Common use of Power Factor Design Criteria Clause in Contracts

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO has established different requirements that apply to all generators in the Balancing Authority Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H of this LGIA.

Appears in 48 contracts

Samples: Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

AutoNDA by SimpleDocs

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators.

Appears in 10 contracts

Samples: Surplus Large Generator Interconnection Agreement, Surplus Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain be capable of maintaining a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a all power factor within the range of factors over 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Local Balancing Authority Area on a comparable basis. Power The applicable Local Balancing Authority power factor design criteria for wind generators requirements are provided in Appendix H of this LGIA.listed on the Transmission Provider’s website at

Appears in 8 contracts

Samples: Generator Interconnection Agreement, Generator Interconnection Agreement, Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO ISO has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix Part H of this LGIA.

Appears in 4 contracts

Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the minimum range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators.

Appears in 3 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Balancing Authority AuthorityControl Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H of this LGIA.

Appears in 2 contracts

Samples: Standard Large Generator Interconnection Agreement (Lgia), Standard Large Generator Interconnection Agreement (Lgia)

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators. Non-synchronous generators shall only be required to maintain the above power factor when their output is above 10 percent of the Generating Facility Capacity.

Appears in 2 contracts

Samples: Large Generator Interconnection Agreement, Large Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Distribution Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators; rather, the requirements of Appendix G shall apply to wind generators.

Appears in 1 contract

Samples: Service Agreement for Wholesale Distribution Service

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain be capable of maintaining a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a all power factor within the range of factors over 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Local Balancing Authority Area on a comparable acomparable basis. Power The applicable Local Balancing Authority power factor design criteria for wind generators requirements are provided in Appendix H of this LGIA.listed on the Transmission Provider’s website at

Appears in 1 contract

Samples: Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO ISO has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H of this LGIA.

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)

AutoNDA by SimpleDocs

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the minimum range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Transmission Provider has established different requirements that apply to all generators in the Balancing Authority Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H Unless otherwise required by Applicable Laws and Regulations or Applicable Reliability Standards, the requirements of this LGIAparagraph shall not apply to wind generators.

Appears in 1 contract

Samples: Transitional Cluster Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Distribution Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for The requirements of this paragraph shall not apply to wind generators are provided in generators; rather, the requirements of Appendix H of this LGIAshall apply to wind generators.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO has established different requirements that apply to all generators in the Balancing Authority Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H of this LGIA.comparable

Appears in 1 contract

Samples: Large Generator Interconnection Agreement

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Distribution Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators; rather, the requirements of Appendix HH shall apply to wind generators.

Appears in 1 contract

Samples: Clustering Large Generator Interconnection Agreement (Giaclgia)

Power Factor Design Criteria. The Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals Point of the Electric Generating Unit Interconnection at a power factor within the range of 0.95 leading to 0.90 0.95 lagging, unless the CAISO Distribution Provider has established different requirements that apply to all generators in the Balancing Authority Control Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H The requirements of this LGIAparagraph shall not apply to wind generators; rather, the requirements of Appendix G shall apply to wind generators.

Appears in 1 contract

Samples: Generator Interconnection Agreement (Gia)

Power Factor Design Criteria. The For all Generating Facilities other than Asynchronous Generating Facilities, the Interconnection Customer shall design the Large Generating Facility to maintain a composite power delivery at continuous rated power output at the terminals of the Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90 lagging, unless the CAISO has established different requirements that apply to all generators in the Balancing Authority Area on a comparable basis. Power factor design criteria for wind generators are provided in Appendix H of this LGIA.that

Appears in 1 contract

Samples: Large Generator Interconnection Agreement (Lgia)