Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary. 4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2. 4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2: (a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder; (b) total monetary value of construction work performed for each of the last five years; (c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts; (d) major items of construction equipment proposed to carry out the Contract; (e) qualifications and experience of key site management and technical personnel proposed for the Contract; (f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years; (g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources); (h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer (i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute; (j) If any of item of works found to be subcontracted and their performance not satisfied in the opinion of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor. (k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones 4.4 Joint ventures
Appears in 3 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Qualification of the Bidder. 4.1 2.1 All bidders shall provide in Section 2IV, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all 2.2 All bidders shall include the following information and documents with their bids in Section 2IV :
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;Bid.
(b) total monetary value of construction work performed for each of the last five three years;
(c) experience in works of a similar nature and size for each of the last five three years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed as well as readily available to carry out the Contract;
(e) major items of laboratory equipments proposed & readily available for setting up of laboratory at the site for soil testing, concrete testing and other essential materials testing in line with design requirement including readily availability of survey equipments like digital total stations, GPS etc .
(f) qualifications and experience of key site management and technical personnel proposed for the Contract;Contract and number of labourers proposed to be employed for the work.
(fg) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(gh) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(hi) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(ij) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five 3 (three) years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(jk) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion of the Corporation of Chennai, the bidder relevant field should immediately terminate services of the subcontractor.be annexed); and
(kl) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint ventures.
Appears in 2 contracts
Samples: Turnkey Contract, Turnkey Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years:
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of Chennaicivil engineering construction works only) of Rs 60 lac @ (usually not less than two times the estimated annual payments under the contract);
(b) satisfactorily completed (not less than 90% of contract value), as a prime contractor, at least one similar work of value not less than Rs 25 lac @ (usually not less than 80% of estimated value of contract);
(c) deleted;
(d) The contractor or his identified sub-contractor should possess required valid electrical license for executing the building electrification works and should have executed similar electrical works totalling Rupees .............@** in any one year N/a
(e) The contractor or his identified sub-contractor should possess required valid license for executing the water supply/sanitary engineering works and should have executed similar water supply/sanitary engineering works totalling Rupees .................@** in any one year N/a * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received. ** at least 50% of the estimated value of electrical/ water supply works. @ at —————* price level. Financial turnover and cost of completed works of previous years shall be given weightage of 5% per year based on rupee value to bring them to —————* price level.
4.5 B. Deleted.
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder should immediately terminate services must demonstrate having experience and resources sufficient to meet the aggregate of the subcontractorqualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in para 4.5 (kA) above.
4.7 Bidders who meet the proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to minimum qualification criteria will be adopted, justifying qualified only if their capability of execution and completion of available bid capacity is more than the work total bid value. The available bid capacity will be calculated as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesunder: Assessed Available Bid capacity = ( A*N*1.5 - B )
Appears in 2 contracts
Samples: Bidding Agreement, Bidding Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation of Chennaicontract, each bidder in its name should have in the bidder should immediately terminate services of the subcontractor.last five years: i.e *
(ka) the proposed methodology and program achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability works only) of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesRs...
Appears in 2 contracts
Samples: Project Agreement, Civil Works Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 190.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 152.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 13900 Cum - Cement Concrete 900 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work:
1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 02 Nos - 01 Nos 3 Tippers/Truck (10 tones) - 05 Nos 4 Water Tanker (5000 liters) - 04 Nos 5 Vibrator - 03 Nos 6 Compaction Unit - 01 Nos 7 Concrete Mixer - 03 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 24.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary. The proposed methodology should include programme of construction backed with equipment planning and deployment duly supported with broad calculations and quality assurance procedures proposed to be adopted justifying their capability of execution and completion of work as per technical specifications, within stipulated period of completion.
4.2 In All bidders shall furnish the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any following information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
(i) Evidence of access to or availability of credit facilities (minimum 10% of notified contract value) certified by the bankers.
(ii) Deleted.
(iii) Deleted.
(iv) Power of attorney.
(v) Latest income tax-clearance certificate from concerned department.
4.3 If the Employer has not undertaken prequalification pre-qualification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:.
(a) copies Copies of original documents defining the constitution or of legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;.
(b) total Total monetary value of construction work performed for each of the last five years;.
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;Deleted
(d) major Major items of construction equipment proposed to carry out the Contract;.
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;.
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports ’s report for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resourcesresources facilities (10% of contract value) (certified by the Bankers (not more than 3 months old);. (as per format at Section-7 of Bid document,)
(h) authority undertaking that the bidder will be able to invest a minimum cash upto 25 % of contract value of work, during implementation of work.
(i) Authority to seek references from the Bidder's ’s bankers; - 9 - Signature of the Tenderer
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If Information regarding any of item of works found to be subcontracted and their performance not satisfied litigation, current or during the last five years, in which the opinion of the Corporation of ChennaiBidder is involved, the bidder should immediately terminate services of the subcontractorparties concerned, and disputed amount.
(k) the Deleted.
(l) The proposed methodology and program programme of construction including Environmental Management Planconstruction, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bid from Joint venturesVenture are acceptable for value of the contract more than Rs 15 ( fifteen) Crore
(A) To qualify for award of the contract, each bidder in its name should have in the last five years, i.e. 2008-2009, 2009-2010, 2010-2011, 2011-2012, 2012-13
(a) Achieved a minimum annual financial turnover (in all classes of civil engineering construction works only) of 67% of the estimated cost of the Package (Cost of completed works of previous years shall be given weightage of 10% per year base on rupee value to bring them to present price level) in any one year.
