Programme. The Contractor shall submit a time programme to the Contract Awarder after the Commencement Date. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's obligations. Unless otherwise stated in the Contract, each programme shall include: (a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works, (b) the periods for reviews under Sub-Clause 5.2 [Contractor's Documents], (c) the sequence and timing of inspections and tests specified in the Contract, and (d) a supporting report which includes: (i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the Works, and (ii) the approximate number of each class of Contractor's Personnel and of each type of Contractor's Equipment for each major stage. Unless the Contract Awarder, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Contract Awarder's Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall promptly give notice to the Contract Awarder of specific probable future events or circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Contract Awarder gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a revised programme to the Contract Awarder in accordance with this Sub-Clause.
Appears in 2 contracts
Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)
Programme. The Contractor shall submit a detailed time programme to the Contract Awarder Engineer within 28 days after receiving the notice under Sub-Clause 8.1 [Commencement Dateof Works]. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's ’s obligations. Unless otherwise stated in the Contract, each Each programme shall include:
(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Worksdesign (if any), Contractor’s Documents, procurement, manufacture of Plant, delivery to Site, construction, erection and testing,
(b) the periods each of these stages for reviews under Sub-work by each nominated Subcontractor (as defined in Clause 5.2 5 [Contractor's DocumentsNominated Subcontractors]),
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the Contractor intends to adopt for adopt, and of the major stages, in the execution of each major stage of the Works, and
(ii) details showing the approximate Contractor’s reasonable estimate of the number of each class of Contractor's ’s Personnel and of each type of Contractor's Equipment ’s Equipment, required on the Site for each major stage. Unless the Contract AwarderEngineer, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Contract Awarder's Employer’s Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall promptly give notice to the Contract Awarder Engineer of specific probable future events or circumstances which may adversely affect the work, increase the Contract Price or delay the execution of the Works. In this eventThe Engineer may require the Contractor to submit an estimate of the anticipated effect of the future event or circumstances, or if and/or a proposal under Sub-Clause 13.3 [Variation Procedure]. If, at any time, the Contract Awarder Engineer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's ’s stated intentions, the Contractor shall submit a revised programme to the Contract Awarder Engineer in accordance with this Sub-Clause.
Appears in 1 contract
Samples: Unit Price Contract
Programme. 7.1 The Contractor shall submit a detailed time programme to Programme for the Contract Awarder execution of the Works within 7 (seven) days of after receiving the Commencement Date. Notice for “commencement of Works”.
7.2 The Employer shall provide comments or Notice of No-objection for the time Programme within 7 (seven) days of receiving the detailed time Programme.
7.3 The Contractor shall also submit a revised programme Programme within 7 (seven) days whenever the previous programme Programme is inconsistent with actual progress or with the Contractor's obligations. Unless otherwise stated in The revised Programme shall be within the Contract, each programme Employer’s approved Time for Completion. Each Programme shall include:
(a) the Commencement Date and the Time for Completion of the Works;
b) The order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works,
design (b) the periods for reviews under Sub-Clause 5.2 [if any), Contractor's Documents],documents, procurement, construction, erection and testing.
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a A supporting report which includes:
(i) includes a general description of the methods which the Contractor intends to adopt for and of the major stages in the execution of each major stage of the Works, and
(ii) and the approximate number of each class of Contractor's Personnel ’s personnel and of each type of Contractor's ’s Equipment for each major stage. Unless .
d) the Contract Awardersequence and timing of inspections and tests specified in, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with or required by the Contract;
e) for a revised Programme and for each activity: the actual progress to date, any delay to such progress and the Contractor shall proceed in accordance with effects of such delay on other activities (if any); If at any time the programme, subject to his other obligations under the Contract. The Contract Awarder's Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall promptly give notice to the Contract Awarder of specific probable future events or circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Contract Awarder Employer gives notice to the Contractor that a programme Programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall within 7 (seven) days submit a revised programme Programme to the Contract Awarder Employer in accordance with this Sub-Clause.
