Common use of Pre-Toll Operations Readiness Deadline Clause in Contracts

Pre-Toll Operations Readiness Deadline. The Joint Board shall assess and TSP shall pay $2,500 per day Delay Liquidated Damages with respect to each day from and after the Pre-Toll Operations Readiness Deadline to and including the date that TSP achieves Pre-Toll Operations Readiness, but not to exceed 90 days, for TSP’s failure to achieve TOC Pre-Toll Operations Readiness by the Pre-Toll Operations Readiness Deadline.

Appears in 6 contracts

Samples: Toll Services Agreement, Toll Services Agreement, Toll Services Agreement