(b) Satisfactorily completed (not less than 90% of contract value) as a prime contractor at least one Major Bridge work of value not less than one third of the estimated cost of package within last five year.
(c) A certificate in this regard should be furnished by the bidder. The certificate so submitted must be obtained from the concerned authority not below the rank Executive Engineer for timely completion of the already allotted work under him. The certificate should be submitted as per following format .
(d) Executed in any one year, the minimum quantities of the major items of work as indicated in Appendix (not less than 40% of the estimated quantity). Cement concrete work (including RCC & PSC):- Earthwork in both excavation, embankment and subgrade. GSB WBM/WMM BM/DBM SDBC/BC Premix carpet Pile foundation / Pile length= RCC in bridge Super Structure = PSC in Bridge Superstructure = *(e) The bidder should have successfully executed and completed at least one Bridge within last 5 years with minimum three Span Continuous PSC Girder Superstructure, constructed with cantilever construction method, with Over all Span length of minimum 101.10 m and central span length of minimum 49.00 m. Documentary evidence should be furnished. .
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Joint ventures(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 131.00 Lakhs
Appears in 1 contract
Samples: Balance Work of Restructuring & Modernization of Siloda Tank and Their Canal Systems
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13 Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 72.00 lakh
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 347.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 278.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 64000 Cum - Cement Concrete 1500 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - 03 Nos Dozer (D-6 or equivalent) - 01 Nos Tippers/Truck (10 tones) - 10 Nos Water Tanker (5000 liters) - 08 Nos Vibrator - 06 Nos Compaction Unit - 02 Nos Concrete Mixer - 06 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 44.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 558.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 447.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 57600 Cum - Cement Concrete 3330 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 2 Tippers/Truck (10 tones) - 06 Nos 3 Water Tanker (5000 liters) - 06 Nos 4 Vibrator - 04 Nos 5 Compaction Unit - 01 Nos 6 Concrete Mixer - 04 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 70.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 151.00 Lacs. (usually not less than two times the estimated annual payments under the contract);
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 110.00 Lacs.(usually not less than 80% of estimated valve of contract) * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received.
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 15300 Cum - Cement Concrete 300 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - 02 Nos 3 Tippers/Truck (10 tones) - 04 Nos 4 Water Tanker(5000 liters) - 04 Nos 6 Compaction Unit - 02 No 7 Concrete Mixer - 02 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 19.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 413.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 275.50 Lakhs
(c) Executed in any one year, the following minimum quantities of work: Earthwork 55600 cum Cement Concrete 2,850 cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: S. No. Item of equipment Requirement No. Capacity 1 Excavator 02 1.00 cum Capacity 2 Truck Dumper 06 4 cum Capacity 3 Concrete Mixer Xxxxxx 03 1 cement bag Capacity 4 Vibrator 03 1.5 HP Capacity 5 Water Tanker 06 5000 liter Capacity 6 Compaction unit 01 8 to 10 Ton Capacity Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 51.65 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Restructuring and Modernization of Distribution System of Kethan Tank
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;. NOTE: Similar works means any work satisfying all of the following:
(i) work of development of buildings and facilities with built-up area not less than 7000 square meter including site development for a site of 2.0 acres or more; or if a part of larger campus development, work of development of buildings and facilities with built-up area not less than 7000 square meter including site development for a site of 2.0 acres or more.
(ii) work is for the purpose of and use as a) a research facility or laboratory, or b) a premier educational institution offering graduate and post-graduate degrees recognized by relevant national regulators, or c) a corporate office of a company listed with the National Stock Exchange of India Ltd, or the Bombay Stock Exchange Ltd.
(iii) the buildings included in work should include at least two of the following four elements: a) laboratories, b) offices, c) large classrooms with minimum seating of 45,) and d) convention or auditorium facility for 200 persons.
(iv) the scope of works completed by the bidder should include all of the following: a) site works including internal roads, paving, and water storage tanks, b) reinforced cement concrete frame structure with areas having exposed concrete finish, c) concrete block work walls with plastering, and d) floor and wall finishes which include stone, IPS, tile flooring and paint finishes.
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones. Provide specific construction work plan / method / strategy and schedule to be employed with respect to the work. The project includes for furniture fit-out and other interior works by a Client nominated contractor within the project master schedule. The construction program should indicate stagewise handover of buildings for works by interior contractor Include response to site parameters and proposed building design, if any. Provide sketch plan with respect to construction site layout and details pertaining to deployment of machinery / equipment .
(l) The bidder and all the identified sub-contractors should have established quality control (QC) or quality assurance (QA) policies for the company (include the certified copies of the QC/QA policies along with the bid). The bidder and all the identified sub-contractors should have established environment, health and safety (EHS) policies; and should include in the bid the proposals for ensuring compliance to environmental, health and safety concerns, and include details of deployment of qualified environmental engineer(s) and safety engineer(s).
4.4 ‘Bids from Joint venturesventures are not acceptable’.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2008-09 to 2012-13
(a) achieved, in at least two financial year, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs.60 Crores
Appears in 1 contract
Samples: Construction Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre-qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work are as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 94.32
Appears in 1 contract
Samples: Renovation Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub- contracting is acceptable); and
4.4 ‘Bids from Joint ventures are not acceptable’.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years i.e *
(a) achieved, in at least one financial years, a minimum annual financial turnover (in all classes of Chennai, civil engineering construction works only) of Rs @((i) not less than the bidder should immediately terminate services estimated value of the subcontractor.
