PROJECT RECORD DOCUMENTS. 2.10.1. CM@Risk understands and agrees that during the construction period, it shall maintain at the jobsite a set of blueline or blackline prints of the Construction Document drawings and shop drawings for Project Record Document purposes. Said Construction Document drawings shall be updated and made available to City for verification on a monthly basis from the date of first submission. 2.10.2. CM@Risk understands and agrees that it shall mark these drawings to indicate the actual installation where the installation varies appreciably from the original Construction Documents. CM@Risk shall specifically indicate information on concealed elements that would be difficult to identify or measure and record later. Items required to be indicated and marked shall include, but are not limited to the following: 2.10.3. CM@Risk understands and agrees that it shall mark completely and accurately Project 2.10.4. CM@Risk understands and agrees that CM@Risk shall be responsible for the creation of record and as-built drawings as the work progresses, and the procurement of warranties and guarantees. CM@Risk shall also mark Project Record Drawings sets with red erasable colored pencil. 2.10.5. CM@Risk understands and agrees that CM@Risk shall note RFI Numbers, Change Order numbers, etc., as required to identify the source of the change to the Construction Documents. 2.10.6. CM@Risk understands and agrees that CM@Risk shall as a condition of Substantial Completion, submit Project Record Drawing and Shop Drawings prints to the OPT for review and comment. 2.10.7. CM@Risk understands and agrees that upon receipt of the reviewed Project Record Drawings from the OPT, the CM@Risk shall correct any deficiencies and/or omissions to the drawings and re-submit to the OPT within fourteen (14) Days. 2.10.8. CM@Risk understands and agrees that Final Record Drawings shall be produced by Design Professional.
Appears in 3 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
PROJECT RECORD DOCUMENTS. 2.10.1. CM@Risk understands and agrees that during the construction period, it shall maintain at the jobsite a set of blueline or blackline prints of the Construction Document drawings and shop drawings for Project Record Document purposes. Said Construction Document drawings shall be updated and made available to City for verification on a monthly basis from the date of first submission.
2.10.2. CM@Risk understands and agrees that it shall mark these drawings to indicate the actual installation where the installation varies appreciably from the original Construction Documents. CM@Risk shall specifically indicate information on concealed elements that would be difficult to identify or measure and record later. Items required to be indicated and marked shall include, but are not limited to the following:: • Dimensional changes to the drawings. • Revisions to details shown on drawings • Depths of foundations below first floor • Locations and depths of underground utilities • Revisions to routing of piping and conduits. • Revisions to electrical circuitry. • Actual equipment locations. • Duct size and routing. • Locations of concealed internal utilities. • Changes made by Change Order. • Details not on original Contract Drawings.
2.10.3. CM@Risk understands and agrees that it shall mark completely and accurately ProjectProject Record Drawing prints of Construction Documents or Shop Drawings, whichever is the most capable of indicating the actual physical condition. Where Shop Drawings are marked, show cross-reference on the Construction Documents’ location.
2.10.4. CM@Risk understands and agrees that CM@Risk shall be responsible for the creation of record and as-built drawings as the work progresses, and the procurement of warranties and guarantees. CM@Risk shall also mark Project Record Drawings sets with red erasable colored pencil.
2.10.5. CM@Risk understands and agrees that CM@Risk shall note RFI Numbers, Change Order numbers, etc., as required to identify the source of the change to the Construction Documents.
2.10.6. CM@Risk understands and agrees that CM@Risk shall as a condition of Substantial Completion, submit Project Record Drawing and Shop Drawings prints to the OPT for review and comment.
2.10.7. CM@Risk understands and agrees that upon receipt of the reviewed Project Record Drawings from the OPT, the CM@Risk shall correct any deficiencies and/or omissions to the drawings and re-submit to the OPT within fourteen (14) Days.
2.10.8. CM@Risk understands and agrees that Final Record Drawings shall be produced by Design Professional.
Appears in 1 contract