Performance of Changed or Extra Work Sample Clauses

Performance of Changed or Extra Work. As a condition precedent to the DB Contractor’s right to receive additional payment or an extension of a Completion Deadline for changed or extra work, the DB Contractor shall have received either a Directive Letter from the District stating that it is issued pursuant to Section 15 or a Change Order for such work executed by the District. To the extent that the DB Contractor undertakes any such work without receiving a Directive Letter or Change Order executed by the District, the DB Contractor shall be deemed to have performed such work voluntarily and may not be entitled to a Change Order in connection therewith. In addition, the DB Contractor may be required to remove or otherwise undo any such work at its sole cost.
AutoNDA by SimpleDocs
Performance of Changed or Extra Work. Contractor’s receipt of a Change Order executed by VPRA or a Directive Letter is a condition precedent to Contractor’s right to receive an adjustment to the Contract Price or a Completion Deadline for changed or Extra Work, provided that VPRA’s failure to execute a Change Order or Directive Letter does not negate Contractor’s right to pursue the Relief Event process in the event of a dispute over entitlement to relief. If Contractor undertakes any such work without receiving a Directive Letter or Change Order executed by VPRA, Contractor shall be deemed to have performed such work voluntarily and will not be entitled to a Change Order for performing that work. In addition, VPRA has the right to require Contractor to remove or otherwise undo any such voluntary work, at Contractor’s sole cost.

Related to Performance of Changed or Extra Work

  • Performance of Work by City If the Contractor fails to perform the Work in accordance with the schedule referred to in section 2 above, the City may, in its discretion, in order to bring the project closer to the schedule, perform or cause to be performed some or all of the Work, and doing so shall not waive any of the City’s rights and remedies. Before doing so, the City shall give the Contractor notice of its intention. The Contractor shall reimburse the City for additional costs incurred by the City in exercising its right to perform or cause to be performed some or all of the Work pursuant to this section.

  • Performance of the Work The Contractor shall perform all of the Work required for the complete and prompt execution of everything described or shown in, or reasonably implied from the Contract Documents for the above referenced Project.

  • Performance of Services The Contractor is responsible for fully meeting all obligations set forth in the Contract and for providing Product in accordance with the Contract or any Authorized User Agreement.

  • Performance of Service 2.1 Appendix A (General Provisions), Articles 1 through 16, governs the performance of services under this contract. 2.2 Appendix B sets forth the liability and insurance provisions of this contract. 2.3 Appendix C sets forth the services to be performed by the contractor. ARTICLE 3.

  • Performance of Work The Work shall be constructed in a good and workmanlike manner substantially in accordance with the Construction Plans. The Work shall be subject, at the option of Landlord, to the inspection of Landlord, Landlord's Architect and Landlord's General Contractor from time to time, during the period in which the Work is being performed, provided that such inspection does not unreasonably interfere with the completion of the Work. If such inspections reveal that any of the Work is not being constructed substantially in conformance with the provisions of this Agreement or the Final Plans, Tenant at its expense shall correct same forthwith. Only new, first class materials shall be used in the performance of the Work. At all times during the construction of the Work, it shall be Tenant's responsibility to cause each of Tenant's contractors and subcontractors to maintain protection of the Premises in such a manner as to prevent any damage to the Work, or to adjacent property and improvements by reason of the performance of the Work. Tenant's contractor and subcontractors shall properly secure the Premises, including, to the extent required, the furnishing of temporary guard rails and barricades. Landlord for good cause shall have the right to require Tenant to terminate any construction work at any time being performed by or on behalf of Tenant in the Premises, and to require that any contractor or subcontractor, or any employee of same, leave the Building. Upon written notification, setting forth in reasonable detail such good cause, from Landlord to Tenant to cease any work, Tenant shall forthwith remove from the Premises all agents, employees and contractors of Tenant performing such work until such time as Landlord shall have given its written consent for the resumption of such construction work (such consent not to be unreasonably withheld or delayed), and Tenant shall have no claim for damages of any nature whatsoever against Tenant in connection therewith.

  • Performance while Dispute is Pending Notwithstanding the existence of a dispute, the Supplier must continue without delay to carry out all of its responsibilities under the Contract that are not affected by the dispute. If the Supplier fails to continue without delay to perform its responsibilities under the Contract, in the accomplishment of all undisputed work, the Supplier will bear any additional costs incurred by Sourcewell and/or its Participating Entities as a result of such failure to proceed.

  • PERFORMANCE OF THE CONTRACT II.1.1 The Contractor shall perform the Contract to the highest professional standards. The Contractor shall have sole responsibility for complying with any legal obligations incumbent on him, notably those resulting from employment, tax and social legislation.

  • Performance Delay Time is of the essence in the Vendor’s performance of this Agreement. If at any time it appears to Vendor that it may not meet any of the performance schedules or the scheduled completion date of the services to be performed for any reason, including labor disputes, Vendor shall immediately by verbal means (to be confirmed in writing) notify Customer of the reasons for and the estimated duration of such delay. If requested by Customer, Vendor shall make every effort to avoid or minimize the delay to the maximum extent possible including the expenditure of premium time. Any additional cost caused by these requirements of Customer shall be borne by Vendor, unless the delay in performance arises out of causes beyond the control and without the fault or negligence of Vendor or its subcontractors within the meaning of the Cancellation- Default clause herein. The foregoing requirements are in addition to any of Customer’s other rights and remedies as may be provided by law or this Agreement.

  • Performance of Agreement Purchaser shall have performed in all material respects all obligations and agreements and complied in all material respects with all covenants and conditions contained in this Agreement to be performed or complied with by it at or prior to the Closing Date.

  • Performance Warranty Contractor shall warrant all work under this Contract, taking necessary steps and precautions to perform the work to County’s satisfaction. Contractor shall be responsible for the professional quality, technical assurance, timely completion and coordination of all documentation and other goods/services furnished by the Contractor under this Contract. Contractor shall perform all work diligently, carefully, and in a good and workmanlike manner; shall furnish all necessary labor, supervision, machinery, equipment, materials, and supplies, shall at its sole expense obtain and maintain all permits and licenses required by public authorities, including those of County required in its governmental capacity, in connection with performance of the work. If permitted to subcontract, Contractor shall be fully responsible for all work performed by subcontractors.