(k) the proposed methodology and program of construction including Environmental Management Plancontract for which bids are invited, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated if period of completion is one year or less; and (ii) not less than the estimated annual payments under the contract, if period of completion is more than one year)
(b) Satisfactorily completed(not less than 90% of contract value), as a prime contractor(or as subcontractor duly certified by the employer/main contractor) a similar work in one or maximum three contracts totaling value not less than Rs @ (80% of estimated value
(d) Deleted
(e) Deleted * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received. @ at —————* price level. Financial turnover and cost of completed works of previous years shall be given weightage of 5% per milestonesyear based on rupee value to bring them to price level.
4.4 Joint ventures4.5 B. Deleted
Appears in 1 contract
Samples: Punjab Rural Water Supply & Sanitation Project Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years: i.e2008-2013*
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of Chennaicivil engineering construction works only) of R 10000000/-. @ (usually not less than two times the estimated annual payments under the contract);
(b) satisfactorily completed (not less than 90% of contract value), as a prime contractor, at least one similar work of value not less than Rs 4000000/- @ (usually not less than 80% of estimated value of contract);
(c) deleted;
(d) The contractor or his identified sub-contractor should possess required valid electrical license for executing the bidder building electrification works and should immediately terminate services of the subcontractorhave executed similar electrical works totaling Rupees 125000/-@** in any one year.
(ke) The contractor or his identified sub-contractor should possess required valid license for executing the proposed methodology water supply/sanitary engineering works and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to should have executed similar water supply/sanitary engineering works totaling Rupees125000/-.@** in any one year. * Specify the financial years; they should be adopted, justifying their capability of execution and completion those immediately preceding the financial year in which the bids are received. ** at least 50% of the work as estimated value of electrical/ water supply works. @ at 2013-14* price level. Financial turnover and cost of completed works of previous years shall be given weightage of 5% per technical specifications within the stipulated period of completion as per milestonesyear based on rupee value to bring them to 2013-14* price level.
4.4 Joint ventures4.5 B. Deleted.
Appears in 1 contract
Samples: Bidding Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 105.50
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 496.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 364.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 23600 Cum - Cement Concrete 3300 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weightage of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - 02 Nos 2 Tippers/Truck (10 tones) - 08 Nos 3 Water Tanker(5000 liters) - 04 Nos 4 Vibrator - 04 Nos 5 Compaction Unit - 01 Nos 6 Concrete Mixer - 04 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 62.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 117.20 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 93.75
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 2.1 All bidders shall provide in Section 2IV, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all 2.2 All bidders shall include the following information and documents with their bids in Section 2IV :
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;Bid.
(b) total monetary value of construction work performed for each of the last five three years;
(c) experience in works of a similar nature and size for each of the last five three years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed as well as readily available to carry out the Contract;
(e) major items of laboratory equipments proposed & readily available for setting up of laboratory at the site for soil testing, concrete testing and other essential materials testing in line with design requirement including readily availability of survey equipments like digital total stations, GPS etc .
(f) qualifications and experience of key site management and technical personnel proposed for the Contract;Contract and number of labourers proposed to be employed for the work.
(fg) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(gh) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(hi) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(ij) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five 3 (three) years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(jk) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion of the Corporation of Chennai, the bidder relevant field should immediately terminate services of the subcontractor.be annexed); and
(kl) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Joint ventures2.3 Consortium bids are acceptable. Bids submitted by a consortium of two or three firms as partners shall comply with the following requirements :
Appears in 1 contract
Samples: Turnkey Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable); and
4.4 ‘Bids from Joint ventures are not acceptable’.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years i.e. 2007-08 to 2011-12:*
(a) achieved, in at least one financial years, a minimum annual financial turnover(in all classes of Chennaicivil engineering construction works only) of Rs. 29.00 Lacs
(b) Satisfactorily completed(not less than 90% of contract value), as a prime contractor(or as subcontractor duly certified by the employer/main contractor) a similar work in one or maximum three contracts totaling value not less than Rs. 23.00 Lacs (c) Deleted. (d) Deleted. (e) Deleted.
4.5 B. Deleted.
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder should immediately terminate services must demonstrate having experience and resources sufficient to meet the aggregate of the subcontractorqualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in 4.5 (kA) (b, d and e) above.
4.7 Bidders who meet the proposed methodology and program minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: where A = Maximum value of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed civil engineering works executed in any one year during the last five years (updated to be adopted, justifying their capability 2012-13* price level) taking into account the completed as well as works in progress. N = Number of execution and years prescribed for completion of the work as per technical specifications within works for which bids are invited or one year, whichever is higher. B = Value, at 2012-13* price level, of existing commitments and on-going works to be completed during the stipulated next one years (period of completion as per milestonesof the works for which bids are invited)
4.4 Joint ventures4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Punjab Rural Water Supply & Sanitation Project Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 199.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 160.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Cement concrete (including RCC and PSC) 1300 cum -
(d) Deleted (e) Deleted @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Qty Capacity
1. Hydraulic Excavator 4 No. 10 cum 2. Concrete xxxxxx Mixer 4 Nos 3 to 5 cum 3. Power rolled compactor 2 No 8 Tonne
4. Truck / Dumper 4 Nos 8 cum 5. Water Tanker 4 Nos 6000 Ltr.
Appears in 1 contract
Samples: Restructuring and Modernizations of Balance Work of Khirawali Tank and It’s Canal System
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Proof of registration with APWD with copy of photo ID proof (photocopy of driving license/PAN Card/bank passbook with photograph etc.)
