Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency. (ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price. (iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 89 contracts
Samples: Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement, Construction Contract
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 37 contracts
Samples: Engineering, Procurement and Construction Agreement, Draft Contract Agreement, Construction Contract
Restrictions on Change of Scope.
(i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 14 contracts
Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement, Engineering Procurement and Construction Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated because of arising from any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 13 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 1025% (ten twenty five per cent) of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated because of arising from any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 8 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Epc Agreement, Epc Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority Employer has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 5 contracts
Samples: Engineering, Procurement and Construction Agreement, Epc Agreement, Epc Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall andshall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 5 contracts
Samples: Construction Contract, Contract Agreement, Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.. Page 92 of 158
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 3 contracts
Samples: Contract Agreement, Contract Agreement, Contract Agreement
Restrictions on Change of Scope. (i) 14.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 14.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) 14.4.3 Notwithstanding anything to the contrary in this Article 1314, if any no change is necessitated because of arising from any default of the Contractor Concessionaire in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 2 contracts
Samples: Concession Agreement, Concession Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 1020% (ten per cent) of the Contract Bid Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated because of arising from any default of the Contractor in the performance of its obligations under this Agreement, the same Contract Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Bid Price or the Project Completion ScheduleCommissioning Scheduled.
Appears in 2 contracts
Samples: Draft Contract Agreement, Contract Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority Employer has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 15 (ten Fifteen) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 2 contracts
Samples: Epc Agreement, Epc Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.. Page 83 of 146
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 2 contracts
Samples: Contract Agreement, Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if 13,if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 1025% (ten twenty five per cent) of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated because of arising from any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Engineering, Procurement and Construction (Epc) Agreement
Restrictions on Change of Scope. (i) 13.4.1 No Change of Scope shall be executed unless the Authority Authority/GMDA has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.of
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.. Page 92 of 159
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Restrictions on Change of Scope. (i)
13.4.1 No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Construction Contract
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated necessitat- ed because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result re- xxxx in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Construction Contract
Restrictions on Change of Scope. (i)
13.4.1 No Change of Scope shall be executed unless the Authority Employer has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2 Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3 Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Demonstration Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of ScopeobligationsunderthisAgreement,thesameshallnotbedeemedtobeChangeofScope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Contract Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything Not with standing any thing to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor Contract or in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Construction Contract
Restrictions on Change of Scope. (i) 13.4.1. No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The 13.4.2. Unless the Parties mutually agree to the contrary, the total value of all Change of Scope Orders shall not exceed 10% 10 (ten ten) per cent) cent of the Contract Price.
(iii) 13.4.3. Notwithstanding anything to the contrary in this Article 13, if any no change is necessitated made necessary because of any default of the Contractor in the performance of its obligations under this Agreement, the same Agreement shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Epc Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per centpercent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be a Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
Restrictions on Change of Scope. (i) No Change of Scope shall be executed unless the Authority has issued the Change of Scope Order save and except any Works necessary for meeting any Emergency.. P a g e | 76
(ii) The total value of all Change of Scope Orders shall not exceed 10% (ten per cent) of the Contract Price.
(iii) Notwithstanding anything to the contrary in this Article 13, if any change is necessitated because of any default of the Contractor in the performance of its obligations under this Agreement, the same shall not be deemed to be Change of Scope, and shall not result in any adjustment of the Contract Price or the Project Completion Schedule.
Appears in 1 contract