REQUESTS FOR PAYMENT. The Contractor may submit to the Owner periodically, but not more than once each month, a Request for Payment for work done and materials delivered to and stored on the site. The Contractor shall furnish the Owner all reasonable information required for obtaining the necessary data relative to the progress and execution of the work. Payment for materials stored on the site will be conditioned upon evidence submitted to establish the Owner's title to such materials. Each Request for Payment shall be computed on the basis of work completed on all items listed in the Detailed Breakdown of Contract (or on unit prices, as the case may be), less previous payments.