c) Copy of up to date Trade License issued by Guwahati Municipal Corporation.
d) Total monetary value of civil construction work performed for during each of the last three for works up to Rs 50.00 Lakhs/five years;years for works above 50.00 Lakhs (To be certified by a Chartered Accountant); (Not mandatory for works up to Rs 10 Lakhs)
(ce) experience Experience in works of a similar nature and size for each of the last three/five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;; (Not mandatory for works up to Rs 10 Lakhs)
(df) major Major items of construction equipment proposed to carry out the Contract;
(eg) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(fh) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's ’s reports for the past three years for works up to Rs 50.00 Lakhs/five years;years for works above 50.00 Lakhs; (Not mandatory for works up to Rs 10 Lakhs)
(gi) evidence Evidence of adequacy of working capital for this contract (access to line (sline(s) of credit and availability of other financial resourcesResources facilities (25% of Contract value), certified by the Bankers (Not more than 3 months old) ;
(hj) authority Undertaking that the bidder will be able to invest a minimum cash of 25% of contract value of work, during implementation of the work.
k) Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(il) information Information regarding any litigation pending in any court of law or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(jm) If any of item of works found to be subcontracted and their performance not satisfied in the opinion of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.
(k) the The proposed methodology and program of construction including Environmental Management Plan, Plan backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones. (Not mandatory for works up to Rs 10 Lakhs)
4.4 Joint venturesA. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2014-15, 2013-14, 2012-13, 2011-12, 2010-11:
a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of 1½ times the
b) satisfactorily completed (not less than 50% of contract value), as a prime contractor, (or as subcontractor duly certified by the employer) at least one similar work of value not less than 80% of the estimated package value; (Not applicable for works of value up to Rs 10.00 Lakhs) c) Deleted.
4.4 B. Each bidder should further demonstrate:
a) availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1. Earth Vibratory Road Roller 8 – 10 t static weight 5 1 3. Loader cum excavator mini type JCB 1 cum bucket size 5 1
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work are as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 1800.00 Lacs
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 1560.00 Lacs
(c) Executed in any one year, the following minimum quantities of work: - Earth Work 1,71,000.0 Cum @ At 2013-14 price level. Financial turn over and cost of complete work of previous years shall be given weightage of 5% per year based on Rs. value to bring item to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - Dozer (D-6 or equivalent) – 10 Nos 8 No. Tippers/Truck (10 tones) - 12 Nos Vibratory roller 8-10 tones - 8Nos Water Tanker(5000 liters) – 10 Nos Concrete mixer - 10 Nos Concrete Paver set complete 6 Nos Mechanical Trimmer 6 Nos Stationary Batching Plant 1 No JCB 6 No
(b) availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) liquid assets and/or availability of credit facilities of no less than Rs. 225.00 Lacs.
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in 4.5 (A)(b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = ( A*N*1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Restructuring & Modernisation of Distribution System of Bila Tank
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13 (a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 19.25 lakh (b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 4.81 Lakhs (c) Deleted (d) Xxxxxxx (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate: (a) Deleted (b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and (c) Liquid assets and/or availability of credit facilities, of not less than Rs. 4.81 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 2 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 150.00 lakh. (Usually not less than two times the estimated annual payment under the contract)
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 117.00 Lakh.
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 21000 Cum - Cement Concrete 1000 Cum (b) Deleted (e) Deleted @ At 2013-14 price level. Financial turn over and cost of complete work of previous years shall be given weightage of 5% per year based on Rs. value to bring item to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 01 Nos - 02 Nos 3 Tippers/Truck (10 tones) - 06 Nos 4 Water Tanker(5000 liters) - 04 Nos 6 Compaction Unit - 01 No 7 Concrete Mixer - 04 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 19.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre-qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work are as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 2722.00 lakh.
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 1815.00 Lakh. (usually not less than 80% of estimated value of contract);
(c) executed in any one year, the following minimum quantities of work: - Earthwork 188500 cum (@) at 2013-14 price level. Financial turnover and cost of completed works of previous years shall be given weightage of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Hydraulic Excavator ( 0.93 Cum Bucket Capacity Dozer (D-6 or equivalent) Tippers/Truck (10 tones) Vibratory roller 8-10 tones - 10 Nos - 08Nos. - 14 Nos - 08Nos Water Tanker(5000 liters) –12 Nos Concrete Mixer - 06 No.s Concrete Paver 12 Nos Trucks mounted concrete mixers/agitator - 08Nos Compaction Unit 06 Nos Stationary batching and mixing plant Mobile Self loading Weigh Batching and mixing - 01 No. and transportation of concrete in a mixture drum of 2.8 cum to deliver 2.0 cum concrete JCB - 04 No.s - 08 No.
(b) availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) liquid assets and/or availability of credit facilities of no less than Rs. 340.00 Lakhs. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in 4.5 (A)(b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = ( A*N*1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 196.00 Lacs.
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 105.00 Lacs. * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received.
