Progress Reports and Phase 1 Project Oversight by the Township Sample Clauses

Progress Reports and Phase 1 Project Oversight by the Township. During the construction of the Phase 1 Project, the Redeveloper shall make periodic reports, in such detail and at such times as may reasonably be requested by the Township, as to the actual progress of Redeveloper with respect to such construction. If so requested by the Township, Redeveloper agrees to attend periodic progress meetings during the period of implementation of the Phase 1 Project, as follows:
AutoNDA by SimpleDocs

Related to Progress Reports and Phase 1 Project Oversight by the Township

  • Progress Reports The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.

  • Progress Reports and Invoices The goals of this subtask are to: (1) periodically verify that satisfactory and continued progress is made towards achieving the project objectives of this Agreement; and (2) ensure that invoices contain all required information and are submitted in the appropriate format. The Recipient shall: • Submit a monthly Progress Report to the CAM. Each progress report must: o Summarize progress made on all Agreement activities as specified in the scope of work for the preceding month, including accomplishments, problems, milestones, products, schedule, fiscal status, and an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. See the Progress Report Format Attachment for the recommended specifications. • Submit a monthly or quarterly Invoice that follows the instructions in the “Payment of Funds” section of the terms and conditions, including a financial report on Match Fund and in-state expenditures. Products: • Progress Reports • Invoices

  • Progress Report 10.1 If required, you shall submit progress reports in connection with the Service (“Report”) on at least a monthly basis, or as we may require. The Report shall include a summary of the activities and accomplishments during the previous reporting period.

  • Project Overview The Statement of Work (SOW) documents the Project Scope, methodology, roles and responsibilities, implementation Stages, and deliverables for the implementation of Tyler products. The Project goals are to offer City of Xxxxx Creek, GA the opportunity to make the City more accessible and responsive to external and internal customer needs and more efficient in its operations through:  Streamlining, automating, and integrating business processes and practices  Providing tools to produce and access information in a real‐time environment  Enabling and empowering users to become more efficient, productive and responsive  Successfully overcoming current challenges and meeting future goals

  • Quarterly Progress Reports The goal of this task is to periodically verify that satisfactory and continued progress is made towards achieving the objectives of this Agreement on time and within budget. The objectives of this task are to summarize activities performed during the reporting period, to identify activities planned for the next reporting period, to identify issues that may affect performance and expenditures, and to form the basis for determining whether invoices are consistent with work performed. The Recipient shall: • Prepare a Quarterly Progress Report which summarizes all Agreement activities conducted by the Recipient for the reporting period, including an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. Progress reports are due to the CAM the 10th day of each January, April, July, and October. The Quarterly Progress Report template can be found on the ECAMS Resources webpage available at xxxxx://xxx.xxxxxx.xx.xxx/media/4691. Product: • Quarterly Progress Reports

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • Progress Reporting 5. The IP will submit to UNICEF narrative progress reports against the planned activities contained in the Programme Document, using the PDPR. Unless otherwise agreed between the Parties in writing, these reports will be submitted at the end of every Quarter. The final report will be submitted no later than thirty (30) calendar days after the end the Programme and will be provided together with the FACE form.

  • Project Reports; Completion Report 1. The Recipient shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 2.06 of the Standard Conditions and on the basis of indicators agreed with the World Bank. Each Project Report shall cover the period of one (1) calendar semester, and shall be furnished to the World Bank not later than one (1) month after the end of the period covered by such report.

  • Progress Reports and Information When required, the Contractor shall submit to the Owner such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Owner may request that concerns the Work performed or to be performed under this Contract. When requested by the Owner, the Contractor shall give the Owner access to its records relating to the foregoing. (See also Article 1.2.3, Audits.) The above reports shall include, but are not limited to, (a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which Non-Compliant Work will be made good, (c) written notice that Non-Compliant Work has been made good, (d) written notice as to the date or dates by which Work that has not been performed with equal steps and at the same rate required by the Overall Project Schedule shall have been brought into conformity with the Overall Project Schedule, (e) date by which any undisputed claim of a Subcontractor, Supplier, or laborer shall have been paid, (f) written advice regarding the nature and amount of any disputed claim of a Subcontractor, Supplier, or laborer, and (g) information regarding Work performed under Change Orders.

  • Project Completion Report At the completion of construction and once a Project is placed in service, the Subrecipient must submit a Project Completion Report that includes the total number of units built and leased, affordable units built and leased, DR-MHP units built and leased, an accomplishment narrative, and the tenants names, demographics and income for each DR-MHP unit.