Restrictions on Change of Scope Sample Clauses
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 km 60.900 of old NH-40) to NH-106 (old NH-44E), (Package-II) km 12+800 to km 24+700 under SARDP-NE ‘Phase A’ in the State of Meghalaya on EPC Mode
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
Restrictions on Change of Scope. 11.4.1 No Change of Scope shall be executed unless the RSCL has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
11.4.2 Change made because of any default of the Contractor in the performance of its obligations under this Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. Rangagara to Kaliabor Tiniali of NH-37 (Old) from Km 297+000 to Km 315+315 (18.315 Km), under SARDP-NE, under EPC Mode at the Risk and Cost of EPC Contractor-2nd Call
(i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligationsunderthisAgreement,thesameshallnotbedeemedtobeChangeofScope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. 13.4.1 No Change of Scope shall be executed unless the Authority/GMDA has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10 (ten) per cent of the Contract Price.
13.4.3 Notwithstanding anything to the contrary in this Article 13, no change made necessary because of any default of the Contractor in the performance of its obligations under this Agreement shall be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Page 83 of 146 (Km 47.075 to Km 77.055) on EPC Mode through ADB Loan assistance
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope km 606+300 of NH-37 on existing Lahoal – Chabua Bypass i.e. Borborua Junction – Kandulibari Grant Gaon section in the State of Assam on EPC mode.
(i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. Widening/Improvement to 4 (Four) Lane with Paved Shoulder from KM 131+500 to Km 146+250 (Design Chainage 131+152 to 145+712) of Manja – Dillai Section (Package-7) of NH 29 in the state of Assam on EPC mode
(i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.