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 23600 Cum - Cement Concrete 210 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 223.50 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 179.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 42100 Cum - Cement Concrete 1700 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 2 Tippers/Truck (10 tones) - 04 Nos 3 Water Tanker (5000 liters) - 04 Nos 4 Vibrator - 03 Nos 5 Compaction Unit - 01 Nos 6 Concrete Mixer - 03 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 28.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 129.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 103.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 16200 Cum - Cement Concrete 350 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 02 Nos - 02 Nos 3 Tippers/Truck (10 tones) - 04 Nos 4 Water Tanker(5000 liters) - 04 Nos 5 Vibrator - 02 Nos 6 Compaction Unit - 02 Nos 7 Concrete Mixer - 03 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 16.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 228.00 Lakhs
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 183.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: (d) Deleted (e) Deleted @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work:
1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - 04 Nos 2 Tippers/Truck (10 tones) -06 Nos 3 Dozer (D-6) - 04 No 4 Vibratory roller 8-10 tones -04 Nos 5 Water Tanker(5000 liters) – 06 Nos 6 Transit Mixture (4 cum) 04 Nos 7 Compaction Unit - 4 No 8 Plate Vibrator -4 Nos
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 29.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13 (a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 708.00 lakh (b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 472.00 Lakhs (c) Executed in any one year, the following minimum quantities of work: Earthwork 69350 cum Cement Concrete 4300 cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate: (a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: S. No. Item of equipment Requirement No. Capacity 1 Excavator 02 1.00 cum Capacity 2 Truck Dumper 06 4 cum Capacity 3 Concrete Mixer Xxxxxx 03 1 cement bag Capacity 4 Vibrator 03 1.5 HP Capacity 5 Water Tanker 06 5000 liter Capacity 6 Compaction unit 01 8 to 10 Ton Capacity Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
Appears in 1 contract
Samples: Civil Works Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 147.00
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 180.00 lakh
(b) Satisfactorily completed (not less than 50% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 90.00 Lakhs
(c) (c) Executed in any one year, the following minimum quantities of work: - Earthwork 13800 Cum (d) Deleted (e) Deleted - @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Capacity
1. J.C.B - 02 Nos.
2. Truck / Dumper - 04 Nos. 4 Cum each
3. Water Tanker - 02 Nos. 5000 ltr each
4. Concrete Mixer - 04 Nos. 1 cement bag each
5. Vibrator - 03 Nos. 1 HP each Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 22.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Renovation Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation of Chennaicontract, each bidder in its name should have in the bidder should immediately terminate services of the subcontractor.last five years: i.e. *
(ka) the proposed methodology and program achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability works only) of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesRs...
Appears in 1 contract
Samples: Project Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 68.50 lakh
(b) Satisfactorily completed (not less than 50% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 34.50 Lakhs (c) Deleted - @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Capacity
1. J.C.B - 02 Nos.
2. Truck / Dumper - 04 Nos. 4 Cum each 3. Water Tanker - 04 Nos. 5000 ltr each
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable); and
4.4 ‘Bids from Joint ventures are not acceptable’.
4.5 A. To qualify for award of the Corporation of Chennaicontract, each bidder in its name should have in the bidder should immediately terminate services of the subcontractor.last five years
(ka) the proposed methodology and program achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability works only) of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesRs. 65.10 Lakhs @
Appears in 1 contract
Samples: Procurement Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 129.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 103.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 16200 Cum - Cement Concrete 350 Cum (d) Deleted (e) Deleted @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 02 Nos - 02 Nos 3 Tippers/Truck (10 tones) - 04 Nos 4 Water Tanker(5000 liters) - 04 Nos 5 Vibrator - 02 Nos 6 Compaction Unit - 02 Nos 7 Concrete Mixer - 03 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 16.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years: i.e 2008 - 2013*
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of Chennaicivil engineering construction works only) of Rs 75 Lacs @ (usually not less than two times the estimated annual payments under the contract);
(b) satisfactorily completed (not less than 90% of contract value), as a prime contractor, at least one similar work of value not less than Rs 20 Lacs @ (usually not less than 80% of estimated value of contract);
(c) deleted;
(d) The contractor or his identified sub-contractor should possess required valid electrical license for executing the bidder building electrification works and should immediately terminate services of the subcontractorhave executed similar electrical works totalling Rupees @** in any one year.
(ke) The contractor or his identified sub-contractor should possess required valid license for executing the proposed methodology water supply/sanitary engineering works and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to should have executed similar water supply/sanitary engineering works totalling Rupees @** in any one year. * Specify the financial years; they should be adopted, justifying their capability of execution and completion those immediately preceding the financial year in which the bids are received. ** at least 50% of the work as estimated value of electrical/ water supply works. @ at 2012-13* price level. Financial turnover and cost of completed works of previous years shall be given weightage of 5% per technical specifications within the stipulated period of completion as per milestonesyear based on rupee value to bring them to 2012-13* price level.
4.4 Joint ventures4.5 B. Deleted.
Appears in 1 contract
Samples: Project Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation of Chennaicontract, each bidder in its name should have in the bidder should immediately terminate services of the subcontractor.last five years:
(ka) the proposed methodology and program achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability works only) of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesRs....
Appears in 1 contract
Samples: Invitation for Bid (Ifb)
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 199.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 160.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Cement concrete (including RCC and PSC) 1300 cum -
