Procedure for Achieving Commercial Operation Sample Clauses

Procedure for Achieving Commercial Operation. Seller shall deliver to Buyer a written notice that describes in reasonable detail Seller’s schedule for achieving any remaining Commercial Operation Conditions and the anticipated Commercial Operation Date (the “Commercial Operation Notice”) thirty (30) days prior to the anticipated Commercial Operation Date. When Seller believes the requirements of the Commercial Operation Conditions have been met, Seller shall provide Buyer with written notice certifying the satisfaction of the Commercial Operation Conditions, together with reasonable documentation and such other information as Buyer may reasonably request for Buyer to evaluate whether or not Seller has satisfied the Commercial Operation Conditions. If Buyer disagrees with Seller’s determination, Buyer must provide Seller notice of such disagreement, together with an explanation of the basis for such disagreement, within ten (10) Business Days following its receipt of Seller’s notice and supporting documentation. If Buyer so notifies Seller of such disagreement, the Parties shall review the supporting documentation and promptly resolve the dispute and determine whether or not the Commercial Operation Conditions have been satisfied. In the event the disagreement remains unresolved within thirty (30) days, either party may initiate the dispute resolution procedures in Section 11.10.
AutoNDA by SimpleDocs

Related to Procedure for Achieving Commercial Operation

  • Synchronization, Commissioning and Commercial Operation 4.1.1 The Power Producer shall give at least fifteen (15) days written notice to the SLDC / ALDC / DISCOM as the case may be, of the date on which it intends to synchronize the Power Project to the Grid System. 4.1.2 Subject to Article 4.1.1, the Power Project may be synchronized by the Power Producer to the Grid System when it meets all the connection conditions prescribed in the Grid Code and otherwise meets all other Indian legal requirements for synchronization to the Grid System. 4.1.3 The synchronization equipment and all necessary arrangements / equipment including Remote Terminal Unit (RTU) for scheduling of power generated from the Project and transmission of data to the concerned authority as per applicable regulation shall be installed by the Power Producer at its generation facility of the Power Project at its own cost. The Power Producer shall synchronize its system with the Grid System only after the approval of GETCO / SLDC / ALDC and GEDA. 4.1.4 The Power Producer shall immediately after each synchronization / tripping of generator, inform the sub-station of the Grid System to which the Power Project is electrically connected in accordance with applicable Grid Code. 4.1.5 The Power Producer shall commission the Project within SCOD. 4.1.6 The Power Producer shall be required to obtain Developer and/ or Transfer Permission, Key Plan drawing etc, if required, from GEDA. In cases of conversion of land from Agricultural to Non-Agriculture, the commissioning shall be taken up by GEDA only upon submission of N.A. permission by the Power Producer. 4.1.7 The Power Producer shall be required to follow the Forecasting and Scheduling procedures as per the Regulations issued by Hon’ble GERC from time to time. It is to clarify that in terms of GERC (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2019 the procedures for Forecasting, Scheduling & Deviation Settlment are applicable to all solar generators having combined installed capacity above 1 MW connected to the State Grid / Substation including those connected via pooling stations.

  • Commercial Operation (i) On or before December 31, 2021, Interconnection Customer must demonstrate commercial operation of all generating units. Demonstrating commercial operation includes achieving Initial Operation in accordance with Section 1.4 of Appendix 2 to this ISA and making commercial sales or use of energy, as well as, if applicable, obtaining capacity qualification in accordance with the requirements of the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region.

  • Commercial Milestones (a) Within [*****] calendar days after the end of the first Calendar Year in which aggregate annual Net Sales for that Calendar Year for the Licensed Product in the Territory reach any threshold indicated in the Commercial Milestone Events listed below, EverInsight shall notify VistaGen of the achievement of such Commercial Milestone Event and VistaGen shall invoice EverInsight for the corresponding non-refundable, non-creditable Milestone Payment set forth below and EverInsight shall remit payment to VistaGen within [*****] Business Days after the receipt of the invoice, as described in Section 8.6 (Currency; Exchange Rate; Payments). Annual Net Sales Milestones for Licensed Product Milestone Payments (in Dollars) (each a “Commercial Milestone Event”): (1). [*****] (2). [*****] (3). [*****] (4). [*****] (5). [*****] (b) For the purposes of determining whether a Net Sales Milestone Event has been achieved, Net Sales of Licensed Product(s) in the Territory shall be aggregated. For clarity, the annual Net Sales Milestone Payments set forth in this Section 8.3 (Commercial Milestones) shall be payable only once, upon the first achievement of the applicable Commercial Milestone Event, regardless of how many times such Commercial Milestone Event is achieved. (c) If a Commercial Milestone Event in Section 8.3 (Commercial Milestones) is achieved and payment with respect to any previous Commercial Milestone Event in Section 8.3 has not been made, then such previous Commercial Milestone Event shall be deemed achieved and EverInsight shall notify VistaGen within fifteen (15) calendar days of such achievement. VistaGen shall then invoice EverInsight for such unpaid previous Commercial Milestone Event(s) and EverInsight shall pay VistaGen such unpaid previous milestone payment(s) within thirty (30) Business Days of receipt of such invoice. (d) In the event that, VistaGen believes any Commercial Milestone Event under Section 8.3(a) has occurred but EverInsight has not given VistaGen the notice of the achievement of such Commercial Milestone Event, it shall so notify EverInsight in writing and shall provide to EverInsight data, documentation or other information that supports its belief. Any dispute under this Section 8.3(d) (Commercial Milestones - subsection (d)) that relates to whether or not a Commercial Milestone Event has occurred shall be referred to the JSC to be resolved in accordance with ARTICLE 3 (Governance) and shall be subject to resolution in accordance with Section 14.10 (Dispute Resolution). The Milestone Payments made for each Commercial Milestone Event shall be non-creditable and non-refundable.

