocation shall be borne by Lessor.
5.7.5. Throughout the Bridge construction process, Lessee will consult and coordinate with Lessor (with update meetings to occur no less frequently than quarterly). Without limiting the generality of the foregoing, in the course of construction of the Project in accordance with the terms and conditions of this Lease, Lessor and Lessee shall cooperate in good faith on issues related to construction staging, crane overhang, and construction parking.
5.7.6. Lessee shall use commercially reasonable efforts to cause Lessor to be named as a third-party beneficiary of any contractor or manufacturer warranties in favor of Lessee in respect of the construction of the Interconnection Point and any other portion of the Bridge located on the Sands Expo Center property.
5.7.7. In the course of construction of the Bridge, Lessee shall comply with the terms and conditions of all agreements with Xxxx Sunrise LLC, a Nevada limited liability company (“Xxxx”), pertaining to the Bridge and recorded against title to the Premises (collectively, and as may be amended from time to time by Xxxx and Lessee, the “Xxxx Bridge Agreements”). Lessor shall reasonably cooperate with Lessee, at no out of pocket cost or expense to Lessor, in connection with any amendments or assignments of or supplements to the Xxxx Bridge Agreements necessary for the construction and operation of the Project, provided that any such amendments do not result in a material adverse impact on the Venetian/Palazzo Resort or the Sands Expo Center.Construction
Appears in 2 contracts
Samples: Construction Agreement (MSG Entertainment Spinco, Inc.), Construction Agreement (MSG Entertainment Spinco, Inc.)