(d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Qty Capacity
1. Hydraulic Excavator 4 No. 10 cum 2. Concrete xxxxxx Mixer 4 Nos 3 to 5 cum 3. Power rolled compactor 2 No 8 Tonne
4. Truck / Dumper 4 Nos 8 cum 5. Water Tanker 4 Nos 6000 Ltr.
Appears in 1 contract
Samples: Restructuring and Modernizations of Balance Work of Khirawali Tank and It’s Canal System
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 345.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 275.50 Lakhs
(c) Executed in any one year, the following minimum quantities of work: Earthwork 46,350 cum Cement Concrete 2,350 cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: S. No. Item of equipment Requirement No. Capacity 1 Excavator 02 1.00 cum Capacity 2 Truck Dumper 06 4 cum Capacity 3 Concrete Mixer Xxxxxx 03 1 cement bag Capacity 4 Vibrator 03 1.5 HP Capacity 5 Water Tanker 06 5000 liter Capacity 6 Compaction unit 01 8 to 10 Ton Capacity Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 44.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Restructuring and Modernization of Distribution System of Kethan Tank
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five Five years;
(c) experience in works of a similar nature and size for each of the last five Five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five three years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control / assurance procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Joint venturesBids submitted by a joint venture is not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name and style should have in the last five years 2007-08,2008-09,2009-10, 2010-11, 2011-12: For Package 1
(a) Achieved, in at least two financial years in last Five years preceding 31/03/2012, a minimum annual financial turnover in civil engineering works Rs. 22 Lacs;
(b) Satisfactorily Constructed and completed (not less than 90% of contract value), as a prime contractor, (or as subcontractor duly certified by the employer/main contractor) at least one similar Civil Work value not less than Rs. 10 lacs.
(c) Executed in any one year, the following minimum quantities of work: Item:- Quantity Cement Concrete (including RCC & PCC) 90 Cu.M Coursed Masonary in Brick/Stone/Concrete pre cast bricks 70 Cu.M.
4.5 B. To qualify for award of the contract, each bidder in its name and style should have in the last five years 2007-08,2008-09,2009-10, 2010-11,2011-12: For Package 2
(a) Achieved, in at least two financial years in last Five years preceding 31/03/2012, a minimum annual financial turnover in civil engineering works Rs. 22 Lacs;
(b) Satisfactorily Constructed and completed (not less than 90% of contract value), as a prime contractor, (or as subcontractor duly certified by the employer/main contractor) at least one similar Civil Work value not less than Rs. 10 lacs.
(c) Executed in any one year, the following minimum quantities of work: Item:- Quantity Cement Concrete (including RCC & PCC) 90 Cu.M Coursed Masonary in Brick/Stone/Concrete pre cast bricks 70 Cu.M.
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesmilestones .
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre-qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 ‘Bids from Joint venturesventures are not acceptable’.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2002-03, 2003-04, 2004-05, 2005-06 and 2006-07
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs.57.00 million. @
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary. The proposed methodology should include program of construction backed with equipment planning and deployment duly supported with broad calculations and quality assurance procedures proposed to be adopted justifying their capability of execution and completion of work as per technical specifications, within stipulated period of completion.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all All bidders shall include the following information and documents with their bids in Section 2:.
(a) copies Copies of original documents defining the constitution or legal status, place of registration, registration under partnership or companies Act and principal place of business; , written power of attorney of the signatory of the Bid to commit the BidderBidder ;
(b) total Total monetary value of construction work performed for each of the last five yearsFive years ;
(c) experience Experience in works of a similar nature and size for each of the last five years, Five years and details of works under way underway or contractually committed; committed and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;.
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contractcontract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's ’s reports for the past five yearsFive years ;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (sline(s) of credit and availability of other financial resourcesresources facilities (10% of contract value) certified by the Bankers. (Not more than 3 months old);
(h) authority Undertaking that the bidder will be able to invest a minimum cash upto 25% of contract value of work during implementation of work;
(i) Authority to seek references from the Bidder's ’s bankers; - 9 - Signature of the Tenderer
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If Information regarding any of item of works found to be subcontracted and their performance not satisfied litigation, current or during the last five years, in which the opinion of the Corporation of ChennaiBidder is involved, the bidder should immediately terminate services of the subcontractor.parties concerned and disputed amount;
(k) Proposals for subcontracting components of the Works amounting to more than 10 percent of the Bid Price (for each, the qualifications and experience of the identified sub-contractor in the relevant field should be annexed); and
(l) The proposed methodology and program of construction including Environmental Management Planconstruction, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 (m) The unregistered contractor should have ISO 9001:2008 certified or equivalent. The certificate shall be provided as part of this document.
(n) Scanned copy of valid Electrical Contractor license of IE&L Department of Government of Maharashtra
4.3 Bids from Joint venturesventures are acceptable
1. Two or more contractors registered with Government of Maharashtra or unregistered contractor /individual /firm can form a Joint Venture (JV) to bid for the work subject to following conditions 2 The JV for the whole period of the contract work including defect liability period.
Appears in 1 contract
Samples: Construction Agreement
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary. The proposed methodology should include programme of construction backed with equipment planning and deployment duly supported with broad calculations and quality assurance procedures proposed to be adopted justifying their capability of execution and completion of work as per technical specifications, within stipulated period of completion.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all All bidders shall include the following information and documents with their bids in Section 2:.
(a) copies Copies of original documents defining the constitution or legal status, place of registration, registration under partnership or companies Act and principal place of business; , written power of attorney of the signatory of the Bid to commit the BidderBidder ;
(b) total Total monetary value of construction work performed for each of the last five yearsFive years ;
(c) experience Experience in works of a similar nature and size for each of the last five years, Five years and details of works under way underway or contractually committed; committed and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;.