  • Commercial Operation Date 6.4.1 The SPV shall ensure that the Project Commercial Operation Date is achieved on or prior to the Scheduled Commercial Operation Date. The SPV shall provide a written notice to MSEDCL at least 30 (thirty) days in advance intimating MSEDCL of the proposed date on which the Commercial Operation Date of a Unit or the Project is proposed to be achieved. 6.4.2 If the Commercial Operation Date for the Units having a capacity equivalent to at least 75% (seventy five percent) of the Contracted Capacity is achieved before the Scheduled Commercial Operation Date, then all Units in respect of which the Commercial Operation Date has been achieved prior to the Scheduled Commercial Operation Date would be eligible for incentives as follows: (a) the Unit(s) injecting energy at 11 kV /22 kV shall be given an incentive of Rs. 0.25/ kWh; and (b) the Unit(s) injecting energy at 33 kV shall be given an incentive of Rs. 0.15/ kWh, for the power sold to MSEDCL for the first 3 (three) years from the Commercial Operation Date. To receive such incentives from MSAPL, which shall be over and above the Tariff, the SPV shall follow the process agreed to by the SPV under the Implementation Agreement. 6.4.3 It is hereby clarified that the aforementioned incentive shall not be available: (i) in respect of any Unit if the Commercial Operation Date for such Unit has not been achieved prior to the Scheduled Commercial Operation Date; and (ii) if the aggregate capacity of the Units for which the Commercial Operation Date has been achieved prior to Scheduled Commercial Operation Date is less than 75% (seventy five percent) of the Contracted Capacity. 6.4.4 In the event that Commercial Operation Date for any of the Units is achieved after the Scheduled Commercial Operation Date, the SPV shall be liable to pay Liquidated Damages as per the provisions set out below. 6.4.5 Without prejudice to any other rights of MSEDCL under this PPA, in case one or more Units of the SPV are unable to achieve Commercial Operation Date within a period of 2 (two) months from the Scheduled Commercial Operation Date, the capacity of such Units shall be annulled, and the Contracted Capacity shall be reduced to that extent. For Illustration: The Project has a Contracted Capacity of 100 MW and comprises of 10 Units of 10 MW each. If at the end of the aforementioned period of 14 (fourteen) months from the Effective Date, the SPV has achieved Commissioning for only 8 out of 10 Units, then the Contracted Capacity of the Project will stand reduced for the capacity of the 2 Units which have not been Commissioned, i.e. the Contracted Capacity will be 80 (100 (original Contracted Capacity)) – 10 (capacity of each Unit)*2 (number of Units not Commissioned).

  • DEVELOPMENT OR ASSISTANCE IN DEVELOPMENT OF SPECIFICATIONS REQUIREMENTS/ STATEMENTS OF WORK

  • Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Project Specific Milestones In addition to the milestones stated in Section 212.5 of the Tariff, as applicable, during the term of this ISA, Interconnection Customer shall ensure that it meets each of the following development milestones: 6.1 Substantial Site work completed. On or before December 31, 2020 Interconnection Customer must demonstrate completion of at least 20% of project site construction. At this time, Interconnection Customer must submit to Interconnected Transmission Owner and Transmission Provider initial drawings, certified by a professional engineer, of the Customer Interconnection Facilities. 6.2 Delivery of major electrical equipment. On or before December 31, 2021, Interconnection Customer must demonstrate that all generating units have been delivered to Interconnection Customer’s project site.

  • Development Phase contractual phase initiated with the approval of ANP for the Development Plan and which is extended during the Production Phase while investments in xxxxx, equipment, and facilities for the Production of Oil and Gas according to the Best Practices of the Oil Industry are required.

  • Project/Milestones Taxpayer provides refrigerated warehousing and logistic distribution services to clients throughout the United States. In consideration for the Credit, Taxpayer agrees to invest in a new refrigeration and distribution facility in the XxXxxxxxx Park area of Sacramento, California, and hire full-time employees (collectively, the “Project”). Further, Taxpayer agrees to satisfy the milestones as described in Exhibit A (“Milestones”) and must maintain Milestones for a minimum of three (3) taxable years thereafter. In the event Taxpayer employs more than the number of full-time employees, determined on an annual full-time equivalent basis, than required in Exhibit A, for purposes of satisfying the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” Taxpayer may use the salaries of any of the full-time employees hired within the required time period. For purposes of calculating the “Minimum Annual Salary of California Full-time Employees Hired” and the “Cumulative Average Annual Salary of California Full-time Employees Hired,” the salary of any full-time employee that is not employed by Taxpayer for the entire taxable year shall be annualized. In addition, the salary of any full-time employee hired to fill a vacated position in which a full-time employee was employed during Taxpayer’s Base Year shall be disregarded.

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving (either itself or through the acts of a SUBLICENSEE) the following development milestones in its diligence activities under this AGREEMENT: (a) (b).