Possession of the Site. 21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.
Appears in 56 contracts
Samples: nahep.icar.gov.in, nahep.icar.gov.in, Guru Nanak
Possession of the Site. 21.1 24.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data Special Conditions of Contract, the Employer is will be deemed to have delayed the start of the relevant activities activities, and this will be a Compensation Event.
Appears in 12 contracts
Samples: Contract Agreement, Contract Agreement, Contract Agreement
Possession of the Site. 21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.cause of Extension of the Intended Completion Date
Appears in 2 contracts
Samples: ofbcipher.s3.amazonaws.com, ofbcipher.s3.amazonaws.com
Possession of the Site. 21.1 21.1. The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.
Appears in 2 contracts
Samples: ofbcipher.s3.amazonaws.com, Civil Works
Possession of the Site. 21.1 The Employer shall give possession of all parts of the Site to the Contractor. If the possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.
Appears in 2 contracts
Samples: Tender Agreement, Agreement
Possession of the Site. 21.1 The Employer Engineer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data and in any case not later than the Employer date when it is actually required for carrying out the work, the Engineer is deemed to have delayed the start of the relevant activities for that part of the site and this will be Compensation Event.
Appears in 1 contract
Samples: www.pidb.org
Possession of the Site. 21.1 21.1. The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in statedin the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.
Appears in 1 contract
Samples: ofbcipher.s3.amazonaws.com
Possession of the Site. 21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data Data, the Employer is will be deemed to have delayed the start of the relevant activities activities, and this will be a Compensation Event.
Appears in 1 contract
Samples: Civil Works Contract