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contractcontract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's ’s reports for the past five yearsFive years ;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (sline(s) of credit and availability of other financial resourcesresources facilities (10% of contract value) certified by the Bankers. (Not more than 3 months old);
(h) authority Undertaking that the bidder will be able to invest a minimum cash upto 25% of contract value of work during implementation of work;
(i) Authority to seek references from the Bidder's ’s bankers; - 9 - Signature of the Tenderer
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If Information regarding any of item of works found to be subcontracted and their performance not satisfied litigation, current or during the last five years, in which the opinion of the Corporation of ChennaiBidder is involved, the bidder should immediately terminate services of the subcontractor.parties concerned and disputed amount;
(k) Proposals for subcontracting components of the Works amounting to more than 10 percent of the Bid Price (for each, the qualifications and experience of the identified sub contractor in the relevant field should be annexed); and
(l) The proposed methodology and program programme of construction including Environmental Management Planconstruction, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 (m) The unregistered contractor should have ISO 9001:2008 certified or equivalent. The certificate shall be provided as part of this document.
4.3 Bids from Joint venturesventures are acceptable Tender by joint venture of two or more registered /unregistered contractors.
1. Two or more contractors registered with Government of Maharashtra or unregistered contractor /individual /firm can form a Joint Venture (JV) to bid for the work subject to following conditions 2 The JV for the whole period of the contract work including defect liability period.
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 127.50 Lacs. (usually not less than two times the estimated annual payments under the contract);
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 98.00 Lacs.(usually not less than 80% of estimated valve of contract) * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received.
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 20700 Cum - Cement Concrete 1150 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 02 Nos - 02 Nos 3 Tippers/Truck (10 tones) - 04 Nos 4 Water Tanker(5000 liters) - 04 Nos 6 Compaction Unit - 02 No 7 Concrete Mixer - 02 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 16.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 83.00 lakh
(b) Satisfactorily completed (not less than 50% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 42.00 Lakhs (c) Deleted - @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Capacity
1. J.C.B - 02 Nos.
2. Truck / Dumper - 04 Nos. 4 Cum each 3. Water Tanker - 04 Nos. 5000 ltr each
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2008-09 to 2012-13
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 193.00 lakh
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 128.50 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 30500 Cum - Cement Concrete 950 Cum (d) Deleted (e) Deleted @ At 2013-14 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 2 Tippers/Truck (10 tones) - 04 Nos 3 Water Tanker(5000 liters) - 04 Nos 4 Vibrator - 03 Nos 5 Compaction Unit - 01 Nos 6 Concrete Mixer - 03 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 24.50 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 97.00 lakh
(b) Satisfactorily completed (not less than 50% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 49.00 Lakhs (c) Deleted - @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: Capacity
1. J.C.B - 02 Nos.
2. Truck / Dumper - 04 Nos. 4 Cum each 3. Water Tanker - 04 Nos. 5000 ltr each
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre-qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e. 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs. 241.00 lakh. (Usually not less than two times the estimated annual payment under the contract)
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 192.00 Lakh.
(c) Executed in any one year, the following minimum quantities of work: - Earthwork 17500 Cum - Cement Concrete 1500 Cum * Specify the financial years; they should be those immediately preceding the financial year in which the bids are received.
(d) Deleted (e) Deleted
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work: 1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) 2 Dozer (D-6 or equivalent) - 02 Nos - 02 Nos 3 Tippers/Truck (10 tones) - 06 Nos 4 Water Tanker(5000 liters) - 06 Nos 6 Compaction Unit - 02 No 7 Concrete Mixer - 04 Nos Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule is shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 31.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work are as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2009-10 to 2013-14
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 554.58 Lakhs
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 222 Lakhs
(c) Executed in any one year, the following minimum quantities of work: - Eartwork 79475 cum @ At 2013-14price level. Financial turn over and cost of complete work of previous years shall be given weightage of 5% per year based on Rs. value to bring item to 2013-14 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work:
1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity - 04 Nos 3 Tippers/Truck (10 tones) - 08Nos 4 Vibratory roller 8-10 tones -04 Nos 5 Water Tanker(5000 liters) – 08 Nos 6 Concrete mixer - 06Nos 7 Batching plant - 01 No. (30 cum/hr) 8 Transit mixture 04 Nos 9 Paver Machine 2Nos 10 Vibrator 06 Nos (5 HP)
(b) availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) liquid assets and/or availability of credit facilities of no less than Rs. 69.50 Lacs.
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in 4.5 (A)(b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = ( A*N*1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified pre- qualified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies Copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total Total monetary value of construction work performed for each of the last five years;
(c) experience Experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major Major items of construction equipment proposed to carry out the Contract;
(e) qualifications Qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports Reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence Evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority Authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information Information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any Proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub- contracting is acceptable); and
(k) the The proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to be adopted, justifying their capability Capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestones.
4.4 Bids from Joint venturesventures are not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e 2007-08 to 2011-12.
(a) Achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil engineering construction works only) of Rs 204.00 Lakhs
(b) Satisfactorily completed (not less than 90% of contract value), as a prime contractor (or as sub contractor duly certified by the employer/main contractor), at least one similar work of value not less than Rs. 164.00 Lakhs
(c) Executed in any one year, the following minimum quantities of work: (d) Deleted (e) Deleted @ At 2012-13 price level Financial turn over and cost of completed work of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2012-13 price level.