Appears in 1 contract
Samples: Conditions of Contract
Programme. 7.1 The Contractor shall submit a detailed time programme to Programme for the Contract Awarder execution of the Works within 3 (three) calendar days of after receiving the Commencement Date. Notice for “commencement of Works”.
7.2 The Employer shall provide comments or Notice of No-objection for the time Programme within 7 (seven) calendar days of receiving the detailed time Programme.
7.3 The Contractor shall also submit a revised programme Programme within 7 (seven) calendar days whenever the previous programme Programme is inconsistent with actual progress or with the Contractor's obligations. Unless otherwise stated in The revised Programme shall be within the Contract, each programme Employer’s approved Time for Completion. Each Programme shall include:
(a) the Commencement Date and the Time for Completion of the Works;
b) The order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works,
design (b) the periods for reviews under Sub-Clause 5.2 [if any), Contractor's Documents],documents, procurement, construction, erection and testing.
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a A supporting report which includes:
(i) includes a general description of the methods which the Contractor intends to adopt for and of the major stages in the execution of each major stage of the Works, and
(ii) and the approximate number of each class category of Contractor's Personnel ’s personnel and of each type of Contractor's ’s Equipment for each major stage. Unless .
d) the Contract Awardersequence and timing of inspections and tests specified in, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with or required by the Contract;
e) for a revised Programme and for each activity: the actual progress to date, any delay to such progress and the Contractor shall proceed in accordance with effects of such delay on other activities (if any); If at any time the programme, subject to his other obligations under the Contract. The Contract Awarder's Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall promptly give notice to the Contract Awarder of specific probable future events or circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Contract Awarder Employer gives notice to the Contractor that a programme Programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall within 7 (seven) days submit a revised programme Programme to the Contract Awarder Employer in accordance with this Sub-Clause.
8. 8.1 Commencement Date shall be the date on which the Contractor obtains Commencement and the right of access to Site as per Sub-clause 4.1, and, the right of access Completion of the Works to the Site is deemed to be provided on the date the Employer issues Notice of commencement to the Contractor.
Appears in 1 contract
Samples: Conditions of Contract
Programme. The If a time programme has not been included as part of the executed Contract, then the Contractor shall submit a time programme to the Contract Awarder Employer within 28 days after the Commencement Date. If the Contractor fails to comply with the milestones as stated in the time programme, the Employer may withhold any scheduled payments due until the milestone as stated in the original time programme has been met. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's obligationsobligations as soon reasonably practicable. Unless otherwise stated in the Contract, each programme shall include:
(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works,;
(b) the sequence and timing of completion and submission to the Employer of Contract Documents for review under Sub-Clause 5.2 [Contractor's Documents];
(c) the periods for reviews under Sub-Clause 5.2 [Contractor's Documents],;
(cd) the sequence and timing of inspections and tests specified in the Contract, ; and
(de) a supporting report which includes:
(i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the Works, ; and
(ii) the approximate number of each class of Contractor's Personnel and of each type of Contractor's Equipment for each major stage. Unless the Contract AwarderEmployer, within 21 days after receiving a programme, gives notice to the Contractor stating the extent to which it does not comply with the Contract, the Contractor shall proceed in accordance with the programme, subject to his other obligations under the Contract. The Contract AwarderEmployer's Personnel shall be entitled to rely upon the programme when planning their activities. The Contractor shall shaI1 promptly give notice to the Contract Awarder Employer of specific probable future events or circumstances which may adversely affect or delay the execution of the Works. In this event, or if the Contract Awarder gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentionsintentions and the Employer gives notice to the Contractor of such failure or inconsistency, the Contractor shall submit a revised programme to the Contract Awarder Employer in accordance with this Sub-Clause.
Appears in 1 contract
Samples: Contract Agreement (Asia Satellite Telecommunications Holdings LTD)