Request for Equitable Adjustment Sample Clauses

Request for Equitable Adjustment. Design-Builder shall provide Owner with written notice, in accordance with Section 8.6.2, of any event that Design-Builder believes entitles it to an equitable adjustment in the Contract Sum and/or Guaranteed Completion Date(s) within fourteen
AutoNDA by SimpleDocs
Request for Equitable Adjustment. 12.3.1 If the Contractor considers a Request for Equitable Adjustment is justified for an increase in the Contract Time or Contract Sum, the Contractor shall promptly, upon first observance of the condition giving rise to the request, provide the Project Manager and County written notice of such condition and circumstance. This notice shall be given by the Contractor before proceeding to execute the Work, except in emergency endangering life or property in which case the Contractor shall proceed in accordance with Paragraph 10.3. No such request shall be valid unless so made. Any change in the Contract Time or Contract Sum resulting from such request for equitable adjustment shall be authorized by Change Order. 12.3.2 If the Contractor requests that additional cost or time is involved because of, but not limited to, (1) any written interpretation pursuant to Subparagraph 2.2.8, (2) any order by the County to stop the Work pursuant to Paragraph 3.3 where the Contractor was not at fault, or any such order by the Project Manager as the County’s agent, (3) any written order for a minor change in the Work issued pursuant to Paragraph 12.4, the Contractor shall make such request for equitable adjustment as provided in Subparagraph 12.3.1.
Request for Equitable Adjustment. Design-Builder shall provide Owner with written notice, in accordance with Section 8.6.2, of any event that Design-Builder believes entitles it to an equitable adjustment in the Contract Sum and/or Guaranteed Completion Date(s) within fourteen (14) days of the occurrence of the event giving rise to the request. For purposes of this part, “occurrence” means when Design-Builder knew, or in its diligent prosecution of the Work should have known, of the event giving rise to the request. If Design-Builder believes it is entitled to an adjustment in the Contract Sum, Design-Builder shall immediately notify Owner and begin to keep and maintain complete, accurate, and specific daily records. Design-Builder shall give Owner access to any such records and, if requested shall promptly furnish copies of
Request for Equitable Adjustment. Design-Builder shall provide Owner with written notice, in accordance with Section 8.6.2, of any event that Design-Builder believes entitles it to an equitable adjustment in the Contract Sum and/or Guaranteed Completion Date(s) within fourteen (14) days of the occurrence of the event giving rise to the request. For purposes of this part, “occurrence” means when Design-Builder knew, or in its diligent prosecution of the Work should have known, of the event giving rise to the request. If Design-Builder believes it is and begin to keep and maintain complete, accurate, and specific daily records. Design-Builder shall give Owner access to any such records and, if requested shall promptly furnish copies of such records to Owner.
Request for Equitable Adjustment. The amount of any request for equitable adjustment (‘REA’) to the terms of the Order shall accurately and fairly reflect the adjustment for which Seller believes Buyer is liable. The request shall include only costs for performing the change, and shall not include any costs that already have been reimbursed or that have been separately claimed. All indirect costs included in the request shall be properly allocable to the change in accordance with applicable acquisition regulations and Seller’s approved cost accounting system. The REA shall include all relevant data, including actual cost data and data supporting estimated costs

Related to Request for Equitable Adjustment

  • Equitable Adjustment Trading volume amounts, price/volume amounts and similar figures in the Transaction Documents shall be equitably adjusted (but without duplication) to offset the effect of stock splits, similar events and as otherwise described in this Agreement and Warrants.

  • Equitable Adjustments (1) If the Contracting Officer confirms that Government conduct effected a change as alleged by the Contractor, and the conduct causes an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the work under this contract, whether changed or not changed by such conduct, an equitable adjustment shall be made-- (i) In the contract price or delivery schedule or both; and (ii) In such other provisions of the contract as may be affected. (2) The contract shall be modified in writing accordingly. In the case of drawings, designs or specifications which are defective and for which the Government is responsible, the equitable adjustment shall include the cost and time extension for delay reasonably incurred by the Contractor in attempting to comply with the defective drawings, designs or specifications before the Contractor identified, or reasonably should have identified, such defect. When the cost of property made obsolete or excess as a result of a change confirmed by the Contracting Officer under this clause is included in the equitable adjustment, the Contracting Officer shall have the right to prescribe the manner of disposition of the property. The equitable adjustment shall not include increased costs or time extensions for delay resulting from the Contractor's failure to provide notice or to continue performance as provided, respectively, in (b) and (c) above.

  • Equitable Adjustments to Prices Whenever any provision of this Indenture requires the Company to calculate the average of the Last Reported Sale Prices, or any function thereof, over a period of multiple days (including to calculate the Stock Price or an adjustment to the Conversion Rate), or to calculate Daily VWAPs over an Observation Period, the Company will make proportionate adjustments, if any, to such calculations to account for any adjustment to the Conversion Rate pursuant to Section 5.05(A)(i) that becomes effective, or any event requiring such an adjustment to the Conversion Rate where the Ex-Dividend Date or effective date, as applicable, of such event occurs, at any time during such period or Observation Period, as applicable.

