Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Restrictions on Change of Scope. 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10 (ten) per cent of the Contract Price.
13.4.3 Notwithstanding anything to the contrary in this Article 13, no change made necessary because of any default of the Contractor in the performance of its obligations under this Agreement shall be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. 11.4.1 No Change of Scope shall be executed unless the RSCL has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Drafit Concession AgreementPage 83 of 145 Restoration & Rehabilitation of Road from Km 21.00 to Km 28.00 on NH-4 (old NH-233) in the Union Territory of Andaman & Nicobar Islands in the FY 2022-23 on EPC Basis Jun. 2022 (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule. 13.5
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Draft Contract AgreementPage 80 of 142 Construction & Up gradation to 2 lane with paved shoulder from Design Km. 31.449 to Km 51.700 of Khellani-Khanabal Section on NH-244 (Pkg-I) Nov 2020 (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule. 13.5
Restrictions on Change of Scope. Widening/Improvement to 4 (Four) Lane with Paved Shoulder from KM 131+500 to Km 146+250 (Design Chainage 131+152 to 145+712) of Manja – Dillai Section (Package-7) of NH 29 in the state of Assam on EPC mode
(i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. Draft Contract AgreementPage 85 of 150 Rehabilitation and Up-gradation to 2 lane with Paved shoulder of NH-717A in Ranipool-Pakyong section from Design CH: 2.00 to CH: 6.00 (Km 3.100 to Km 7.200 of NH-717A) in the State of Sikkim on EPC Mode Feb. 2021 (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule. 13.5
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract Agreement floating material for providing floating Terminal facilities at various locations on NW – 2 (Brahmaputra River) on EPC mode Sept, 2021
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. Draft Contract AgreementPage 84 of 261 S-D Tunnel 2022 (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule. 13.5