Requests for Information. The Grantee shall fully and promptly comply with all reporting requirements and requests for information issued by the Department or its authorized designee. The Grantee shall provide such information in the format requested by the Department. The Grantee shall ensure that its staff, interns, volunteers, and subcontractors comply in a timely and complete manner with all the Department’s requests for information. The Grantee shall comply in a timely manner with requests by the Department or its authorized designee for financial information, records, and documents related to evaluating costs of programs and ser vices provided by the Grantee’s probation department. The Grantee shall timely submit any files or records of the Grantee’s juvenile probation department, or any facility or program operated by or under the authority of the Grantee, requested by the Department or its authorized designee as a part of the monitoring, auditing, or investigatory process.
Requests for Information. 18.1 Any Request for Information shall reference all applicable Contract Document(s), including Specification section(s), detail(s), page number(s), drawing number(s), and sheet number(s), etc. Developer shall make suggestions and interpretations of the issue raised by each Request for Information. A Request for Information cannot modify the Guaranteed Maximum Price, Contract Time, or the Contract Documents.
18.2 Developer may be responsible for any costs incurred for professional services that District may deduct from any amounts owing to Developer, if a Request for Information requests an interpretation or decision of a matter where the information sought is equally available to the party making the request. District may deduct from and/or invoice Developer for professional services arising therefrom.
Requests for Information. Grantor may request, and Grantee shall supply, upon request, necessary information and documentation regarding transactions constituting contractual (whether a written contract exists or not) or other relationships, paid for with funds received hereunder. Documentation may include, but is not limited to, information regarding Grantee’s contractual agreements, identity of employees, shareholders and directors of Grantee and any party providing services which will or may be paid for with funds received hereunder, including, but not limited to, management and consulting services rendered to Grantee.
Requests for Information. DHS may request, and Provider shall supply, upon request, necessary information and documentation regarding transactions constituting contractual (whether a written contract is in existence or not) or other relationships, paid for with funds received hereunder. Documentation may include, but is not limited to, information regarding Provider’s contractual agreements, identity of employees, shareholders and directors of Provider and any party providing services which will or may be paid for with funds received hereunder, including, but not limited to, management and consulting services rendered to Provider.
Requests for Information. Manager shall respond, with reasonable promptness, to any information requests by Owner's Leasehold Mortgagee in accordance with Owner's Mortgage Documents, to the extent such information is required to be furnished by Manager to Owner pursuant to this Agreement. Any additional information or reports requested by Owner's Leasehold Mortgagee shall be provided by Manager only if Owner so directs Manager in writing and, to the extent such information or reports are not being prepared for Owner in the ordinary course of business pursuant to this Agreement, Owner agrees to pay the reasonable expenses of preparing such information and reports;
Requests for Information. 18.1. Any Request for Information (“RFI”) shall reference all applicable Contract Document(s), including Specification section(s), detail(s), page number(s), drawing number(s), and sheet number(s), etc. The Contractor shall make suggestions and interpretations of the issue raised by each Request for Information. A Request for Information cannot modify the Guaranteed Project Cost, Contract Time, or the Contract Documents.
18.2. The Contractor shall be responsible for any costs incurred for professional services that District may deduct from any amounts owing to the Contractor, if Contractor makes multiple Requests for Information that request interpretation(s) or decision(s) of a matter where the information sought is equally available to the Contractor. District, at its sole discretion, shall deduct from and/or invoice Contractor for all the professional services arising herein.
18.3. Requests for Information shall comply with all requirements of the Contract Documents.
18.4. Prior to submitting the RFI, Contractor shall diligently review the Contract Documents for information responsive to the RFI, including information incorporated by reference. Contractor should not issue an RFI regarding information contained in or inferable from the Contract Documents, including information incorporated by reference. An RFI is invalid if the RFI response is contained in or inferable from the Contract Documents.
18.5. Contractor shall be responsible for preparing and submitting each RFI so as to not cause delay to the progress of the Work nor to cause any impact to the Contractor’s labor productivity. An RFI may be considered untimely if not submitted within Forty Eight (48) hours of receipt from a Contractor’s subcontractor. Untimely submission of any RFI will preclude Contractor from asserting any claims for delay or for labor impact against the District.
18.6. If the Contractor fails to timely notify the Architect in writing of any Conditions encountered and the Contractor proceeds to perform any portion of the Work containing or affected by such Conditions the Contractor shall bear all costs associated with or required to correct, remove, or otherwise remedy any portion of the Work affected thereby without adjustment of the Contract Time or the Contract Price. In requesting information of the District to address and resolve any conditions, the Contractor shall act with promptness in submitting any written request so as to allow the District a reasonable period of t...
Requests for Information. The Borrowers shall furnish to the Lender within five (5) Business Days after the Lender’s request, any information, documents, records or reports with respect to the servicing or subservicing of the Collateral, any Borrower Party’s or Subservicer’s business or its relationship with any Agency, as the Lender may from time to time reasonably request.
Requests for Information. Chase will provide all required information in a timely fashion in support of regulatory filings.
Requests for Information. In order to fulfill its responsibilities as the exclusive representative of classified employees, the Association will be provided upon request two (2) copies of any current published District report including the tentative and adopted budgets, public records, and other materials pertaining to matters of collective bargaining.
Requests for Information a. Construction Manager shall submit requests for information using the Project Management Software.
b. Architect shall answer requests for information via the Project Management Software. Requests for Information responses that have cost impact will have corresponding Change Order Bulletin (Form SC 6.311) issued by the Architect/ Engineer.