Common use of Resumption of Work Clause in Contracts

Resumption of Work. After the permission or instruction to proceed is given, the Contractor and the Engineer shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

Appears in 3 contracts

Samples: Contract Agreement, Contract Agreement, Contract Agreement

AutoNDA by SimpleDocs

Resumption of Work. After the permission or instruction to proceed is given, the Contractor and the Engineer Parties shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

Appears in 2 contracts

Samples: Contract Agreement (Renewable Fuel Corp), Contract Agreement (Renewable Fuel Corp)

Resumption of Work. After the permission or instruction to proceed is given, the Contractor and the Engineer shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspensionsuspension after receiving from the Engineer an instruction to this effect under Clause 13 [Variations and Adjustments].

Appears in 2 contracts

Samples: Unit Price Contract, Unit Price Contract

Resumption of Work. After the permission or instruction to proceed is given, the Contractor and the Engineer Project Manager shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

Appears in 1 contract

Samples: Contract for Design and Construction

AutoNDA by SimpleDocs

Resumption of Work. After the permission or instruction to proceed is given, the Contractor and the Engineer parties shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension.

Appears in 1 contract

Samples: Conditions of Contract

Resumption of Work. After the receipt of permission or of an instruction to proceed is givenproceed, the Contractor shall, after notice to the Engineer, and together with the Engineer shall jointly Engineer, examine the Works and the Plant Works, Plant, Rolling Stock and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Works, Plant, Rolling Stock and Materials, which has occurred during the suspension.9 Employer's Taking Over Taking Over Certificate

Appears in 1 contract

Samples: General Conditions of Contract