  • Fee Adjustment Fees as provided in this Agreement to be charged to residents of Joplin and the City pursuant to this Agreement may be adjusted based upon the AARC's change in costs subsequent to the previous adjustment. Any individual fee increases will be adjusted only to the extent of an increase in the Consumer Price Index (St. Louis -All Urban Consumers), utilizing the December 12 month period index from the previous year. If a fee increase request is in excess of the Consumer Price Index the city may request to review data on actual costs of each service if needed to document cost increases. In the event an adjustment to documented cost is warranted, AARC shall provide written notice thereof with supporting documentation, by no later than May 1 of each year. All increases shall be subject to annual appropriation by the Joplin City Council. City shall have thirty (30) days to review and request additional supporting documentation. In the event the parties are unable to agree to the cost adjustment, either party shall be entitled to terminate this Agreement as provided herein.

  • Performance Adjustment Rate Except as otherwise provided in sub-paragraph (e) of this paragraph 3, the Performance Adjustment Rate is 0.02% for each percentage point (the performance of the Portfolio and the Index each being calculated to the nearest .01%) that the Portfolio's investment performance for the performance period was better or worse than the record of the Index as then constituted. The maximum performance adjustment rate is 0.20%. For purposes of calculating the performance adjustment of the portfolio, the portfolio's investment performance will be based on the performance of the retail class. The performance period will commence with the first day of the first full month following the retail class's commencement of operations. During the first eleven months of the performance period for the retail class, there will be no performance adjustment. Starting with the twelfth month of the performance period, the performance adjustment will take effect. Following the twelfth month a new month will be added to the performance period until the performance period equals 36 months. Thereafter the performance period will consist of the current month plus the previous 35 months. The Portfolio's investment performance will be measured by comparing (i) the opening net asset value of one share of the retail class of the Portfolio on the first business day of the performance period with (ii) the closing net asset value of one share of the retail class of the Portfolio as of the last business day of such period. In computing the investment performance of the retail class of the Portfolio and the investment record of the Index, distributions of realized capital gains, the value of capital gains taxes per share paid or payable on undistributed realized long-term capital gains accumulated to the end of such period and dividends paid out of investment income on the part of the Portfolio, and all cash distributions of the securities included in the Index, will be treated as reinvested in accordance with Rule 205-1 or any other applicable rules under the Investment Advisers Act of 1940, as the same from time to time may be amended.

  • Determination of Adjustments If any questions will at any time arise with respect to the Exercise Price or any adjustment provided for in Section 4.8, such questions will be conclusively determined by the Company’s Auditors, or, if they decline to so act any other firm of certified public accountants in the United States of America that the Company may designate and who will have access to all appropriate records and such determination will be binding upon the Company and the Holders of the Warrants.

  • Determination of One-Month LIBOR Pursuant to the terms of the Global Agency Agreement, the Global Agent shall calculate the Class Coupons for the applicable Classes of Notes (including MAC Notes on which the Exchange Administrator has directed the Global Agent to make payments) for each Accrual Period (after the first Accrual Period) on the applicable LIBOR Adjustment Date. U.S. dollar deposits with a maturity of one month set by ICE Benchmark Administration Limited (“ICE”) as of 11:00 a.m. (London time) on the LIBOR Adjustment Date (the “ICE Method”). ICE’s Interest Settlement Rates are currently displayed on Bloomberg L.P.’s page “BBAM.” That page, or any other page that may replace page BBAM on that service or any other service that ICE nominates as the information vendor to display the ICE’s Interest Settlement Rates for deposits in U.S. dollars, is a “Designated Page.” ICE’s Interest Settlement Rates currently are rounded to five decimal places. If ICE’s Interest Settlement Rate does not appear on the Designated Page as of 11:00 a.m. (London time) on a LIBOR Adjustment Date, or if the Designated Page is not then available, One-Month LIBOR for that date will be the most recently published Interest Settlement Rate. If ICE no longer sets an Interest Settlement Rate, Xxxxxxx Mac will designate an alternative index that has performed, or that Xxxxxxx Mac (or its agent) expects to perform, in a manner substantially similar to ICE’s Interest Settlement Rate.

  • Fee Adjustments The fixed fees and other fees expressed as stated dollar amounts in this Schedule C and in this Agreement are subject to annual increases, commencing on the one-year anniversary date of the date of this Agreement, in an amount equal to the percentage increase in consumer prices for services as measured by the United States Consumer Price Index entitled “All Services Less Rent of Shelter,” or a similar index should such index no longer be published, since such one-year anniversary or since the date of the last fee increase, as applicable.

  • Rate Redetermination for Market Change In the event of delay or interruption, exceeding 90 days, under B8.33, Contracting Officer shall make an appraisal to determine for each species the difference between the appraised unit value of Included Timber immediately prior to the delay or interruption and the appraised unit value of Included Timber immediately after the delay or interruption. The appraisal shall be done after any rate redetermination done pursuant to B3.31, using remaining volumes.

  • Performance Adjustment One-twelfth of the annual Performance Adjustment Rate will be applied to the average of the net assets of the Portfolio (computed in the manner set forth in the Fund's Declaration of Trust or other organizational document) determined as of the close of business on each business day throughout the month and the performance period.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!