Project Labor Agreement. (a) Unless extended by NYSERDA, Seller shall, no later than 30 days after the date of BOEM’s approval of the COP for the Selected Project, present to NYSERDA for its review a plan outlining its intentions with respect to the negotiation of a PLA to cover construction activities within the United States (including in federal waters) on the Selected Project. NYSERDA should be kept reasonably apprised of negotiations as they proceed, and NYSERDA shall have the right to have one or more representatives attend negotiation sessions as it determines is in its best interests. A final form of PLA, agreed to by Seller and the trades, consistent with the description in Exhibit J to this Agreement shall be presented to NYSERDA for review and approval no later than 180 days after BOEM’s approval of the COP for the Selected Project (unless extended by NYSERDA, which request for extension shall not be unreasonably withheld, conditioned, or delayed).
Appears in 2 contracts
Samples: Sale Agreement, Renewable Energy Certificate Purchase and Sale Agreement
Project Labor Agreement. (a) Unless extended by NYSERDA, Seller shall, no later than 30 thirty (30) days after the date Effective Date of BOEM’s approval of the COP for the Selected Projectthis Agreement, present to NYSERDA for its review a plan outlining its intentions with respect to the negotiation of a PLA one or more PLAs to cover all construction activities within the United States (including in federal waters) on the Selected Project. NYSERDA should be kept reasonably apprised of negotiations as they proceed, and NYSERDA shall have the right to have one or more representatives attend negotiation sessions as it determines is in its best interests. A final form of each PLA, agreed to by Seller and the trades, consistent with the description in Exhibit J to this Agreement shall be presented to NYSERDA for review and approval no later than 180 one hundred eighty (180) days after BOEMXXXX’s approval of the COP for the Selected Project (unless extended by NYSERDA, which request for extension shall not be unreasonably withheld, conditioned, or delayed).
Appears in 1 contract
Samples: Renewable Energy Certificate Purchase and Sale Agreement
Project Labor Agreement. (a) Unless extended by NYSERDA, Seller shall, no later than 30 thirty (30) days after the date of BOEM’s approval of the COP for the Selected ProjectApproval, present to NYSERDA for its review a plan outlining its intentions with respect to the negotiation of a PLA one or more PLAs to cover all construction activities within the United States (including in federal waters) on the Selected Project. NYSERDA should be kept reasonably apprised of negotiations as they proceed, and NYSERDA shall have the right to have one or more representatives attend negotiation sessions as it determines is in its best interests. A final form of each PLA, agreed to by Seller and the trades, consistent with the description in Exhibit J to this Agreement shall be presented to NYSERDA for review and approval no later than 180 one hundred eighty (180) days after BOEMXXXX’s approval of the COP for the Selected Project (unless extended by NYSERDA, which request for extension shall not be unreasonably withheld, conditioned, or delayed).
Appears in 1 contract
Samples: portal.nyserda.ny.gov
Project Labor Agreement. (a) Unless extended by NYSERDA, Seller shall, no later than 30 days after the date of BOEMXXXX’s approval of the COP for the Selected Project, present to NYSERDA for its review a plan outlining its intentions with respect to the negotiation of a PLA to cover construction activities within the United States (including in federal waters) on the Selected Project. NYSERDA should be kept reasonably apprised of negotiations as they proceed, and NYSERDA shall have the right to have one or more representatives attend negotiation sessions as it determines is in its best interests. A final form of PLA, agreed to by Seller and the trades, consistent with the description in Exhibit J to this Agreement shall be presented to NYSERDA for review and approval no later than 180 days after BOEM’s approval of the COP for the Selected Project (unless extended by NYSERDA, which request for extension shall not be unreasonably withheld, conditioned, or delayed).
Appears in 1 contract
Samples: Purchase and Sale Agreement