4.5 B. Each bidder should further demonstrate:
(a) Availability (either owned or leased or by procurement against mobilization advances) of the following key and critical equipment for this work:
1 Hydraulic Excavator ( 0.93 Cum Bucket Capacity) - 04 Nos 2 Tippers/Truck (10 tones) -06 Nos 3 Dozer (D-6) - 02 No 4 Vibratory roller 8-10 tones -02 Nos 5 Water Tanker(5000 liters) – 06 Nos 6 Transit Mixture (4 cum) 03 Nos 7 Compaction Unit - 4 No
(b) Availability for this work of a Project Manager with no less than five years' experience in construction of similar civil engineering works and other key personnel with adequate experience as required; and
(c) Liquid assets and/or availability of credit facilities, of not less than Rs. 26.00 Lakhs in the format given in Section-2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB. The bidder must demonstrate having experience and resources sufficient to meet the aggregate of the qualifying criteria for the individual contracts
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder’s compliance with the qualifying criteria except to the extent stated in 4.5 (A) (b) above.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A * N * 1.5 - B )
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
Appears in 1 contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five Five years;
(c) experience in works of a similar nature and size for each of the last five Five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five three years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Bid Price (for each, the qualifications and their performance not satisfied experience of the identified sub-contractor in the opinion relevant field should be annexed; no vertical splitting of the Corporation of Chennai, the bidder should immediately terminate services of the subcontractor.work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan, backed with equipment equipment, materials and manpower planning and deployment, duly supported with broad calculations and quality control / assurance procedures proposed to be adopted, justifying their capability of execution and completion of the work as per technical specifications within the stipulated period of completion as per milestonesmilestones .
4.4 Joint venturesBids submitted by a joint venture is not acceptable.
4.5 A. To qualify for award of the contract, each bidder in its name and style should have in the last five years 2006-07,2007-08,2008-09,2009-10, 2010-11*:
(a) Achieved, in at least two financial years in last Five years preceding 31/03/2012, a minimum annual financial turnover in civil engineering works Rs. 100 Lacs;
(b) Satisfactorily Constructed and completed (not less than 90% of contract value), as a prime contractor, (or as subcontractor duly certified by the employer/main contractor) at least one similar Civil Work of value not less than Rs. 40 lacs.
(c) Executed in any one year, the following minimum quantities of work: Item:- Quantity Cement Concrete (including RCC & PCC) 425 Cu.M Coursed Masonary in Brick/Stone/Concrete pre cast bricks 350 Cu.M. (*2011-2012 price level. Financial turnover and cost of completed works of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2011-12 price level.)
4.5 B. Each bidder should further demonstrate: Contract Package – Construction and establishment of Research Center at XXXX Foundation
(a) Availability (either owned or leased or by procurement) of the following key and critical equipment for this work: -Concrete Mixture – 2 No. -Vibrator – 1 No. Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the completion of works in accordance with the prescribed construction schedule are shown in the above list. The bidders should, however, undertake their own studies and furnish with their bid, a detailed construction planning and methodology supported with layout and necessary drawings and calculations (detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals. The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with the cycle time for each operation for the given production capacity to match the requirements.
(b) Availability for this work of following Key persons: Project Manager – A Graduate in Civil Engineering with not less than 15 years‘ experience in construction of similar civil engineering works and other key personnel with adequate experience as required, and
(c) Liquid assets and/or availability of credit facilities of not less than Rs 15 lacs in the format given in Section 2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement etc.)
Appears in 1 contract
Samples: Construction Contract
Qualification of the Bidder. 4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders will be considered for award for Contract. These qualified bidders should submit with their bids any information updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted prequalification information remains essentially correct as of date of bid submission. The update or confirmation should be provided in Section 2.
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under way or contractually committed; and clients who may be contacted for further information on those contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of other financial resources);
(h) authority to seek references from the Bidder's bankers; - 9 - Signature of the Tenderer;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the last five years or currently under execution. The information shall include the names of the parties concerned, the disputed amount, cause of litigation, and matter in dispute;; and
(j) If any proposals for subcontracting components of item the Works which in aggregate add to more than 20 percent of works found to be subcontracted the Contract Price [for each, the qualifications and their performance not satisfied experience of the identified sub- contractor in the opinion relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable].
4.4 Bids from Joint ventures are not acceptable.
4.5 A. To qualify for award of the Corporation contract, each bidder in its name should have in the last five years: i.e 2007-2012*
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of Chennaicivil engineering construction works only) of Rs 2,00,00000/-.
(b) satisfactorily completed (not less than 90% of contract value), as a prime contractor, at least one similar work of value not less than Rs. 35,00000/-.
(c) deleted;
(d) The contractor or his identified sub-contractor should possess required valid electrical license for executing the building electrification works and should have executed similar electrical works totaling Rupees Rs 300000/-.@** in any one year.
(e) The contractor or his identified sub-contractor should possess required valid license for executing the water supply/sanitary engineering works and should have executed similar water supply/sanitary engineering works totaling Rupees Rs 300000/-@** in any one year. @ at 2013-14*price level. Financial turnover and cost of completed works of previous years shall be given weight age of 5% per year based on rupee value to bring them to 2013-14* price level.
4.5 B. Deleted.
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder should immediately terminate services must demonstrate having experience and resources sufficient to meet the aggregate of the subcontractorqualifying criteria for the individual contracts.
4.6 Sub-contractors' experience and resources shall not be taken into account in determining the bidder's compliance with the qualifying criteria except to the extent stated in para 4.5 (kA) above.
4.7 Bidders who meet the proposed methodology and program of construction including Environmental Management Plan, backed with equipment planning and deployment, duly supported with broad calculations and quality control procedures proposed to minimum qualification criteria will be adopted, justifying qualified only if their capability of execution and completion of available bid capacity is more than the work total bid value. The available bid capacity will be calculated as per technical specifications within the stipulated period of completion as per milestones
4.4 Joint venturesunder: Assessed Available Bid capacity = ( A*N*1.5 - B )
Appears in 1 contract
Samples: Project Agreement